9761 N KESTER AVE 91343
Certificate Information: 9761 N KESTER AVE 91343
- Application / Permit
- 23010-20000-00780
- Plan Check / Job No.
- B23VN02373
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 25' X 34' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c) AND (d). WORK DONE PER WFPP AND ENGINEERED BEAM. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
- Permit Issued
- Issued on 4/5/2023
- Issuing Office
- Current Status
- CofO Issued on 4/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2023 | MADISON ODELL |
| Corrections Issued | 3/4/2023 | MADISON ODELL |
| Applicant returned to address corrections | 3/29/2023 | MADISON ODELL |
| Plan Check Approved | 4/5/2023 | MIROOSH KHACHATOORIAN |
| Issued | 4/5/2023 | APPLICANT |
| CofO in Progress | 2/14/2024 | JENNIFER RABUCHIN |
| Permit Finaled | 4/3/2024 | DANIEL ORRANTE |
| CofO Issued | 4/3/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/3/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/13/2023 | WALTER RAMIREZ |
| Construction within easement | Cleared | 3/13/2023 | WALTER RAMIREZ |
| Address approval | Cleared | 3/17/2023 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 3/17/2023 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/20/2023 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 3/20/2023 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 3/20/2023 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/6/2023 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 6/6/2023 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 6/6/2023 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 6/13/2023 | Conditional Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 8/4/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 8/4/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 8/4/2023 | Partial Approval | JENNIFER RABUCHIN |
| HVAC-Rough | 8/4/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/4/2023 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 8/4/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 8/18/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Insulation | 8/18/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 8/18/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 8/23/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 8/23/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 8/23/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 8/23/2023 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/6/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 9/6/2023 | Approved | JENNIFER RABUCHIN |
| Insulation | 9/6/2023 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 9/12/2023 | Approved | DAVID MATSON |
| Shower Pan | 10/5/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 10/11/2023 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/19/2024 | Approved | JENNIFER RABUCHIN |
| Final | 1/19/2024 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/19/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 1/19/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 1/19/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 2/13/2024 | Approved | JENNIFER RABUCHIN |
| Final | 2/13/2024 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 2/13/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 2/13/2024 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 2/13/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 2/13/2024 | Approved | JENNIFER RABUCHIN |