23400 W COLLINS ST 91367

Certificate Information: 23400 W COLLINS ST 91367

Application / Permit
23010-20000-01041
Plan Check / Job No.
B23VN03095
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 16'-5" X 37'-8" DETTACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g). ALL WORK PER ENGINEERING. NFPA 13D FIRE SPRINKLERES REQUIRED THROUGOUT
Permit Issued
Issued on 10/19/2023
Issuing Office
Current Status
CofO Issued on 12/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/24/2023 APPLICANT
Assigned to Plan Check Engineer 3/31/2023 LUISANGEL VALENZUELA
Corrections Issued 4/1/2023 LUISANGEL VALENZUELA
Applicant returned to address corrections 9/22/2023 KAMYAR EMAMI
Plan Check Approved 9/28/2023 KAMYAR EMAMI
Issued 10/19/2023 APPLICANT
CofO in Progress 10/29/2024 GEVORK IPCHYAN
Permit Finaled 12/30/2024 JOHN JANSON
CofO Issued 12/30/2024 JOHN JANSON
Permit Finaled 12/30/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/15/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/17/2023 CARLOS AGUILERA
Sewer availability Cleared 4/17/2023 CARLOS AGUILERA
Grading Pre-Inspection Cleared 6/14/2023 ALEXANDER HELFER
Hydrant and Access approval Cleared 8/30/2023 KURT CORRAL
Low Impact Development (LID) Cleared 9/1/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 9/5/2023 CARLOS AGUILERA
GPI Written Notices Cleared 9/28/2023 LUISANGEL VALENZUELA

Contact Information

Architect Hanna,, Remon; Lic. No.: NA36271       ,
Contractor Green Source Energy Inc; Lic. No.: 1018294-B       ,
Engineer Hanna,, Emil Ramzy; Lic. No.: NA63602       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/9/2024 Approved TROY SANDERS
PLUMBING-Rough 2/9/2024 Partial Approval GEVORK IPCHYAN
Deputy Reinf. Concrete 2/13/2024 Conditional Approval TROY SANDERS
Deputy Wood Construction 3/8/2024 Conditional Approval GEVORK IPCHYAN
ELECTRICAL-Rough 3/13/2024 Not Ready for Inspection GEVORK IPCHYAN
HVAC-Rough 3/13/2024 Not Ready for Inspection GEVORK IPCHYAN
Light Gage Steel Frame 3/13/2024 Partial Approval GEVORK IPCHYAN
PLUMBING-Rough 3/13/2024 Approved GEVORK IPCHYAN
ELECTRICAL-Rough 3/28/2024 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 4/16/2024 Partial Approval GEVORK IPCHYAN
Insulation 4/22/2024 Approved TROY SANDERS
Underground Mechanical 4/22/2024 Partial Approval TROY SANDERS
Drywall Nailing 5/7/2024 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 5/7/2024 Approved GEVORK IPCHYAN
Sewer 5/7/2024 Approved GEVORK IPCHYAN
Shower Pan 5/7/2024 Approved GEVORK IPCHYAN
ELECTRICAL-Final 8/7/2024 Approved GEVORK IPCHYAN
HVAC-Final 8/7/2024 Approved TROY SANDERS
PLUMBING-Final 8/7/2024 Approved GEVORK IPCHYAN
BUILDING-Rough-Frame 8/21/2024 Approved GEVORK IPCHYAN
ELECTRICAL-Final 8/21/2024 Approved GEVORK IPCHYAN
Final 8/21/2024 Not Ready for Inspection GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 8/21/2024 SGSOV Approved GEVORK IPCHYAN
Smoke Detectors 8/21/2024 Approved GEVORK IPCHYAN
Verify Sprinkler Sign Off 8/21/2024 Approved GEVORK IPCHYAN
Final 10/11/2024 Corrections Issued GEVORK IPCHYAN
Service/Power Release 10/11/2024 Not Ready for Inspection GEVORK IPCHYAN
Final 10/28/2024 OK to Issue CofO GEVORK IPCHYAN
Service/Power Release 10/28/2024 Approved GEVORK IPCHYAN