18649 W ECCLES ST 91324

Certificate Information: 18649 W ECCLES ST 91324

Application / Permit
23010-20000-00893
Plan Check / Job No.
B23VN02709
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan NEW 2-STORY ACCESSORY DWELLING UNIT
Permit Issued
Issued on 8/16/2024
Issuing Office
Valley
Current Status
CofO Issued on 10/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/8/2023 APPLICANT
Assigned to Plan Check Engineer 3/16/2023 VU NGUYEN
Corrections Issued 3/18/2023 VU NGUYEN
Quality Review Completed 3/20/2023 EUGENE BARBEAU
Applicant returned to address corrections 5/29/2024 VU NGUYEN
Plan Check Approved 7/31/2024 VU NGUYEN
Issued 8/16/2024 APPLICANT
CofO in Progress 6/12/2025 KRISTEN BEVERIDGE
Permit Finaled 10/14/2025 JOHN JANSON
CofO Issued 10/14/2025 JOHN JANSON
Permit Finaled 10/14/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/11/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 9/19/2023 LEE GUILBEAUX
Sewer availability Cleared 9/19/2023 LEE GUILBEAUX
Low Impact Development (LID) Cleared 7/23/2024 LUIS LUVANO
Roof/Waste drainage to street Cleared 7/26/2024 JOHN LIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/2/2024 Approved KRISTEN CAUSEY
PLUMBING-Rough 10/2/2024 Partial Approval KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 10/15/2024 No Access for Inspection KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 10/16/2024 Partial Approval KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 11/6/2024 Partial Approval DAVID SCANTLIN
Verify Sprinkler Sign Off 11/6/2024 Not Ready for Inspection DAVID SCANTLIN
Interior/Exterior Lathing 11/27/2024 Partial Approval KRISTEN CAUSEY
BUILDING-Rough-Frame 12/18/2024 Approved DAVID SCANTLIN
ELECTRICAL-Rough 12/18/2024 Approved DAVID SCANTLIN
Green Building Rough 12/18/2024 Approved DAVID SCANTLIN
HVAC-Rough 12/18/2024 Approved DAVID SCANTLIN
Interior/Exterior Lathing 12/18/2024 Partial Approval DAVID SCANTLIN
Verify Sprinkler Sign Off 12/18/2024 Approved DAVID SCANTLIN
Insulation 1/27/2025 Partial Inspection KRISTEN CAUSEY
Drywall Nailing 1/30/2025 Approved KRISTEN CAUSEY
Insulation 1/30/2025 Approved KRISTEN CAUSEY
Pre-Inspection 1/31/2025 Partial Inspection KRISTEN CAUSEY
PLUMBING-Rough 2/24/2025 Approved KRISTEN CAUSEY
Underground Mechanical 3/4/2025 Partial Approval JEFFREY HARTLINE
Final 5/20/2025 Corrections Issued KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 5/20/2025 SGSOV Approved KRISTEN CAUSEY
Smoke Detectors 5/20/2025 Approved KRISTEN CAUSEY
Final 6/11/2025 OK to Issue CofO KRISTEN CAUSEY
Service/Power Release 6/11/2025 Approved KRISTEN CAUSEY
Service/Power Release 6/13/2025 Approved KRISTEN CAUSEY