9533 N COLUMBUS AVE 91343
Certificate Information: 9533 N COLUMBUS AVE 91343
- Application / Permit
- 23010-20000-00666
- Plan Check / Job No.
- B23VN02000
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 44'11" X 28' ONE STORY SFD per SB9 Two-Unit Development Ca Govt Code 65852.21 type V-A, ,NFPA 13-D FIRE SPRINKLERS THROUGHOUT , ALL WORK PER WFPP
- Permit Issued
- Issued on 5/31/2023
- Issuing Office
- Current Status
- CofO Issued on 3/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/23/2023 | RARES BODEA |
| Corrections Issued | 2/27/2023 | RARES BODEA |
| Quality Review Completed | 3/2/2023 | STEVEN KIM |
| Building Plans Picked Up | 5/9/2023 | APPLICANT |
| Plan Check Approved | 5/31/2023 | RARES BODEA |
| Issued | 5/31/2023 | APPLICANT |
| CofO in Progress | 1/31/2024 | JENNIFER RABUCHIN |
| Permit Finaled | 3/18/2024 | RUBEN SALAS |
| CofO Issued | 3/18/2024 | RUBEN SALAS |
| Permit Finaled | 3/18/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/6/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 3/6/2023 | COLIN LOREDO |
| Senate Bill 9 | Cleared | 4/19/2023 | STEVEN WECHSLER |
| Low Impact Development (LID) | Cleared | 5/15/2023 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 5/23/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 5/23/2023 | COLIN LOREDO |
| Hydrant and Access approval | Cleared | 5/31/2023 | GILBERT URREA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/7/2023 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 6/7/2023 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 6/21/2023 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 6/21/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/21/2023 | Partial Approval | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 6/21/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2023 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/26/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/26/2023 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 7/26/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 7/26/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 8/14/2023 | Approved | DAVID MATSON |
| HVAC-Rough | 8/14/2023 | Approved | DAVID MATSON |
| PLUMBING-Rough | 8/14/2023 | Approved | DAVID MATSON |
| Underground Mechanical | 8/14/2023 | Partial Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 8/16/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 8/16/2023 | Approved | DAVID ANDERSON |
| Underground Mechanical | 8/16/2023 | Partial Approval | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 8/16/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 8/21/2023 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 8/30/2023 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 8/30/2023 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 9/7/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 9/7/2023 | Approved | JENNIFER RABUCHIN |
| Final | 1/16/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 1/16/2024 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/16/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 1/16/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 1/16/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 1/30/2024 | Approved | JENNIFER RABUCHIN |
| Final | 1/30/2024 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 1/30/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 1/30/2024 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 1/30/2024 | Approved | JENNIFER RABUCHIN |