137-139 W 57TH ST 90037

Certificate Information: 137-139 W 57TH ST 90037

Application / Permit
23010-20000-00709
Plan Check / Job No.
B23VN02085
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
*EPLAN* NEW 2-STORY DUPLEX WITH ATTACHED 3-CAR GARAGE.
Permit Issued
Issued on 8/24/2023
Issuing Office
Current Status
CofO Issued on 3/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/21/2023 APPLICANT
Assigned to Plan Check Engineer 2/23/2023 VIVIAN LAO
Corrections Issued 2/28/2023 VIVIAN LAO
Quality Review Completed 3/2/2023 GARO TELMI
Applicant returned to address corrections 5/30/2023 VIVIAN LAO
Plan Check Approved 6/13/2023 VIVIAN LAO
Issued 8/24/2023 APPLICANT
CofO in Progress 3/13/2024 ALEJANDRO DE ARTOLA
Permit Finaled 3/18/2024 DEROLD HAUFF
CofO Issued 3/18/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/17/2023 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 3/20/2023 CELINA MORENO
Sewer availability Cleared 3/20/2023 CELINA MORENO
Hydrant and Access approval Cleared 3/24/2023 KURT CORRAL
Low Impact Development (LID) Cleared 3/29/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 4/6/2023 CELINA MORENO
SB8 RUD Cleared 4/27/2023 NICHOLAS KAWAZOE

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/26/2023 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 10/6/2023 Approved ALEJANDRO DE ARTOLA
Wood Frame 10/6/2023 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/10/2023 Partial Approval ALEJANDRO DE ARTOLA
Insulation 10/10/2023 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/26/2023 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/17/2023 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Rough 11/30/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 11/30/2023 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 12/1/2023 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 12/1/2023 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 12/1/2023 Corrections Issued ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 12/1/2023 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 12/5/2023 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 12/5/2023 Approved ALEJANDRO DE ARTOLA
Green Building Rough 12/5/2023 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 12/5/2023 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 12/5/2023 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 12/6/2023 Approved ALEJANDRO DE ARTOLA
Insulation 12/6/2023 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 12/28/2023 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 12/28/2023 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 2/16/2024 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Final 3/8/2024 Approved ALEJANDRO DE ARTOLA
Final 3/8/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 3/8/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Final 3/8/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 3/8/2024 Approved ALEJANDRO DE ARTOLA
Pre-Inspection 3/8/2024 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 3/8/2024 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 3/8/2024 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 3/8/2024 Approved ALEJANDRO DE ARTOLA
Final 3/11/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 3/11/2024 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 3/11/2024 Approved ALEJANDRO DE ARTOLA
Final 3/12/2024 OK to Issue CofO ALEJANDRO DE ARTOLA
HVAC-Final 3/12/2024 Approved ALEJANDRO DE ARTOLA