14949 W VALLEYHEART DR 91403
Certificate Information: 14949 W VALLEYHEART DR 91403
- Application / Permit
- 23010-20000-00951
- Plan Check / Job No.
- B23VN02862
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW TWO-STORY ( 31'-0" X 21'-0" ) DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK PER ENGINEER.
- Permit Issued
- Issued on 6/14/2023
- Issuing Office
- Current Status
- CofO Issued on 5/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/13/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 3/14/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 3/15/2023 | APPLICANT |
| Plan Check Approved | 6/14/2023 | ROSENDO MEDINA |
| Issued | 6/14/2023 | APPLICANT |
| CofO in Progress | 5/7/2024 | THOMAS FINNILA |
| Permit Finaled | 5/10/2024 | RUBEN SALAS |
| Permit Finaled | 5/10/2024 | RUBEN SALAS |
| CofO Issued | 5/10/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/18/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 3/20/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 3/20/2023 | COLIN LOREDO |
| Hydrant and Access approval | Cleared | 3/31/2023 | RUEL COLE |
| Low Impact Development (LID) | Cleared | 6/9/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 6/13/2023 | ROMAN GUTIERREZ |
| ZI | Cleared | 6/13/2023 | BRENNEN OBETO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| DAVID ANDERSON, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 6/30/2023 | Partial Approval | THOMAS FINNILA |
| PLUMBING-Rough | 6/30/2023 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 7/7/2023 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2023 | Partial Approval | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 8/29/2023 | Partial Approval | THOMAS FINNILA |
| Gas Test | 9/11/2023 | Partial Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 9/13/2023 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2023 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 9/13/2023 | Conditional Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 9/22/2023 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2023 | Corrections Issued | THOMAS FINNILA |
| HVAC-Rough | 9/22/2023 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2023 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 10/6/2023 | Corrections Issued | THOMAS FINNILA |
| Green Building Rough | 10/6/2023 | Approved | THOMAS FINNILA |
| MERV13>=Rough | 10/6/2023 | Approved | THOMAS FINNILA |
| Sewer | 10/6/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 10/6/2023 | Approved | THOMAS FINNILA |
| Sewer | 10/11/2023 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 10/16/2023 | Approved | THOMAS FINNILA |
| Gas Test | 10/18/2023 | Approved | THOMAS FINNILA |
| Insulation | 10/23/2023 | Corrections Issued | THOMAS FINNILA |
| Insulation | 10/26/2023 | Approved | THOMAS FINNILA |
| Drywall Nailing | 11/3/2023 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 11/3/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 11/6/2023 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 1/8/2024 | Partial Approval | THOMAS FINNILA |
| Final | 2/26/2024 | No Access for Inspection | CRAIG DAVIS |
| Green Building Final | 2/26/2024 | No Access for Inspection | CRAIG DAVIS |
| MERV13>=Final | 2/26/2024 | No Access for Inspection | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 2/26/2024 | SGSOV Not Ready | CRAIG DAVIS |
| Service/Power Release | 2/26/2024 | No Access for Inspection | CRAIG DAVIS |
| Smoke Detectors | 2/26/2024 | No Access for Inspection | CRAIG DAVIS |
| ELECTRICAL-Final | 2/27/2024 | Corrections Issued | THOMAS FINNILA |
| Final | 2/27/2024 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Final | 2/27/2024 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 2/28/2024 | SGSOV Not Ready | THOMAS FINNILA |
| Final | 5/1/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Final | 5/1/2024 | Approved | THOMAS FINNILA |
| MERV13>=Final | 5/1/2024 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 5/1/2024 | SGSOV Not Ready | THOMAS FINNILA |
| Service/Power Release | 5/1/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Smoke Detectors | 5/1/2024 | Approved | THOMAS FINNILA |
| Pre-Inspection | 5/3/2024 | Approved | THOMAS FINNILA |
| Final | 5/6/2024 | OK to Issue CofO | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 5/6/2024 | SGSOV Approved | THOMAS FINNILA |
| Service/Power Release | 5/6/2024 | Approved | THOMAS FINNILA |