6450 N LONGRIDGE AVE 91401
Certificate Information: 6450 N LONGRIDGE AVE 91401
- Application / Permit
- 23010-20000-01140
- Plan Check / Job No.
- B23VN03471
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 33'-10" X 22'-6" TWO STORY SINGLE FAMILY DWELLING PER SB9; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 10/12/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/23/2023 | SELLA BENYAMIN |
| Corrections Issued | 3/30/2023 | SELLA BENYAMIN |
| Quality Review Completed | 3/31/2023 | STEVEN KIM |
| Building Plans Picked Up | 4/7/2023 | APPLICANT |
| Plan Check Approved | 10/12/2023 | SELLA BENYAMIN |
| Issued | 10/12/2023 | APPLICANT |
| CofO in Progress | 3/18/2024 | JOSE AVILA |
| Permit Finaled | 5/14/2024 | RUBEN SALAS |
| CofO Issued | 5/14/2024 | RUBEN SALAS |
| Permit Finaled | 5/14/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/15/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/17/2023 | CARLOS AGUILERA |
| Senate Bill 9 | Cleared | 5/3/2023 | STEVEN WECHSLER |
| Low Impact Development (LID) | Cleared | 5/9/2023 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 5/9/2023 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 5/24/2023 | NICHOLAS AYARS |
| Construction near power lines | Cleared | 9/26/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Andrejic,, Milos; Lic. No.: C67443 | 3601 BEVERLY RIDGE DR SHERMAN OAKS, CA 91423 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/23/2023 | Not Ready for Inspection | KIRK SANDERS |
| Underground Mechanical | 10/23/2023 | Partial Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 10/26/2023 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2023 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2023 | Partial Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 11/29/2023 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 11/29/2023 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2023 | Partial Approval | KIRK SANDERS |
| Green Building Rough | 11/29/2023 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Rough | 11/29/2023 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 11/29/2023 | Approved | KIRK SANDERS |
| Verify Sprinkler Sign Off | 11/29/2023 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 12/7/2023 | Approved | JOSE AVILA |
| Shower Pan | 12/7/2023 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 12/11/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 12/11/2023 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 12/11/2023 | Approved | JOSE AVILA |
| Insulation | 12/13/2023 | Approved | JOSE AVILA |
| Drywall Nailing | 12/15/2023 | Corrections Issued | JOSE AVILA |
| Interior/Exterior Lathing | 12/15/2023 | Approved | JOSE AVILA |
| Drywall Nailing | 12/20/2023 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 12/21/2023 | Approved | JOSE AVILA |
| Sewer | 1/5/2024 | Approved | KIRK SANDERS |
| Underground Mechanical | 1/5/2024 | Partial Approval | KIRK SANDERS |
| Underground Mechanical | 1/8/2024 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 1/26/2024 | SGSOV Not Ready | CRAIG DAVIS |
| BUILDING-Rough-Frame | 2/6/2024 | Approved | JOSE AVILA |
| Green Building Final | 2/6/2024 | Approved | JOSE AVILA |
| Green Building Rough | 2/6/2024 | Approved | JOSE AVILA |
| HVAC-Rough | 2/6/2024 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 2/6/2024 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 2/6/2024 | SGSOV Not Required | JOSE AVILA |
| Smoke Detectors | 2/6/2024 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 2/22/2024 | Approved | JOSE AVILA |
| HVAC-Final | 2/22/2024 | Approved | JOSE AVILA |
| PLUMBING-Final | 2/22/2024 | Approved | JOSE AVILA |
| Service/Power Release | 2/22/2024 | Approved | JOSE AVILA |
| Final | 3/15/2024 | OK to Issue CofO | JOSE AVILA |