22821 W BURBANK BLVD 91367

Certificate Information: 22821 W BURBANK BLVD 91367

Application / Permit
23010-20000-00931
Plan Check / Job No.
B23VN02815
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New Detached 1-Story Detached ADU per LAMC 12.22 A.33 (c) and (d), and WFPP
Permit Issued
Issued on 6/10/2023
Issuing Office
Current Status
CofO Issued on 2/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/6/2023 APPLICANT
Assigned to Plan Check Engineer 3/10/2023 DAVID CASTILLO
Corrections Issued 3/11/2023 DAVID CASTILLO
Applicant returned to address corrections 4/11/2023 DAVID CASTILLO
Plan Check Approved 4/28/2023 ALEC MOUSAKHANIAN
Issued 6/10/2023 APPLICANT
CofO in Progress 12/23/2024 TROY SANDERS
No Progress 1/8/2025 HENRY KIM
CofO in Progress 1/8/2025 HENRY KIM
Permit Finaled 2/20/2025 JOHN JANSON
CofO Issued 2/20/2025 JOHN JANSON
Permit Finaled 2/20/2025 JOHN JANSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/17/2023 KIRK LINKLATER
Address approval Cleared 3/18/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/20/2023 CARLOS AGUILERA
Sewer availability Cleared 3/20/2023 CARLOS AGUILERA
Low Impact Development (LID) Cleared 3/31/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 4/8/2023 MARKOS PEREZ-BRAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/3/2023 Partial Approval TROY SANDERS
Footing/Foundation/Slab 8/11/2023 Approved HORACE FULTZ
Footing/Foundation/Slab 8/15/2023 Approved TROY SANDERS
BUILDING-Rough-Frame 9/18/2023 Approved TROY SANDERS
Green Building Rough 9/18/2023 Not Ready for Inspection TROY SANDERS
Rough-Elec/Plmb/HVAC 9/18/2023 Approved TROY SANDERS
Verify Sprinkler Sign Off 9/18/2023 Approved TROY SANDERS
Insulation 9/25/2023 Approved TROY SANDERS
Interior/Exterior Lathing 9/25/2023 Partial Approval TROY SANDERS
Drywall Nailing 10/6/2023 Approved TROY SANDERS
Shower Pan 10/6/2023 Approved TROY SANDERS
Sewer 12/20/2023 Approved TROY SANDERS
Underground Mechanical 12/20/2023 Approved TROY SANDERS
Gas Test 2/12/2024 Not Ready for Inspection TROY SANDERS
Special/Order Compliance 4/3/2024 Approved TROY SANDERS
BUILDING-Rough-Frame 7/29/2024 Approved TROY SANDERS
Final 7/29/2024 Corrections Issued TROY SANDERS
Green Building Final 7/29/2024 Not Ready for Inspection TROY SANDERS
Green Building Rough 7/29/2024 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 7/29/2024 SGSOV Approved TROY SANDERS
Service/Power Release 7/29/2024 Approved TROY SANDERS
Smoke Detectors 7/29/2024 Approved TROY SANDERS
Final 12/19/2024 Not Ready for Inspection TROY SANDERS
Green Building Final 12/19/2024 Approved TROY SANDERS
Final 12/20/2024 OK to Issue CofO TROY SANDERS
Special/Order Compliance 1/9/2025 Corrections Issued TROY SANDERS