11215 W COHASSET ST 91352

Certificate Information: 11215 W COHASSET ST 91352

Application / Permit
23010-20000-00673
Plan Check / Job No.
B23VN02004
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan NEW 2- STORY 1,261 SQ.FT. (1,142.2 SQ.FT. RFA) SINGLE FAMILY DWELLING WITH ATTACHED 439 SQ.FT. GARAGE.
Permit Issued
Issued on 8/9/2023
Issuing Office
Current Status
CofO in Progress on 6/3/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/16/2023 APPLICANT
Assigned to Plan Check Engineer 3/2/2023 NGHI SU
Corrections Issued 3/10/2023 NGHI SU
Quality Review Completed 3/14/2023 GARO TELMI
Plan Check Approved 7/27/2023 NGHI SU
Issued 8/9/2023 APPLICANT
CofO in Progress 6/3/2026 JOSE AVILA

Permit Application Clearance Information

Low Impact Development (LID) Cleared 6/13/2023 MELINEH AGHAKHABIAN
Hydrant and Access approval Cleared 7/11/2023 GILBERT URREA
Roof/Waste drainage to street Cleared 7/11/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 7/11/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 7/12/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Baraty,, Patrick; Lic. No.: S5900 450 NORTH BRAND BLVD STE 600      GLENDALE, CA 91203

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/12/2023 Not Ready for Inspection JOHN HAYES
Underground Mechanical 9/12/2023 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 9/25/2023 Corrections Issued JOHN HAYES
PLUMBING-Rough 9/25/2023 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 10/3/2023 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 10/3/2023 Partial Inspection MISAEL ESPARZA
Footing/Foundation/Slab 10/10/2023 Corrections Issued JOHN HAYES
PLUMBING-Rough 10/10/2023 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 10/11/2023 Corrections Issued ROBERT GOLD
PLUMBING-Rough 10/11/2023 Not Ready for Inspection ROBERT GOLD
Footing/Foundation/Slab 10/19/2023 Approved ROBERT GOLD
PLUMBING-Rough 10/19/2023 Partial Approval ROBERT GOLD
BUILDING-Rough-Frame 11/2/2023 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 11/2/2023 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 11/7/2023 Partial Approval ROBERT GOLD
PLUMBING-Rough 11/7/2023 Partial Approval ROBERT GOLD
Verify Sprinkler Sign Off 11/7/2023 Not Ready for Inspection ROBERT GOLD
BUILDING-Rough-Frame 11/9/2023 Partial Approval ROBERT GOLD
Green Building Rough 11/9/2023 No Access for Inspection ROBERT GOLD
Verify Sprinkler Sign Off 11/9/2023 Not Ready for Inspection ROBERT GOLD
BUILDING-Rough-Frame 11/20/2023 Corrections Issued ROBERT GOLD
Green Building Rough 11/20/2023 Not Ready for Inspection ROBERT GOLD
Verify Sprinkler Sign Off 11/20/2023 Not Ready for Inspection ROBERT GOLD
Deputy Wood Construction 11/22/2023 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 12/18/2023 Corrections Issued ROBERT GOLD
Deputy Wood Construction 12/18/2023 Approved ROBERT GOLD
ELECTRICAL-Rough 12/18/2023 Corrections Issued ROBERT GOLD
Green Building Rough 12/18/2023 Not Ready for Inspection ROBERT GOLD
HVAC-Rough 12/18/2023 Corrections Issued ROBERT GOLD
PLUMBING-Rough 12/18/2023 Corrections Issued ROBERT GOLD
Verify Sprinkler Sign Off 12/18/2023 Not Ready for Inspection ROBERT GOLD
BUILDING-Rough-Frame 1/8/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 1/8/2024 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 1/8/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 1/8/2024 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 1/8/2024 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 1/8/2024 Corrections Issued CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 1/8/2024 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 1/26/2024 Not Ready for Inspection JUAN VALENZUELA
ELECTRICAL-Rough 1/26/2024 Not Ready for Inspection JUAN VALENZUELA
Green Building Rough 1/26/2024 Approved JUAN VALENZUELA
HVAC-Rough 1/26/2024 Approved JUAN VALENZUELA
Interior/Exterior Lathing 1/26/2024 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 1/26/2024 Approved JUAN VALENZUELA
Verify Sprinkler Sign Off 1/26/2024 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 1/30/2024 Partial Approval ROBERT GOLD
Interior/Exterior Lathing 1/30/2024 Partial Approval ROBERT GOLD
Rough-Elec/Plmb/HVAC 1/30/2024 Approved ROBERT GOLD
Insulation 2/2/2024 Approved JUAN VALENZUELA
Drywall Nailing 2/6/2024 Approved JUAN VALENZUELA
Interior/Exterior Lathing 2/6/2024 Approved JUAN VALENZUELA
Shower Pan 2/6/2024 Approved JUAN VALENZUELA
Sewer 6/12/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Underground Mechanical 6/12/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Underground Mechanical 6/18/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Underground Mechanical 6/24/2024 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 10/25/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 10/25/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 10/25/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Final 10/25/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Final 10/25/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 10/25/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 10/25/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 10/25/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Smoke Detectors 10/25/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 12/1/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 12/1/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 12/1/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 12/1/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 12/1/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Smoke Detectors 12/1/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 12/2/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 12/24/2025 Corrections Issued JOSE AVILA
PLUMBING-Final 12/31/2025 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 12/31/2025 SGSOV Approved JOSE AVILA
Final 6/1/2026 OK to Issue CofO JOSE AVILA
Green Building Final 6/1/2026 Approved JOSE AVILA
Service/Power Release 6/1/2026 Approved JOSE AVILA
Smoke Detectors 6/1/2026 Approved JOSE AVILA