8010 N SAUSALITO AVE 91304
Certificate Information: 8010 N SAUSALITO AVE 91304
- Application / Permit
- 23010-20000-01105
- Plan Check / Job No.
- B23VN03354
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: New Detached ADU ADU PER LAMC 12.22 A.33 (c) & (d)
- Permit Issued
- Issued on 9/20/2023
- Issuing Office
- Current Status
- CofO Issued on 2/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/30/2023 | ADRIANA LOPEZ |
| Corrections Issued | 5/4/2023 | ADRIANA LOPEZ |
| Quality Review Completed | 5/22/2023 | QUAN NGHIEM |
| Applicant returned to address corrections | 8/21/2023 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 9/1/2023 | ADRIANA LOPEZ |
| Plan Check Approved | 9/18/2023 | ADRIANA LOPEZ |
| Issued | 9/20/2023 | APPLICANT |
| CofO in Progress | 1/27/2025 | CHRIS CHRISTENSEN |
| Permit Finaled | 2/12/2025 | JOHN JANSON |
| CofO Issued | 2/12/2025 | JOHN JANSON |
| Permit Finaled | 2/12/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/11/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 5/23/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 5/23/2023 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 6/20/2023 | WALTER RAMIREZ |
| Construction within easement | Cleared | 6/20/2023 | WALTER RAMIREZ |
| Low Impact Development (LID) | Cleared | 6/20/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 6/21/2023 | NIKKI ZULUETA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/26/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 9/26/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 9/29/2023 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2024 | Partial Approval | JEFFREY HARTLINE |
| HVAC-Rough | 2/16/2024 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 2/23/2024 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2024 | Partial Approval | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 2/23/2024 | Partial Approval | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 3/5/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| PLUMBING-Rough | 3/5/2024 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 3/27/2024 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 4/12/2024 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 4/12/2024 | Approved | JEFFREY HARTLINE |
| Verify Sprinkler Sign Off | 4/12/2024 | Approved | JEFFREY HARTLINE |
| Insulation | 7/19/2024 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 7/31/2024 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 7/31/2024 | Partial Approval | GEVORK IPCHYAN |
| Shower Pan | 7/31/2024 | Approved | GEVORK IPCHYAN |
| Final | 9/13/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 9/13/2024 | Approved | JEFFREY HARTLINE |
| Green Building Final | 9/13/2024 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 9/13/2024 | SGSOV Not Ready | JEFFREY HARTLINE |
| Service/Power Release | 9/13/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Smoke Detectors | 9/13/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Final | 9/23/2024 | Corrections Issued | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 9/23/2024 | SGSOV Not Required | CHRIS CHRISTENSEN |
| Service/Power Release | 9/23/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 9/23/2024 | Approved | CHRIS CHRISTENSEN |
| Final | 12/26/2024 | Corrections Issued | CHRIS CHRISTENSEN |
| Service/Power Release | 12/26/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Final | 1/24/2025 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Service/Power Release | 1/24/2025 | Approved | CHRIS CHRISTENSEN |