425-427 E 21ST ST 90011
Certificate Information: 425-427 E 21ST ST 90011
- Application / Permit
- 23010-20000-01099
- Plan Check / Job No.
- B23VN03342
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePLAN. NEW DUPLEX WITH ATTACHED GARAGE.
- Permit Issued
- Issued on 8/7/2023
- Issuing Office
- Current Status
- CofO Issued on 2/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/23/2023 | KEVIN MORALES |
| Corrections Issued | 3/28/2023 | KEVIN MORALES |
| Quality Review Completed | 3/30/2023 | EUGENE BARBEAU |
| Applicant returned to address corrections | 6/27/2023 | KEVIN MORALES |
| Plan Check Approved | 7/27/2023 | KEVIN MORALES |
| Issued | 8/7/2023 | APPLICANT |
| CofO in Progress | 2/14/2024 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 2/28/2024 | DEROLD HAUFF |
| CofO Issued | 2/28/2024 | DEROLD HAUFF |
| Permit Finaled | 2/28/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 4/14/2023 | MATTHEW CRAIG |
| Address approval | Cleared | 4/22/2023 | TREVOR QUAN |
| Highway dedication | Cleared | 4/22/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/1/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 5/1/2023 | TREVOR QUAN |
| Frnt yard landscape/Water mgmt | Cleared | 5/30/2023 | FIPE LEILUA |
| Low Impact Development (LID) | Cleared | 6/15/2023 | ANTHONY VARGAS |
| SB8 RUD | Cleared | 6/15/2023 | KE ZHANG |
| Roof/Waste drainage to street | Cleared | 6/16/2023 | ADRIAN SANCHEZ |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | , |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/22/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 8/23/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 8/23/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 8/24/2023 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 8/24/2023 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2023 | Partial Approval | ANTHONY EGSON |
| Underground Mechanical | 8/31/2023 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 9/1/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/19/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 10/19/2023 | Approved | MICHAEL LEWIS |
| Sewer | 10/19/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 10/20/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 10/20/2023 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 10/20/2023 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/23/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 10/23/2023 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/25/2023 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 11/9/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 11/9/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 12/22/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 12/26/2023 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Final | 12/28/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 2/2/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 2/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 2/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 2/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 2/2/2024 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 2/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 2/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 2/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 2/13/2024 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Service/Power Release | 2/13/2024 | Approved | ALEJANDRO DE ARTOLA |