2383 N MANDEVILLE CANYON ROAD 90049
Certificate Information: 2383 N MANDEVILLE CANYON ROAD 90049
- Application / Permit
- 23010-20000-01124
- Plan Check / Job No.
- B23VN03408
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- NEW DETACHED 1-STORY (70'-1"x68'-8"), 1323 SQFT ACCESSORY LIVING QUARTERS W/ATTACHED PATIO COVERS (1072) W/NFPA 13R SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 12/28/2023
- Issuing Office
- Valley
- Current Status
- Issued on 12/28/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/23/2023 | PETER MOSESIAN |
| Corrections Issued | 3/31/2023 | PETER MOSESIAN |
| Quality Review Completed | 3/31/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 4/20/2023 | APPLICANT |
| Plan Check Approved | 12/19/2023 | PETER MOSESIAN |
| Issued | 12/28/2023 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 6/21/2023 | DARIN LAM |
| BHO/Hillside ordinance | Cleared | 6/21/2023 | DARIN LAM |
| BHO/Hillside ordinance | Cleared | 6/21/2023 | DARIN LAM |
| BHO/Hillside ordinance | Cleared | 6/21/2023 | DARIN LAM |
| BHO/Hillside ordinance | Cleared | 6/21/2023 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 6/21/2023 | DARIN LAM |
| ZA Case | Cleared | 6/27/2023 | ASHLEY RODARTE |
| ZA Case | Cleared | 6/27/2023 | ASHLEY RODARTE |
| Watercourse | Cleared | 6/28/2023 | HISASHI KOBAYAKAWA |
| Hydrant and Access approval | Cleared | 10/4/2023 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 11/8/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 11/13/2023 | ANTHONY MAINEZ |
Contact Information
| Contractor | J R C Group Inc; Lic. No.: 980658-B | 8981 SUNSET BLVD STE 505 LOS ANGELES, CA 90069 |
| Engineer | Arca,, Perfecto; Lic. No.: C28918 | 23222 ROSANNA COURT TORRANCE, CA 90502 |
| Engineer | Baad,, Katherine Firestone; Lic. No.: C64669 | 5232 ZAKON RD TORRANCE, CA 90505 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/16/2024 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 5/29/2024 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 5/30/2024 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 6/21/2024 | Partial Approval | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 7/2/2024 | Partial Approval | EVAN COOPER |
| HVAC-Rough | 7/29/2024 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 7/29/2024 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 8/26/2024 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2024 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2024 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 12/11/2024 | Partial Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2025 | Partial Approval | KEVIN SARGSYAN |
| Underground Mechanical | 1/24/2025 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 2/5/2025 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 2/6/2025 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 2/19/2025 | Approved | EVAN COOPER |
| HVAC-Rough | 2/20/2025 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 3/21/2025 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 3/21/2025 | Partial Approval | ARAM AVEDISIAN |
| Sewer | 3/21/2025 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 3/24/2025 | Not Ready for Inspection | HERBERT GIRON |
| Underground Mechanical | 4/8/2025 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 4/14/2025 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 5/5/2025 | Corrections Issued | KEVIN SARGSYAN |
| FLOOD-Proofing Certificate | 5/5/2025 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 5/5/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 5/5/2025 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 5/22/2025 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 5/22/2025 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 5/22/2025 | Partial Approval | KEVIN SARGSYAN |
| Insulation | 6/4/2025 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 7/31/2025 | Partial Approval | KEVIN SARGSYAN |
| Drywall Nailing | 9/29/2025 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 10/14/2025 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 11/19/2025 | Partial Approval | KEVIN SARGSYAN |
| Shower Pan | 11/26/2025 | Approved | KEVIN SARGSYAN |
| Grounding or Bonding | 12/12/2025 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 1/14/2026 | Partial Approval | KEVIN SARGSYAN |