160 N TIGERTAIL ROAD 90049
Certificate Information: 160 N TIGERTAIL ROAD 90049
- Application / Permit
- 23010-20000-00868
- Plan Check / Job No.
- B23VN02608
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW IRR. SHAPED 87'-10 1/2" x 71'-9 1/2" TWO-STORY SINGLE FAMILY DWELLING W/ BASEMENT, OPEN TRELLIS, 3-CAR GARAGE AND STORAGE; NFPA-13D THRU-OUT
- Permit Issued
- Issued on 10/10/2023
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 10/10/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2023 | SEAN SHAHMIRI |
| Corrections Issued | 3/23/2023 | SEAN SHAHMIRI |
| Quality Review Completed | 3/23/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 3/29/2023 | APPLICANT |
| Applicant returned to address corrections | 4/4/2023 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 5/25/2023 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 10/2/2023 | SEAN SHAHMIRI |
| Plan Check Approved | 10/2/2023 | SEAN SHAHMIRI |
| Issued | 10/10/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/22/2023 | JENSON LEE |
| Permit | Cleared | 3/22/2023 | JENSON LEE |
| BHO/Hillside ordinance | Cleared | 4/6/2023 | DARIN LAM |
| BHO/Hillside ordinance | Cleared | 4/10/2023 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 4/10/2023 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 4/10/2023 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 4/10/2023 | ANTHONY MAINEZ |
| Trees in Parkway | Cleared | 4/11/2023 | ADALBERTO VERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/8/2023 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 5/8/2023 | ANTHONY MAINEZ |
| Hydrant and Access approval | Cleared | 5/15/2023 | RUEL COLE |
| Low Impact Development (LID) | Cleared | 9/20/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 9/27/2023 | ANTHONY MAINEZ |
Contact Information
| Contractor | Blue Label Construction Inc; Lic. No.: 972011-B | 2632 WILSHIRE BLVD #363 SANTA MONICA, CA 90403 |
| Engineer | Daneshfar,, Kourosh Dan; Lic. No.: C68377 | 19722 ARMINTA ST WINNETKA, CA 91306 |
| Engineer | Tani,, Jason; Lic. No.: C58271 | 5296 VIA PATRICIA THOUSAND OAKS, CA 91320 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/11/2024 | Approved | CARLOS MATAMOROS |
| Pre-Inspection | 9/10/2024 | Approved | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 10/18/2024 | Conditional Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 10/22/2024 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 10/22/2024 | Partial Approval | CARLOS MATAMOROS |
| Underground Mechanical | 10/22/2024 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 10/23/2024 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 10/31/2024 | Conditional Approval | CARLOS MATAMOROS |
| Pre-Inspection | 11/6/2024 | Approved | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 11/8/2024 | Conditional Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 11/8/2024 | Partial Approval | BOBBY KEY |
| Deputy Reinf. Concrete | 11/12/2024 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Shotcrete | 12/2/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 12/3/2024 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Shotcrete | 12/3/2024 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Steel/Welding | 12/3/2024 | Conditional Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 12/4/2024 | Partial Approval | CARLOS MATAMOROS |
| Deputy Shotcrete | 12/5/2024 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Shotcrete | 12/6/2024 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Steel/Welding | 12/23/2024 | Conditional Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2025 | Approved | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 2/19/2025 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Steel/Welding | 2/19/2025 | Conditional Approval | CARLOS MATAMOROS |
| Structural Steel Frame | 2/19/2025 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 2/25/2025 | Approved | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 2/28/2025 | Conditional Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2025 | Partial Approval | STEPHANIE SWANSON |
| Deputy Drilled-In Anchors | 4/11/2025 | Conditional Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2025 | Corrections Issued | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2025 | Approved | CARLOS MATAMOROS |
| Special/Order Compliance | 5/5/2025 | Partial Inspection | CHRISTOPHER WILSON |
| Deputy Wood Construction | 5/21/2025 | Conditional Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2025 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 7/15/2025 | Corrections Issued | JESUS PINEDA |
| Gas Test | 8/15/2025 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 8/15/2025 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 8/25/2025 | Corrections Issued | CARLOS MATAMOROS |
| HVAC-Rough | 8/25/2025 | Approved | CARLOS MATAMOROS |
| Sewer | 8/25/2025 | Approved | CARLOS MATAMOROS |
| Underground Mechanical | 8/25/2025 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 8/26/2025 | Conditional Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2025 | Partial Approval | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 8/26/2025 | Approved | CARLOS MATAMOROS |
| Deputy Wood Construction | 8/28/2025 | Conditional Approval | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 8/29/2025 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 8/29/2025 | Approved | CARLOS MATAMOROS |
| Insulation | 9/11/2025 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 10/2/2025 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 10/15/2025 | Partial Approval | CARLOS MATAMOROS |
| Shower Pan | 10/15/2025 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 10/23/2025 | Partial Approval | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 12/8/2025 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 4/20/2026 | Approved | EVAN COOPER |
| Underground Mechanical | 5/6/2026 | Approved | EVAN COOPER |
| Deputy Drilled-In Anchors | 5/15/2026 | Conditional Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 5/19/2026 | Approved | EVAN COOPER |
| Deputy Reinf. Concrete | 5/20/2026 | Conditional Approval | EVAN COOPER |
| Gas Test | 6/1/2026 | Approved | EVAN COOPER |