7660 N BALBOA BLVD Bldg A 91406

Certificate Information: 7660 N BALBOA BLVD Bldg A 91406

Application / Permit
23010-20000-00987
Plan Check / Job No.
B23VN02960
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(22) Storage Building
Work Description
Proposed 3-story self storage facility per ZA-2019-2956-CU-ZAD-SPR (1/2).
Permit Issued
Issued on 3/15/2024
Issuing Office
Metro
Current Status
CofO Issued on 10/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/23/2023 APPLICANT
Assigned to Plan Check Engineer 3/30/2023 ARMEN JIVALAGIAN
Corrections Issued 4/11/2023 ARMEN JIVALAGIAN
Quality Review Completed 4/11/2023 PETER KIM
Applicant returned to address corrections 5/1/2023 ARMEN JIVALAGIAN
Applicant returned to address corrections 10/13/2023 ARMEN JIVALAGIAN
Applicant returned to address corrections 11/17/2023 ARMEN JIVALAGIAN
Applicant returned to address corrections 11/22/2023 ARMEN JIVALAGIAN
Applicant returned to address corrections 11/27/2023 ARMEN JIVALAGIAN
Applicant returned to address corrections 2/7/2024 ARMEN JIVALAGIAN
Applicant returned to address corrections 3/5/2024 ARMEN JIVALAGIAN
Applicant returned to address corrections 3/6/2024 ARMEN JIVALAGIAN
Plan Check Approved 3/8/2024 ARMEN JIVALAGIAN
Issued 3/15/2024 APPLICANT
CofO in Progress 9/10/2025 GREGORY POMISH
Permit Finaled 10/1/2025 JEFFREY DURAN
CofO Issued 10/1/2025 JEFFREY DURAN
Permit Finaled 10/1/2025 JEFFREY DURAN

Permit Application Clearance Information

Address approval Cleared 6/1/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 6/1/2023 LEE GUILBEAUX
Watercourse Cleared 6/1/2023 LEE GUILBEAUX
Trees in Parkway Cleared 6/5/2023 ADALBERTO VERA
Construction near power lines Cleared 8/17/2023 RIDWAN HARDY
Construction within easement Cleared 8/17/2023 RIDWAN HARDY
Low Impact Development (LID) Cleared 9/22/2023 MARTIN FRAGOSO
Miscellaneous Cleared 11/2/2023 GEORGIA SMITH
Plan Approval Cleared 11/2/2023 GEORGIA SMITH
ZA Case Cleared 11/2/2023 GEORGIA SMITH
DAS Clearance Cleared 11/13/2023 ARMEN JIVALAGIAN
Drainage to Storm Drain Cleared 11/14/2023 LEE GUILBEAUX
Highway dedication Cleared 11/14/2023 LEE GUILBEAUX
Internal circulation Cleared 11/14/2023 MIGUEL CRISOSTOMO
Miscellaneous Cleared 11/14/2023 LEE GUILBEAUX
Miscellaneous Cleared 11/14/2023 LEE GUILBEAUX
Permit Cleared 11/14/2023 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 11/14/2023 LEE GUILBEAUX
Sewer availability Cleared 12/12/2023 CARLOS AGUILERA
Miscellaneous Cleared 12/22/2023 STEVEN WECHSLER
Tract Map conditions Cleared 12/22/2023 NATHAN ROMINE
Hydrant and Access approval Cleared 1/18/2024 RUEL COLE
Building over 36-ft Cleared 1/25/2024 CALOSHA APPROVED
Prkng lot landscape/Water mgmt Cleared 1/29/2024 NATHAN ROMINE
Site Plan review Cleared 1/29/2024 NATHAN ROMINE
ZA Case Cleared 1/29/2024 NATHAN ROMINE
Green Code Cleared 2/4/2024 ARMEN JIVALAGIAN
Flood clearance Cleared 3/8/2024 LEE GUILBEAUX

Contact Information

Architect Vakili,, Shabnam; Lic. No.: NA26298       ,
Contractor Gray Wc; Lic. No.: 775947-B 421 E CERRITOS AVENUE      ANAHEIM, CA 92805
Engineer Grigorian,, Carl Edward; Lic. No.: S4786 1589 TRENTON AVE      GLENDALE, CA 91206
Engineer Maier,, John Luke; Lic. No.: GE3135 3100 N ASHWOOD ST      ORANGE, CA 92865

Inspector Information

GREGORY POMISH, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI
EDWIN GREGORYONA, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/20/2024 Partial Inspection GREGORY POMISH
Footing/Foundation/Slab 5/31/2024 Partial Approval MARTIN TAVITIAN
Deputy Reinf. Concrete 6/4/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 6/6/2024 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 6/6/2024 Not Ready for Inspection GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 6/7/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 6/13/2024 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 6/20/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 6/26/2024 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 6/26/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 6/27/2024 Conditional Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 6/28/2024 Not Ready for Inspection GREGORY POMISH
Footing/Foundation/Slab 7/2/2024 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 7/2/2024 Partial Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 7/3/2024 Partial Approval JOHN KITCKO
Deputy Reinf. Masonry 7/8/2024 Approved GREGORY POMISH
Masonry Wall/Backfill 7/8/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Masonry 7/9/2024 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 7/9/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Masonry 7/11/2024 Conditional Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 7/11/2024 Partial Approval GREGORY POMISH
Masonry Wall/Backfill 7/12/2024 Partial Approval GREGORY POMISH
Footing/Foundation/Slab 7/15/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 7/16/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 7/16/2024 Conditional Approval GREGORY POMISH
Reinforced Concrete Frame 7/16/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 7/17/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 7/19/2024 Conditional Approval GREGORY POMISH
Masonry Wall/Backfill 7/19/2024 Partial Inspection GREGORY POMISH
Deputy Reinf. Concrete 7/23/2024 Conditional Approval ROBERT DAVIS
Deputy Reinf. Masonry 7/23/2024 Conditional Approval ROBERT DAVIS
Footing/Foundation/Slab 7/23/2024 Partial Approval ROBERT DAVIS
Masonry Wall/Backfill 7/23/2024 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 7/24/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 7/24/2024 Conditional Approval GREGORY POMISH
Masonry Wall/Backfill 7/24/2024 Not Ready for Inspection GREGORY POMISH
Masonry Wall/Backfill 7/27/2024 Off-Hour Fees Due
Masonry Wall/Backfill 7/27/2024 Partial Approval GREGORY POMISH
Masonry Wall/Backfill 7/29/2024 Not Ready for Inspection GREGORY POMISH
Reinforced Masonry Frame 7/29/2024 Not Ready for Inspection GREGORY POMISH
Verify Sprinkler Sign Off 7/29/2024 Not Ready for Inspection GREGORY POMISH
Masonry Wall/Backfill 8/1/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Masonry 8/2/2024 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 8/2/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 8/7/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 8/7/2024 Conditional Approval GREGORY POMISH
Masonry Wall/Backfill 8/7/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Masonry 8/8/2024 Partial Approval GREGORY POMISH
Masonry Wall/Backfill 8/12/2024 Partial Approval GREGORY POMISH
Footing/Foundation/Slab 8/13/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 8/14/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 8/14/2024 Conditional Approval GREGORY POMISH
Masonry Wall/Backfill 8/14/2024 Not Ready for Inspection GREGORY POMISH
Footing/Foundation/Slab 8/15/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 8/19/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 8/19/2024 Conditional Approval GREGORY POMISH
Masonry Wall/Backfill 8/19/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Masonry 8/20/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 8/20/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 8/23/2024 Conditional Approval GREGORY POMISH
Masonry Wall/Backfill 8/23/2024 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 8/26/2024 Partial Approval GREGORY POMISH
Masonry Wall/Backfill 8/26/2024 Partial Inspection GREGORY POMISH
Deputy Reinf. Concrete 8/28/2024 Conditional Approval GREGORY POMISH
Masonry Wall/Backfill 8/30/2024 Partial Approval GREGORY POMISH
Footing/Foundation/Slab 9/4/2024 Partial Approval GREGORY POMISH
Light Gage Steel Frame 9/4/2024 Partial Inspection GREGORY POMISH
Deputy Reinf. Concrete 9/5/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 9/9/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 9/10/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 9/11/2024 Conditional Approval GREGORY POMISH
Masonry Wall/Backfill 9/11/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Masonry 9/12/2024 Conditional Approval GREGORY POMISH
Masonry Wall/Backfill 9/19/2024 Partial Approval JOHN KITCKO
Deputy Reinf. Masonry 9/20/2024 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 9/20/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 9/23/2024 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 9/25/2024 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 9/26/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 9/30/2024 Conditional Approval CAMERON CHABAN
Deputy Drilled-In Anchors 10/2/2024 Conditional Approval GREGORY POMISH
Deputy Drilled-In Anchors 10/4/2024 Conditional Approval GREGORY POMISH
Structural Steel Frame 10/7/2024 Partial Inspection GREGORY POMISH
Deputy Drilled-In Anchors 10/8/2024 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 10/10/2024 Conditional Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 10/10/2024 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 10/18/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 10/24/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 10/25/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 10/29/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 10/29/2024 Conditional Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 10/31/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Masonry 11/6/2024 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 11/6/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Masonry 11/7/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 11/8/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 11/12/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 11/13/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 11/13/2024 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 11/13/2024 Partial Approval GREGORY POMISH
Masonry Wall/Backfill 11/13/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Masonry 11/14/2024 Conditional Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 11/14/2024 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 11/18/2024 Conditional Approval ANDREW DORSO
Special/Order Compliance 11/18/2024 Not Ready for Inspection ANDREW DORSO
Deputy Reinf. Masonry 11/19/2024 Conditional Approval GREGORY POMISH
Reinforced Masonry Frame 11/19/2024 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 11/19/2024 Not Ready for Inspection GREGORY POMISH
Footing/Foundation/Slab 11/21/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 11/25/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 11/25/2024 Conditional Approval GREGORY POMISH
Masonry Wall/Backfill 11/25/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Masonry 12/2/2024 Conditional Approval GREGORY POMISH
Reinforced Masonry Frame 12/2/2024 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 12/2/2024 Not Ready for Inspection GREGORY POMISH
Deputy Reinf. Masonry 12/4/2024 Conditional Approval GREGORY POMISH
Masonry Wall/Backfill 12/4/2024 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 12/5/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 12/5/2024 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 12/5/2024 Partial Approval GREGORY POMISH
Drywall Nailing 12/6/2024 Partial Approval GREGORY POMISH
Pre-Inspection 1/29/2025 Off-Hour Fees Due
Masonry Wall/Backfill 1/30/2025 Off-Hour Fees Due
Deputy Reinf. Masonry 2/11/2025 Conditional Approval GREGORY POMISH
Insulation 4/2/2025 Partial Approval GREGORY POMISH
Drywall Nailing 4/11/2025 Partial Approval GREGORY POMISH
Special/Order Compliance 9/4/2025 Conditional Approval JEFFREY DURAN
Final 9/5/2025 Not Ready for Inspection JOHN KITCKO
Footing/Foundation/Slab 9/5/2025 Approved JOHN KITCKO
Reinforced Masonry Frame 9/5/2025 Approved JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 9/5/2025 SGSOV Not Ready JOHN KITCKO
Smoke Detectors 9/5/2025 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 9/5/2025 Approved JOHN KITCKO
Final 9/10/2025 OK to Issue CofO GREGORY POMISH
SGSOV-Seismic Gas S/O Valve 9/10/2025 SGSOV Approved GREGORY POMISH
Smoke Detectors 9/10/2025 Approved GREGORY POMISH
Special/Order Compliance 9/10/2025 Partial Approval GREGORY POMISH