6736 N BUFFALO AVE 91401
Certificate Information: 6736 N BUFFALO AVE 91401
- Application / Permit
- 23010-20000-00690
- Plan Check / Job No.
- B23VN02057
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 30'-0" X 35'-1" IRREGEULAR SHAPED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 8/25/2023
- Issuing Office
- Current Status
- CofO Issued on 6/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 2/24/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 2/27/2023 | APPLICANT |
| Applicant returned to address corrections | 8/8/2023 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 8/11/2023 | SARKIS HARABEDIAN |
| Plan Check Approved | 8/25/2023 | ISIS ARGUETA |
| Issued | 8/25/2023 | APPLICANT |
| CofO in Progress | 6/11/2025 | GAREN HAYRAPETYAN |
| Permit Finaled | 6/13/2025 | RUBEN SALAS |
| CofO Issued | 6/13/2025 | RUBEN SALAS |
| Permit Finaled | 6/13/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/1/2023 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/1/2023 | JOSE DUARTE-DIAZ |
| Hydrant and Access approval | Cleared | 3/19/2023 | KURT CORRAL |
| Sewer availability | Cleared | 3/30/2023 | ROMAN GUTIERREZ |
| Low Impact Development (LID) | Cleared | 8/4/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 8/9/2023 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/26/2024 | Approved | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 3/18/2024 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 3/19/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Pre-Inspection | 3/19/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 4/3/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Deputy Reinf. Concrete | 4/4/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2024 | Approved | OGANES TARAKHCHYAN |
| Sewer | 6/6/2024 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 6/6/2024 | Approved | OGANES TARAKHCHYAN |
| Underground Mechanical | 6/6/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 6/14/2024 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 7/10/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 7/10/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 7/10/2024 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 7/18/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Rough | 7/18/2024 | Approved | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 7/18/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Insulation | 8/7/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Wood Frame | 8/7/2024 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 8/12/2024 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 8/21/2024 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 1/17/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Final | 1/17/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Final | 1/17/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 1/17/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Final | 1/17/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| HVAC-Final | 1/17/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| PLUMBING-Final | 1/17/2025 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 1/17/2025 | SGSOV No Gas | GAREN HAYRAPETYAN |
| Service/Power Release | 1/17/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Smoke Detectors | 1/17/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Final | 1/30/2025 | Approved | GAREN HAYRAPETYAN |
| Service/Power Release | 2/14/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Final | 5/22/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 5/22/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 5/22/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Final | 5/22/2025 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 5/22/2025 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 6/3/2025 | Approved | VINCENT HANLEY |
| Final | 6/3/2025 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 6/3/2025 | Approved | VINCENT HANLEY |
| HVAC-Final | 6/3/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 6/3/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 6/11/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 6/11/2025 | OK to Issue CofO | GAREN HAYRAPETYAN |
| HVAC-Final | 6/11/2025 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Final | 6/11/2025 | Approved | GAREN HAYRAPETYAN |