4814 N DEMPSEY AVE 91436

Certificate Information: 4814 N DEMPSEY AVE 91436

Application / Permit
23010-20000-00650
Plan Check / Job No.
B23VN01940
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 37'-0" X 14'-0" DETACHED ACCESSORY DWELLING UNIT WITH 6'-0" X 13' 1 1/2" OPEN TRELLIS PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g). FIRE SPRINKLER REQUIRED THROUGHOUT. WORK PER ENGINEER
Permit Issued
Issued on 6/13/2023
Issuing Office
Current Status
CofO Issued on 3/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/16/2023 APPLICANT
Assigned to Plan Check Engineer 2/22/2023 ARTIN ZARUKIAN
Corrections Issued 2/23/2023 ARTIN ZARUKIAN
Building Plans Picked Up 3/13/2023 APPLICANT
Plan Check Approved 6/13/2023 RAMA DABADGE
Issued 6/13/2023 APPLICANT
CofO in Progress 2/20/2024 VINCENT HANLEY
Permit Finaled 3/27/2024 JOHN JANSON
CofO Issued 3/27/2024 JOHN JANSON
Permit Finaled 3/27/2024 JOHN JANSON

Permit Application Clearance Information

Hydrant and Access approval Cleared 3/11/2023 MATTHEW CRAIG
Construction near power lines Cleared 6/6/2023 RIDWAN HARDY
Stormwater Pollution Mitigatn Cleared 6/6/2023 ERNEST TSE
Address approval Cleared 6/10/2023 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 6/10/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 6/12/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 6/12/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/15/2023 Approved VINCENT HANLEY
Footing/Foundation/Slab 6/15/2023 Approved VINCENT HANLEY
PLUMBING-Rough 6/15/2023 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 7/6/2023 Corrections Issued VINCENT HANLEY
HVAC-Rough 7/6/2023 Corrections Issued VINCENT HANLEY
ELECTRICAL-Rough 7/10/2023 Approved VINCENT HANLEY
HVAC-Rough 7/10/2023 Approved VINCENT HANLEY
Shower Pan 7/12/2023 Approved VINCENT HANLEY
Insulation 7/17/2023 Approved VINCENT HANLEY
Drywall Nailing 7/20/2023 Partial Inspection JUSTIN HAWLEY
Green Building Rough 7/20/2023 Corrections Issued JUSTIN HAWLEY
BUILDING-Rough-Frame 7/21/2023 Approved VINCENT HANLEY
Drywall Nailing 7/21/2023 Approved VINCENT HANLEY
Green Building Rough 7/21/2023 Approved VINCENT HANLEY
Insulation 7/21/2023 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 7/21/2023 Approved VINCENT HANLEY
Interior/Exterior Lathing 7/26/2023 Approved VINCENT HANLEY
ELECTRICAL-Final 12/26/2023 Approved VINCENT HANLEY
HVAC-Final 12/26/2023 Approved VINCENT HANLEY
ELECTRICAL-Final 1/8/2024 Approved VINCENT HANLEY
Final 1/8/2024 Not Ready for Inspection VINCENT HANLEY
Green Building Final 1/8/2024 Approved VINCENT HANLEY
HVAC-Final 1/8/2024 Approved VINCENT HANLEY
PLUMBING-Final 1/8/2024 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 1/8/2024 SGSOV Approved VINCENT HANLEY
Service/Power Release 1/8/2024 Approved VINCENT HANLEY
Smoke Detectors 1/8/2024 Approved VINCENT HANLEY
Final 2/16/2024 OK to Issue CofO VINCENT HANLEY