4908 N DENSMORE AVE 91436

Certificate Information: 4908 N DENSMORE AVE 91436

Application / Permit
23010-20000-00819
Plan Check / Job No.
B23VN02473
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 32' X 20' DETACHED 1 STORY ACCESSORY DWLELING UNIT AS PER GCS 65852.2(E)(1)(B), NFPA-13D FIRE SPRINKLERS REQUIRED TROUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 7/15/2024
Issuing Office
Valley
Current Status
Issued on 7/15/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/28/2023 APPLICANT
Assigned to Plan Check Engineer 3/9/2023 RARES BODEA
Corrections Issued 3/17/2023 RARES BODEA
Quality Review Completed 3/22/2023 STEVEN KIM
Building Plans Picked Up 3/23/2023 APPLICANT
Plan Check Approved 10/3/2023 RARES BODEA
Issued 7/15/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/4/2023 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 4/25/2023 ROMAN GUTIERREZ
Sewer availability Cleared 4/25/2023 ROMAN GUTIERREZ
Hydrant and Access approval Cleared 5/5/2023 KURT CORRAL
Trees in Parkway Cleared 5/11/2023 ADALBERTO VERA
Construction near power lines Cleared 8/17/2023 RIDWAN HARDY
Low Impact Development (LID) Cleared 9/18/2023 LUIS LUVANO
Permit Cleared 9/23/2023 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 9/23/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 12/11/2024 Corrections Issued SEAN WIRCH
Underground Mechanical 5/15/2025 Approved JOHN COLEMAN
Footing/Foundation/Slab 5/23/2025 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 5/28/2025 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/30/2025 Corrections Issued THOMAS FINNILA
HVAC-Rough 10/27/2025 Partial Inspection THOMAS FINNILA
ELECTRICAL-Rough 11/17/2025 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 11/17/2025 Corrections Issued MORRIS JACKSON
HVAC-Rough 11/17/2025 Partial Approval MORRIS JACKSON
PLUMBING-Rough 11/25/2025 Approved THOMAS FINNILA
BUILDING-Rough-Frame 3/31/2026 Partial Approval JOHN KIDWELL
Green Building Rough 3/31/2026 Not Ready for Inspection JOHN KIDWELL
Verify Sprinkler Sign Off 3/31/2026 Approved JOHN KIDWELL
Interior/Exterior Lathing 4/3/2026 Partial Approval MORRIS JACKSON
Shower Pan 4/17/2026 Approved JOHN KIDWELL
Insulation 5/4/2026 Approved MORRIS JACKSON
Interior/Exterior Lathing 5/6/2026 Partial Approval JOHN KIDWELL
Drywall Nailing 5/15/2026 Approved JOHN KIDWELL