12014 W HARTSOOK ST 91607

Certificate Information: 12014 W HARTSOOK ST 91607

Application / Permit
23010-20000-00588
Plan Check / Job No.
B23VN01674
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 12'6" X 18' RECREATION ROOM WITH HALF A BATHROOM AND WITH SHOWER WITH EXTERIOR ACCESS, ALL WORK PER ENGINEERING
Permit Issued
Issued on 5/9/2023
Issuing Office
Valley
Current Status
CofO Issued on 5/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/10/2023 APPLICANT
Assigned to Plan Check Engineer 2/23/2023 RARES BODEA
Corrections Issued 2/27/2023 RARES BODEA
Quality Review Completed 3/2/2023 STEVEN KIM
Building Plans Picked Up 3/3/2023 APPLICANT
Plan Check Approved 5/8/2023 RARES BODEA
Issued 5/9/2023 APPLICANT
CofO in Progress 4/18/2024 CHRISTOPHER ROJAS
Permit Finaled 5/8/2024 RUBEN SALAS
CofO Issued 5/8/2024 RUBEN SALAS
Permit Finaled 5/8/2024 RUBEN SALAS

Permit Application Clearance Information

Hydrant and Access approval Cleared 3/27/2023 KURT CORRAL
Specific Plan Cleared 3/28/2023 JOANNA MARROQUIN
ZI Cleared 3/28/2023 JOANNA MARROQUIN
ZI Cleared 3/28/2023 JOANNA MARROQUIN
Low Impact Development (LID) Cleared 4/17/2023 TOMMY YIN
Eng Process Fee Ord 176,300 Cleared 4/20/2023 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 4/20/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/24/2023 Partial Approval RAUL OLAGI
Sewer 5/24/2023 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 6/16/2023 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 7/6/2023 Corrections Issued JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 8/22/2023 Partial Approval THOMAS FINNILA
PLUMBING-Rough 8/31/2023 Approved JACK KARGODORIAN
ELECTRICAL-Rough 9/7/2023 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 9/7/2023 Not Ready for Inspection MISAEL ESPARZA
Deputy Wood Construction 9/8/2023 Conditional Approval JUAN VALENZUELA
HVAC-Rough 9/8/2023 Partial Inspection THOMAS FINNILA
ELECTRICAL-Rough 9/12/2023 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/12/2023 Partial Approval THOMAS FINNILA
HVAC-Rough 9/12/2023 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/22/2023 Approved JACK KARGODORIAN
Shower Pan 9/22/2023 Approved JACK KARGODORIAN
Interior/Exterior Lathing 9/29/2023 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 10/12/2023 Corrections Issued MISAEL ESPARZA
Green Building Rough 10/12/2023 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 10/12/2023 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 10/17/2023 Approved MICHEL ABAJAN
Underground Mechanical 10/17/2023 Partial Approval MICHEL ABAJAN
Insulation 10/20/2023 Approved JUAN VALENZUELA
Drywall Nailing 10/25/2023 Approved JUAN VALENZUELA
ELECTRICAL-Final 2/2/2024 Corrections Issued CRAIG DAVIS
HVAC-Final 2/6/2024 Partial Approval KIRK SANDERS
ELECTRICAL-Final 2/8/2024 Approved KIRK SANDERS
HVAC-Final 2/8/2024 Corrections Issued KIRK SANDERS
Final 2/22/2024 Corrections Issued KIRK SANDERS
Green Building Final 2/22/2024 Approved KIRK SANDERS
HVAC-Final 2/22/2024 Approved KIRK SANDERS
PLUMBING-Final 2/22/2024 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 2/22/2024 SGSOV Approved KIRK SANDERS
Service/Power Release 2/22/2024 Not Ready for Inspection KIRK SANDERS
Smoke Detectors 2/22/2024 Approved KIRK SANDERS
PLUMBING-Final 2/28/2024 Approved KIRK SANDERS
Service/Power Release 2/28/2024 Not Ready for Inspection KIRK SANDERS
Final 4/17/2024 OK to Issue CofO CHRISTOPHER ROJAS
Service/Power Release 4/17/2024 Approved CHRISTOPHER ROJAS