9982-9984 W EDMORE PL 91352

Certificate Information: 9982-9984 W EDMORE PL 91352

Application / Permit
23010-20000-00849
Plan Check / Job No.
B23VN02548
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(35) Condo-Multi Family
Work Description
ePlan addition to sfd and add new attached ADU
Permit Issued
Issued on 11/17/2025
Issuing Office
Current Status
Issued on 11/17/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/21/2023 APPLICANT
Assigned to Plan Check Engineer 4/6/2023 ARSALAN SHABESTARI
Corrections Issued 4/12/2023 ARSALAN SHABESTARI
Quality Review Completed 4/19/2023 GARO TELMI
Plan Check Approved 11/7/2025 ARSALAN SHABESTARI
Issued 11/17/2025 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 5/8/2023 NIKKI ZULUETA
BHO/Hillside ordinance Cleared 5/8/2023 NIKKI ZULUETA
BHO/Hillside ordinance Cleared 5/8/2023 NIKKI ZULUETA
BHO/Hillside ordinance Cleared 5/8/2023 NIKKI ZULUETA
BHO/Hillside ordinance Cleared 5/8/2023 NIKKI ZULUETA
ZA Case Cleared 5/8/2023 DANG NGUYEN
Hydrant and Access approval Cleared 6/2/2023 RUEL COLE
Eng Process Fee Ord 176,300 Cleared 6/5/2023 NIKKI ZULUETA
Construction near power lines Cleared 7/10/2023 RIDWAN HARDY
Construction within easement Cleared 7/10/2023 RIDWAN HARDY
Low Impact Development (LID) Cleared 3/20/2024 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 3/26/2024 BIAINA HARITUNIAN
Grading Pre-Inspection Cleared 12/19/2024 CHARLES POWELL
Address approval Cleared 12/20/2024 CARLOS RAMIREZ
Sewer availability Cleared 12/24/2024 CARLOS RAMIREZ
GPI Written Notices Cleared 10/30/2025 ARSALAN SHABESTARI

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/18/2025 Partial Inspection DAVID ANDERSON
Pre-Inspection 12/19/2025 Not Ready for Inspection DAVID MATSON
Deputy Drilled-In Anchors 1/12/2026 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 1/13/2026 Approved DAVID ANDERSON
BUILDING-Rough-Frame 2/2/2026 Not Ready for Inspection DAVID ANDERSON
Green Building Rough 2/2/2026 Not Ready for Inspection DAVID ANDERSON
Wood Frame 2/2/2026 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 2/5/2026 Approved DAVID ANDERSON
Insulation 2/5/2026 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 2/24/2026 Partial Approval MATTHEW NELSON
PLUMBING-Rough 3/23/2026 Approved DAVID ANDERSON
BUILDING-Rough-Frame 4/21/2026 Corrections Issued DAVID ANDERSON
ELECTRICAL-Rough 4/21/2026 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 4/21/2026 Approved DAVID ANDERSON
Green Building Rough 4/21/2026 Approved DAVID ANDERSON
HVAC-Rough 4/21/2026 Approved DAVID ANDERSON
Structural Steel Frame 4/21/2026 Corrections Issued DAVID ANDERSON
Deputy Wood Construction 4/23/2026 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 4/27/2026 Approved DAVID ANDERSON
Insulation 5/7/2026 Approved DAVID ANDERSON
Interior/Exterior Lathing 5/7/2026 Not Ready for Inspection DAVID ANDERSON
Drywall Nailing 5/12/2026 Approved DAVID ANDERSON
Shower Pan 5/12/2026 Approved DAVID ANDERSON
Interior/Exterior Lathing 5/18/2026 Partial Approval DAVID ANDERSON
Interior/Exterior Lathing 6/3/2026 Approved DAVID ANDERSON
Interior/Exterior Lathing 6/10/2026 Approved DAVID ANDERSON