3600 S FRANCES AVE 90066
Certificate Information: 3600 S FRANCES AVE 90066
- Application / Permit
- 23010-20000-00953
- Plan Check / Job No.
- B23VN02864
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- New 9'10" X 22' Detached recreation room with 1/2 bathroom and shower with exterior acccess, all work per engineering
- Permit Issued
- Issued on 8/22/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/9/2023 | RARES BODEA |
| Corrections Issued | 3/13/2023 | RARES BODEA |
| Quality Review Completed | 3/16/2023 | STEVEN KIM |
| Building Plans Picked Up | 3/17/2023 | APPLICANT |
| Applicant returned to address corrections | 5/10/2023 | RARES BODEA |
| Applicant returned to address corrections | 6/5/2023 | RARES BODEA |
| Applicant returned to address corrections | 6/27/2023 | RARES BODEA |
| Applicant returned to address corrections | 8/4/2023 | RARES BODEA |
| Plan Check Approved | 8/9/2023 | RARES BODEA |
| Issued | 8/22/2023 | APPLICANT |
| CofO in Progress | 3/6/2025 | JESUS PINEDA |
| Permit Finaled | 3/11/2025 | RICHARD STEINBACH |
| CofO Issued | 3/11/2025 | RICHARD STEINBACH |
| Permit Finaled | 3/11/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 4/9/2023 | LAVEON RIDER |
| Specific Plan | Cleared | 4/10/2023 | ALESSANDRO MERCURI |
| Sewer availability | Cleared | 4/18/2023 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/20/2023 | ANTHONY MAINEZ |
| Low Impact Development (LID) | Cleared | 4/21/2023 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 5/8/2023 | AHMED AMARRAGY |
| Grading Pre-Inspection | Cleared | 5/10/2023 | RARES BODEA |
| Construction near power lines | Cleared | 6/16/2023 | RIDWAN HARDY |
| GPI Written Notices | Cleared | 8/4/2023 | RARES BODEA |
| Construction near power lines | Cleared | 8/9/2023 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 11/30/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 11/30/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Underground Mechanical | 11/30/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Rough-Elec/Plmb/HVAC | 2/13/2024 | Corrections Issued | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 4/1/2024 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 4/1/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 4/1/2024 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 4/1/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 4/1/2024 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 4/8/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Green Building Rough | 4/8/2024 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 1/30/2025 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 2/19/2025 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Final | 2/19/2025 | Not Ready for Inspection | JESUS PINEDA |
| HVAC-Final | 2/19/2025 | Not Ready for Inspection | JESUS PINEDA |
| ELECTRICAL-Final | 2/28/2025 | Approved | JESUS PINEDA |
| HVAC-Final | 2/28/2025 | Approved | JESUS PINEDA |
| PLUMBING-Final | 2/28/2025 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 3/5/2025 | Approved | JESUS PINEDA |
| Drywall Nailing | 3/5/2025 | Approved | JESUS PINEDA |
| Final | 3/5/2025 | OK to Issue CofO | JESUS PINEDA |
| Footing/Foundation/Slab | 3/5/2025 | Approved | JESUS PINEDA |
| Green Building Final | 3/5/2025 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 3/5/2025 | SGSOV Approved | JESUS PINEDA |
| Service/Power Release | 3/5/2025 | Approved | JESUS PINEDA |
| Smoke Detectors | 3/5/2025 | Approved | JESUS PINEDA |