6736 W FOOTHILL BLVD 91042
Certificate Information: 6736 W FOOTHILL BLVD 91042
- Application / Permit
- 23010-20000-01092
- Plan Check / Job No.
- B23VN03301
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant - Drive Through Fast Food
- Work Description
- Construction of a New one-story drive-through (Starbucks )Single Tenant- Building. Consisting of new drive-through driveway, Site Improvements, new parking areas CORE AND SHELL ONLY. TI UNDER SEPARATE PERMIT. HOURS OF OPERATION BETWEEN 7 AM AND 11 PM
- Permit Issued
- Issued on 2/23/2024
- Issuing Office
- Current Status
- CofO Issued on 5/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/23/2023 | SERGIO GUTIERREZ |
| Corrections Issued | 3/29/2023 | SERGIO GUTIERREZ |
| Quality Review Completed | 3/31/2023 | RODOLFO ARIAS |
| Applicant returned to address corrections | 5/26/2023 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 7/5/2023 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 8/22/2023 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 2/9/2024 | SERGIO GUTIERREZ |
| Plan Check Approved | 2/23/2024 | SERGIO GUTIERREZ |
| Issued | 2/23/2024 | APPLICANT |
| TCO Issued (Expire Date: 10-09-2025) | 4/12/2025 | JEFFREY DURAN |
| Permit Finaled | 5/30/2025 | RICKEY JACKSON |
| CofO Issued | 5/30/2025 | RICKEY JACKSON |
| Permit Finaled | 5/30/2025 | RICKEY JACKSON |
Permit Application Clearance Information
| Food Service Establishment | Cleared | 4/11/2023 | KENNETH BROWNE |
| Address approval | Cleared | 4/15/2023 | CARLOS AGUILERA |
| Bicycle Parking | Cleared | 4/15/2023 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 4/18/2023 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 4/20/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/20/2023 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 4/25/2023 | TINA MIRANDA |
| Encroachment in public way | Cleared | 5/9/2023 | CARLOS AGUILERA |
| Fire Marshal Fire Life Safety | Cleared | 6/9/2023 | DOMINIQUE MEDINA |
| Green Code | Cleared | 6/13/2023 | MICHAEL AYERS |
| DAS Clearance | Cleared | 6/29/2023 | Sarkis Harabedian |
| Disturb/Remove Protected Trees | Cleared | 10/2/2023 | ADALBERTO VERA |
| Work Adjacent to Public Way | Cleared | 10/3/2023 | LEE GUILBEAUX |
| Trees in Parkway | Cleared | 10/11/2023 | ADALBERTO VERA |
| Frnt yard landscape/Water mgmt | Cleared | 12/4/2023 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 12/4/2023 | JAZMIN ROQUE |
| Comm Cor/Mini-Mall | Cleared | 12/6/2023 | JAZMIN ROQUE |
| Comm Cor/Mini-Mall | Cleared | 12/6/2023 | JAZMIN ROQUE |
| Comm Cor/Mini-Mall | Cleared | 12/6/2023 | JAZMIN ROQUE |
| Drive-through fast food | Cleared | 12/6/2023 | JAZMIN ROQUE |
| Landscape for retaining wall | Cleared | 12/6/2023 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 12/6/2023 | JAZMIN ROQUE |
| Prkng lot landscape/Water mgmt | Cleared | 12/6/2023 | JAZMIN ROQUE |
| Site Plan review | Cleared | 12/6/2023 | JAZMIN ROQUE |
| Specific Plan | Cleared | 12/6/2023 | JAZMIN ROQUE |
| ZA Case | Cleared | 12/6/2023 | JAZMIN ROQUE |
| Low Impact Development (LID) | Cleared | 1/2/2024 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 1/11/2024 | RYAN KIM |
| Drive Through | Cleared | 1/16/2024 | MIGUEL CRISOSTOMO |
| Driveway location | Cleared | 1/16/2024 | MIGUEL CRISOSTOMO |
| Driveway location | Cleared | 1/16/2024 | MIGUEL CRISOSTOMO |
| Internal circulation | Cleared | 1/16/2024 | MIGUEL CRISOSTOMO |
| Specific Plan | Cleared | 1/16/2024 | MIGUEL CRISOSTOMO |
| Highway dedication | Cleared | 1/31/2024 | LEE GUILBEAUX |
| Permit | Cleared | 1/31/2024 | LEE GUILBEAUX |
| Food establishment approval | Cleared | 2/9/2024 | LACDHS APPROVED |
| Grading Pre-Inspection | Cleared | 2/9/2024 | SERGIO GUTIERREZ |
Contact Information
| Architect | , ; Lic. No.: C38560 | , |
| Contractor | Sipan Contruction Co.; Lic. No.: 676103-B | 3200 LA CRESCENTA AVE SUITE_B GLENDALE, CA 91208 |
| Engineer | Babayan,, Raffi Samuel; Lic. No.: C72168 | 7718 DAY STREET LOS ANGELES, CA 91042 |
| Engineer | Pachunuri,, Nalin Kumar; Lic. No.: C78970 | 21126 INGOMAR CT CANOGA PARK, CA 91304 |
| Engineer | Zweigler,, Robert Ingraham; Lic. No.: GE2120 | 1461 E. CHEVY CHASE DR. #200 GLENDALE, CA 91206 |
Inspector Information
| JOHN KITCKO, (818) 374-1109 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/28/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 4/1/2024 | Partial Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 5/17/2024 | Conditional Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 5/22/2024 | Conditional Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 6/5/2024 | Conditional Approval | JEFFREY DURAN |
| Footing/Foundation/Slab | 6/12/2024 | Partial Approval | KENNETH ROBERTS |
| Deputy Steel/Welding | 6/27/2024 | Conditional Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 7/8/2024 | Approved | DANNY RODRIGUEZ |
| Deputy Steel/Welding | 7/8/2024 | Approved | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 7/8/2024 | Partial Inspection | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 7/9/2024 | Conditional Approval | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 7/9/2024 | Partial Approval | DANNY RODRIGUEZ |
| Green Building Rough | 7/9/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 7/9/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Deputy Wood Construction | 7/22/2024 | Approved | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 7/22/2024 | Partial Approval | DANNY RODRIGUEZ |
| Green Building Rough | 7/22/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 7/22/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 7/22/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Green Building Rough | 7/25/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 7/25/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 7/25/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Deputy Steel/Welding | 7/30/2024 | Conditional Approval | DANNY RODRIGUEZ |
| Deputy Wood Construction | 7/30/2024 | Approved | DANNY RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2024 | Partial Approval | DANNY RODRIGUEZ |
| Deputy Steel/Welding | 8/5/2024 | Conditional Approval | DANNY RODRIGUEZ |
| Deputy Steel/Welding | 8/6/2024 | Approved | DANNY RODRIGUEZ |
| Deputy Wood Construction | 8/6/2024 | Conditional Approval | DANNY RODRIGUEZ |
| Green Building Rough | 8/6/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 8/6/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 8/6/2024 | Partial Inspection | DANNY RODRIGUEZ |
| Deputy Steel/Welding | 8/8/2024 | Conditional Approval | DANNY RODRIGUEZ |
| Wood Frame | 8/8/2024 | Partial Inspection | DANNY RODRIGUEZ |
| Green Building Rough | 8/9/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 8/9/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 8/9/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Green Building Rough | 8/14/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Insulation | 8/14/2024 | Partial Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 8/14/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 8/14/2024 | Partial Inspection | DANNY RODRIGUEZ |
| Insulation | 8/16/2024 | Partial Approval | DANNY RODRIGUEZ |
| Drywall Nailing | 8/20/2024 | Approved | DANNY RODRIGUEZ |
| Special/Order Compliance | 9/10/2024 | Partial Inspection | GREGORY POMISH |
| Green Building Rough | 9/20/2024 | Not Ready for Inspection | GREGORY POMISH |
| Interior/Exterior Lathing | 9/20/2024 | Partial Approval | GREGORY POMISH |
| Verify Sprinkler Sign Off | 9/20/2024 | Not Ready for Inspection | GREGORY POMISH |
| Wood Frame | 9/20/2024 | Not Ready for Inspection | GREGORY POMISH |
| Drywall Nailing | 10/2/2024 | Partial Approval | DANNY RODRIGUEZ |
| Structural Steel Frame | 10/2/2024 | Approved | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 10/8/2024 | Conditional Approval | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 10/16/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Footing/Foundation/Slab | 10/21/2024 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 10/24/2024 | Conditional Approval | DANNY RODRIGUEZ |
| Drywall Nailing | 10/25/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 10/25/2024 | Partial Approval | DANNY RODRIGUEZ |
| Drywall Nailing | 11/21/2024 | Partial Inspection | ANDREW DORSO |
| Deputy Reinf. Concrete | 12/3/2024 | Conditional Approval | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 12/6/2024 | Partial Approval | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 12/13/2024 | Partial Approval | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 1/24/2025 | Partial Inspection | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 1/28/2025 | Approved | DANNY RODRIGUEZ |
| Final | 4/3/2025 | Partial Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 4/3/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Green Building Final | 4/3/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Green Building Rough | 4/3/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 4/3/2025 | SGSOV Approved | DANNY RODRIGUEZ |
| Smoke Detectors | 4/3/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 4/3/2025 | Approved | DANNY RODRIGUEZ |
| Wood Frame | 4/3/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Final | 4/8/2025 | OK for TCO | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 4/8/2025 | Approved | DANNY RODRIGUEZ |
| Green Building Final | 4/8/2025 | Approved | DANNY RODRIGUEZ |
| Green Building Rough | 4/8/2025 | Approved | DANNY RODRIGUEZ |
| Smoke Detectors | 4/8/2025 | Approved | DANNY RODRIGUEZ |
| Wood Frame | 4/8/2025 | Approved | DANNY RODRIGUEZ |
| Final | 4/10/2025 | OK for TCO | DANNY RODRIGUEZ |
| Special/Order Compliance | 4/29/2025 | Corrections Issued | DANNY RODRIGUEZ |
| Final | 5/2/2025 | Partial Approval | DANNY RODRIGUEZ |