8387 N CAPISTRANO AVE 91304

Certificate Information: 8387 N CAPISTRANO AVE 91304

Application / Permit
23010-20000-00954
Plan Check / Job No.
B23VN02873
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan NEW TWO STORY ADU, WITH NEW ATTACHED CAR GARAGE The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
Permit Issued
Issued on 7/28/2023
Issuing Office
Current Status
CofO Issued on 6/11/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/17/2023 APPLICANT
Assigned to Plan Check Engineer 3/30/2023 MARCELA FRANQUEZ
Corrections Issued 4/10/2023 MARCELA FRANQUEZ
Quality Review Completed 4/17/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 7/26/2023 MARCELA FRANQUEZ
Plan Check Approved 7/27/2023 MARCELA FRANQUEZ
Issued 7/28/2023 APPLICANT
CofO in Progress 5/22/2024 JEFFREY HARTLINE
Permit Finaled 6/11/2024 JOHN JANSON
CofO Issued 6/11/2024 JOHN JANSON
Permit Finaled 6/11/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/2/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 5/2/2023 NIKKI ZULUETA
Sewer availability Cleared 5/2/2023 NIKKI ZULUETA
Grading Pre-Inspection Cleared 5/5/2023 ALEXANDER HELFER
Roof/Waste drainage to street Cleared 7/12/2023 NIKKI ZULUETA
GPI Written Notices Cleared 7/26/2023 MARCELA FRANQUEZ

Contact Information

Contractor Flip It Homes Inc; Lic. No.: 1043456-B       ,
Engineer Nagovitsyn,, Evgeny; Lic. No.: C93527 17436 ARMINTA ST      NORTHRIDGE, CA 91325

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/29/2023 Approved JEFFREY HARTLINE
Underground Mechanical 8/29/2023 Approved JEFFREY HARTLINE
Footing/Foundation/Slab 9/5/2023 Approved JEFFREY HARTLINE
Deputy Wood Construction 9/14/2023 Conditional Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 9/26/2023 Corrections Issued CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 10/10/2023 Partial Approval JEFFREY HARTLINE
PLUMBING-Rough 10/10/2023 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 10/20/2023 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 10/24/2023 Partial Approval JEFFREY HARTLINE
HVAC-Rough 10/24/2023 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 11/20/2023 Approved JEFFREY HARTLINE
Green Building Rough 11/20/2023 Approved JEFFREY HARTLINE
Verify Sprinkler Sign Off 11/20/2023 Approved JEFFREY HARTLINE
Insulation 11/27/2023 Partial Approval JEFFREY HARTLINE
Interior/Exterior Lathing 11/27/2023 Approved JEFFREY HARTLINE
Shower Pan 11/27/2023 Approved JEFFREY HARTLINE
Drywall Nailing 12/5/2023 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 12/5/2023 Approved JEFFREY HARTLINE
Gas Test 2/26/2024 Approved JEFFREY HARTLINE
ELECTRICAL-Final 3/8/2024 Not Ready for Inspection JEFFREY HARTLINE
Final 3/8/2024 Corrections Issued JEFFREY HARTLINE
Green Building Final 3/8/2024 Approved JEFFREY HARTLINE
HVAC-Final 3/8/2024 Approved JEFFREY HARTLINE
PLUMBING-Final 3/8/2024 Not Ready for Inspection JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 3/8/2024 SGSOV Approved JEFFREY HARTLINE
Service/Power Release 3/8/2024 Not Ready for Inspection JEFFREY HARTLINE
Smoke Detectors 3/8/2024 Approved JEFFREY HARTLINE
ELECTRICAL-Final 3/19/2024 Approved JEFFREY HARTLINE
Final 3/19/2024 Partial Approval JEFFREY HARTLINE
PLUMBING-Final 3/19/2024 Approved JEFFREY HARTLINE
Service/Power Release 3/19/2024 Approved JEFFREY HARTLINE
Final 5/22/2024 OK to Issue CofO JEFFREY HARTLINE