14289 W BERG ST 91342

Certificate Information: 14289 W BERG ST 91342

Application / Permit
23010-20000-00769
Plan Check / Job No.
B23VN02322
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 21'- 0" x 40'- 6" ONE STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 5/12/2023
Issuing Office
Valley
Current Status
CofO Issued on 7/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/24/2023 APPLICANT
Assigned to Plan Check Engineer 3/1/2023 ARTIN ZARUKIAN
Corrections Issued 3/4/2023 ARTIN ZARUKIAN
Building Plans Picked Up 3/13/2023 APPLICANT
Plan Check Approved 5/12/2023 GURUNATH NESARAJAH
Issued 5/12/2023 APPLICANT
CofO in Progress 7/24/2024 KEVIN BERBERYAN
CofO in Progress 6/26/2025 KEVIN BERBERYAN
CofO in Progress 7/9/2025 KEVIN BERBERYAN
Permit Finaled 7/22/2025 RUBEN SALAS
CofO Issued 7/22/2025 RUBEN SALAS
Permit Finaled 7/22/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/16/2023 FERNANDO GIL
Hydrant and Access approval Cleared 3/29/2023 KURT CORRAL
Eng Process Fee Ord 176,300 Cleared 4/17/2023 FERNANDO GIL
Sewer availability Cleared 4/17/2023 FERNANDO GIL
Low Impact Development (LID) Cleared 5/2/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 5/10/2023 FERNANDO GIL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/27/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 6/27/2023 Corrections Issued JENNIFER RABUCHIN
Sewer 6/27/2023 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 7/19/2023 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 8/8/2023 Approved DAVID ANDERSON
Green Building Rough 8/15/2023 Not Ready for Inspection KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 8/21/2023 Partial Approval DAVID ANDERSON
Verify Sprinkler Sign Off 8/21/2023 Approved DAVID ANDERSON
BUILDING-Rough-Frame 8/28/2023 Corrections Issued JACK KARGODORIAN
Green Building Rough 8/28/2023 Approved JACK KARGODORIAN
ELECTRICAL-Rough 8/31/2023 Corrections Issued KEVIN BERBERYAN
Interior/Exterior Lathing 8/31/2023 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 9/6/2023 Approved KEVIN BERBERYAN
ELECTRICAL-Rough 9/6/2023 Approved KEVIN BERBERYAN
PLUMBING-Rough 9/6/2023 Approved KEVIN BERBERYAN
Insulation 9/12/2023 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 9/18/2023 Partial Approval KEVIN BERBERYAN
Interior/Exterior Lathing 10/5/2023 Approved KEVIN BERBERYAN
Shower Pan 10/5/2023 Approved KEVIN BERBERYAN
Final 6/27/2024 Corrections Issued KEVIN BERBERYAN
Green Building Final 6/27/2024 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 6/27/2024 SGSOV Not Required KEVIN BERBERYAN
Service/Power Release 6/27/2024 Approved KEVIN BERBERYAN
Smoke Detectors 6/27/2024 Approved KEVIN BERBERYAN
Final 7/9/2025 OK to Issue CofO KEVIN BERBERYAN