NEW 22'-8" X 20' ACCESSORY LIVING QUARTERS WITH ATTACHED TRELLIS; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 7/27/2023
Issuing Office
Current Status
CofO Issued on 8/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/17/2023 APPLICANT
Assigned to Plan Check Engineer 2/23/2023 SELLA BENYAMIN
Corrections Issued 2/28/2023 SELLA BENYAMIN
Quality Review Completed 3/2/2023 STEVEN KIM
Building Plans Picked Up 3/2/2023 APPLICANT
Plan Check Approved 7/27/2023 SELLA BENYAMIN
Issued 7/27/2023 APPLICANT
CofO in Progress 6/17/2024 SEAN WIRCH
CofO Issued 8/22/2024 JOHN JANSON
Permit Finaled 8/22/2024 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/2/2023 CARLOS AGUILERA
Low Impact Development (LID) Cleared 3/28/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 4/1/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/11/2023 Approved VINCENT HANLEY
PLUMBING-Rough 8/11/2023 Partial Approval VINCENT HANLEY
Sewer 8/11/2023 Approved VINCENT HANLEY
Footing/Foundation/Slab 8/16/2023 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 10/19/2023 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 11/8/2023 Approved VINCENT HANLEY
HVAC-Rough 11/8/2023 Approved VINCENT HANLEY
PLUMBING-Rough 11/8/2023 Approved VINCENT HANLEY
Shower Pan 11/16/2023 Approved VINCENT HANLEY
BUILDING-Rough-Frame 11/22/2023 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 11/22/2023 Approved VINCENT HANLEY
Green Building Rough 11/22/2023 Not Ready for Inspection VINCENT HANLEY
Verify Sprinkler Sign Off 11/22/2023 Approved VINCENT HANLEY
BUILDING-Rough-Frame 12/6/2023 Approved VINCENT HANLEY
Green Building Rough 12/6/2023 Approved VINCENT HANLEY
Interior/Exterior Lathing 12/6/2023 Partial Approval VINCENT HANLEY
Insulation 12/8/2023 Approved VINCENT HANLEY
Interior/Exterior Lathing 12/14/2023 Approved VINCENT HANLEY
Drywall Nailing 12/15/2023 Approved VINCENT HANLEY
Special/Order Compliance 2/29/2024 Partial Approval VINCENT HANLEY
Special/Order Compliance 2/29/2024 Partial Inspection SEAN WIRCH
ELECTRICAL-Final 5/8/2024 Approved VINCENT HANLEY
HVAC-Final 5/8/2024 Corrections Issued VINCENT HANLEY
Service/Power Release 5/8/2024 Approved VINCENT HANLEY
Final 6/14/2024 OK to Issue CofO SEAN WIRCH
Green Building Final 6/14/2024 Approved SEAN WIRCH
HVAC-Final 6/14/2024 Approved SEAN WIRCH
PLUMBING-Final 6/14/2024 Approved SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 6/14/2024 SGSOV Approved SEAN WIRCH
Smoke Detectors 6/14/2024 Approved SEAN WIRCH