3867 S BUDLONG AVE 90037

Certificate Information: 3867 S BUDLONG AVE 90037

Application / Permit
23010-20000-01033
Plan Check / Job No.
B23VN03087
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 23'-0" X 16'-6" ONE STORY DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c), (d), and (g). ALL WORK PER ENG.
Permit Issued
Issued on 5/30/2023
Issuing Office
Valley
Current Status
CofO Issued on 3/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/10/2023 APPLICANT
Assigned to Plan Check Engineer 3/15/2023 ARTIN ZARUKIAN
Corrections Issued 3/15/2023 ARTIN ZARUKIAN
Building Plans Picked Up 3/20/2023 APPLICANT
Issued 5/30/2023 APPLICANT
CofO in Progress 3/19/2024 SABAS ALONSO
Permit Finaled 3/29/2024 DEROLD HAUFF
CofO Issued 3/29/2024 DEROLD HAUFF
Permit Finaled 3/29/2024 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 3/22/2023 YINGSHI HUANG
Address approval Cleared 3/31/2023 TREVOR QUAN
Hydrant and Access approval Cleared 4/4/2023 KURT CORRAL
Low Impact Development (LID) Cleared 5/16/2023 LUIS LUVANO
Eng Process Fee Ord 176,300 Cleared 5/24/2023 TREVOR QUAN
Roof/Waste drainage to street Cleared 5/24/2023 TREVOR QUAN
Sewer availability Cleared 5/24/2023 TREVOR QUAN

Contact Information

Contractor J G Builders Inc; Lic. No.: 1049536-B 4418 LA MADERA AVENUE      EL MONTE, CA 91732
Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/29/2023 Partial Approval SABAS ALONSO
Underground Mechanical 6/29/2023 Approved SABAS ALONSO
Excavation/Setback/Form/Re-Bar 7/14/2023 Approved SABAS ALONSO
Footing/Foundation/Slab 7/14/2023 Approved SABAS ALONSO
BUILDING-Rough-Frame 10/27/2023 Approved SABAS ALONSO
ELECTRICAL-Rough 10/27/2023 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 10/27/2023 Approved SABAS ALONSO
Green Building Rough 10/27/2023 Approved SABAS ALONSO
HVAC-Rough 10/27/2023 Approved SABAS ALONSO
PLUMBING-Rough 10/27/2023 Approved SABAS ALONSO
Verify Sprinkler Sign Off 10/27/2023 Approved SABAS ALONSO
Insulation 10/31/2023 Approved SABAS ALONSO
Drywall Nailing 11/9/2023 Approved SABAS ALONSO
Shower Pan 1/16/2024 Corrections Issued SABAS ALONSO
Shower Pan 1/18/2024 Corrections Issued SABAS ALONSO
Shower Pan 1/23/2024 Corrections Issued JOSE MACIAS
Interior/Exterior Lathing 1/25/2024 Approved SABAS ALONSO
Shower Pan 1/25/2024 Approved SABAS ALONSO
Gas Test 2/13/2024 Approved SABAS ALONSO
Sewer 2/13/2024 Approved SABAS ALONSO
Underground Mechanical 2/13/2024 Approved SABAS ALONSO
ELECTRICAL-Final 2/26/2024 Not Ready for Inspection SABAS ALONSO
Final 2/26/2024 Corrections Issued SABAS ALONSO
Green Building Final 2/26/2024 Approved SABAS ALONSO
PLUMBING-Final 2/26/2024 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 2/26/2024 SGSOV Approved SABAS ALONSO
Service/Power Release 2/26/2024 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 2/26/2024 Approved SABAS ALONSO
Pre-Inspection 2/29/2024 Not Ready for Inspection ANTHONY EGSON
Final 3/13/2024 Not Ready for Inspection SABAS ALONSO
Final 3/19/2024 OK to Issue CofO SABAS ALONSO
Service/Power Release 3/19/2024 Approved SABAS ALONSO