2225 1/2-3/4 S CLYDE AVE 90016

Certificate Information: 2225 1/2-3/4 S CLYDE AVE 90016

Application / Permit
23010-20000-00662
Plan Check / Job No.
B23VN01995
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW GROUND FLOOR ACCESSORY DWELLING UNIT, CARPORT, AND PATIO COVER WITH 2ND FLOOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c)1, (d)1, and (g)
Permit Issued
Issued on 5/30/2024
Issuing Office
Metro
Current Status
CofO Issued on 4/17/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/16/2023 APPLICANT
Assigned to Plan Check Engineer 2/24/2023 JEROME MAGAT PALMA
Corrections Issued 2/25/2023 JEROME MAGAT PALMA
Building Plans Picked Up 2/27/2023 APPLICANT
Applicant returned to address corrections 3/28/2023 ISIS ARGUETA
Plan Check Approved 5/22/2023 PINANK PATEL
Issued 5/30/2024 APPLICANT
CofO in Progress 11/21/2025 ARTHUR NEGRETE
No Progress 11/23/2025 DEROLD HAUFF
CofO in Progress 11/23/2025 DEROLD HAUFF
CofO in Progress 4/17/2026 BRENDAN MORELLI
Permit Finaled 4/17/2026 DEROLD HAUFF
CofO Issued 4/17/2026 DEROLD HAUFF
Permit Finaled 4/17/2026 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/16/2023 CINDY QI
Sewer availability Cleared 3/16/2023 CINDY QI
Address approval Cleared 3/21/2023 CINDY QI
Hydrant and Access approval Cleared 3/31/2023 LAVEON RIDER
Low Impact Development (LID) Cleared 5/11/2023 ERNEST TSE
Construction near power lines Cleared 5/12/2023 RIDWAN HARDY
Roof/Waste drainage to street Cleared 5/22/2023 TREVOR QUAN

Contact Information

Contractor Truebuilt Construction Inc; Lic. No.: 1052087-B 950 E KATELLA AVE STE 5      ORANGE, CA 92867
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/24/2024 Approved ENRIQUE MIRELES
Underground Mechanical 6/24/2024 Corrections Issued ENRIQUE MIRELES
Sewer 6/25/2024 Off-Hour Fees Due
Sewer 6/26/2024 Approved ENRIQUE MIRELES
Underground Mechanical 6/26/2024 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 6/28/2024 Not Ready for Inspection ENRIQUE MIRELES
Footing/Foundation/Slab 6/28/2024 Not Ready for Inspection ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 7/2/2024 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 7/23/2024 Partial Approval JUSTIN HAWLEY
BUILDING-Rough-Frame 8/12/2024 Not Ready for Inspection ARTHUR NEGRETE
Green Building Rough 8/12/2024 Not Ready for Inspection ARTHUR NEGRETE
Special/Order Compliance 8/12/2024 Partial Approval NICHOLAS LOPEZ
Verify Sprinkler Sign Off 8/12/2024 Not Ready for Inspection ARTHUR NEGRETE
Wood Frame 8/12/2024 Not Ready for Inspection ARTHUR NEGRETE
BUILDING-Rough-Frame 8/20/2024 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 8/20/2024 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 8/20/2024 Not Ready for Inspection ENRIQUE MIRELES
HVAC-Rough 8/20/2024 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 8/20/2024 Not Ready for Inspection ENRIQUE MIRELES
Verify Sprinkler Sign Off 8/20/2024 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 8/21/2024 Not Ready for Inspection ARTHUR NEGRETE
HVAC-Rough 8/21/2024 Not Ready for Inspection ARTHUR NEGRETE
PLUMBING-Rough 8/21/2024 Not Ready for Inspection ARTHUR NEGRETE
ELECTRICAL-Rough 8/28/2024 Not Ready for Inspection ARTHUR NEGRETE
HVAC-Rough 8/28/2024 Not Ready for Inspection ARTHUR NEGRETE
PLUMBING-Rough 8/28/2024 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 9/3/2024 Corrections Issued RONNIE MINDANAO
BUILDING-Rough-Frame 9/4/2024 Partial Approval ARTHUR NEGRETE
ELECTRICAL-Rough 9/4/2024 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 9/4/2024 Approved ARTHUR NEGRETE
Green Building Rough 9/4/2024 Approved ARTHUR NEGRETE
HVAC-Rough 9/4/2024 Approved ARTHUR NEGRETE
PLUMBING-Rough 9/4/2024 Approved ARTHUR NEGRETE
Verify Sprinkler Sign Off 9/4/2024 Approved ARTHUR NEGRETE
ELECTRICAL-Rough 9/5/2024 Approved ENRIQUE MIRELES
HVAC-Rough 9/5/2024 Approved ENRIQUE MIRELES
PLUMBING-Rough 9/5/2024 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 9/12/2024 Not Ready for Inspection ARTHUR NEGRETE
Drywall Nailing 9/17/2024 Approved BRENDAN MORELLI
Interior/Exterior Lathing 9/20/2024 Conditional Approval RONNIE MINDANAO
Shower Pan 10/7/2024 Approved JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 10/30/2024 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 3/5/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Final 3/5/2025 Approved ARTHUR NEGRETE
Final 3/5/2025 Partial Inspection ARTHUR NEGRETE
Footing/Foundation/Slab 3/5/2025 Approved ARTHUR NEGRETE
Green Building Final 3/5/2025 Partial Approval ARTHUR NEGRETE
HVAC-Final 3/5/2025 Approved ARTHUR NEGRETE
PLUMBING-Final 3/5/2025 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 3/5/2025 SGSOV Not Required ARTHUR NEGRETE
Service/Power Release 3/5/2025 Approved ARTHUR NEGRETE
Smoke Detectors 3/5/2025 Approved ARTHUR NEGRETE
Special/Order Compliance 3/5/2025 Partial Inspection ALEX COLIN
Final 11/17/2025 OK to Issue CofO ARTHUR NEGRETE
Green Building Final 11/17/2025 Approved ARTHUR NEGRETE
Special/Order Compliance 1/6/2026 Corrections Issued BRENDAN MORELLI
Special/Order Compliance 2/2/2026 Corrections Issued BRENDAN MORELLI
Final 4/16/2026 OK to Issue CofO BRENDAN MORELLI