642 W 45TH ST 90037
Certificate Information: 642 W 45TH ST 90037
- Application / Permit
- 23010-20000-00583
- Plan Check / Job No.
- B23VN00382
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: NEW 2-STORY ADU AT REAR OF LOT W/ ATTACHED TWO-CAR GARAGE. FIRE SPRINKLER NFPA 13D THROUGHOUT.
- Permit Issued
- Issued on 6/12/2024
- Issuing Office
- Current Status
- CofO Issued on 2/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/7/2023 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 2/13/2023 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 2/18/2023 | GARO TELMI |
| Applicant returned to address corrections | 3/22/2024 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 3/28/2024 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 3/28/2024 | FARSHAD ALIMOHAMADI |
| No Progress | 5/24/2024 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 5/24/2024 | FARSHAD ALIMOHAMADI |
| No Progress | 6/11/2024 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 6/11/2024 | FARSHAD ALIMOHAMADI |
| No Progress | 6/11/2024 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 6/11/2024 | FARSHAD ALIMOHAMADI |
| Issued | 6/12/2024 | APPLICANT |
| CofO in Progress | 2/26/2026 | RAUL BARAJAS |
| Permit Finaled | 2/28/2026 | DEROLD HAUFF |
| Permit Finaled | 2/28/2026 | DEROLD HAUFF |
| CofO Issued | 2/28/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/10/2023 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2023 | WALLIE JONG |
| ZI | Cleared | 8/22/2023 | RUBEN VASQUEZ |
| Sewer availability | Cleared | 8/23/2023 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 9/8/2023 | LAVEON RIDER |
| Construction near power lines | Cleared | 3/2/2024 | RIDWAN HARDY |
| Stormwater Pollution Mitigatn | Cleared | 3/15/2024 | LUIS CRUZ |
| Roof/Waste drainage to street | Cleared | 3/19/2024 | JUSTIN BICOL |
Contact Information
| Contractor | Pacific Rim Construction Group Inc; Lic. No.: 995891-B | 540 WEST 45TH STREET LOS ANGELES, CA 90037 |
| Engineer | Nuno,, Arnulfo; Lic. No.: C88425 | 7057 DWIGHT WAY SAN BERNARDINO, CA 92404 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 10/16/2024 | Corrections Issued | CRAIG DAVIS |
| Underground Mechanical | 10/18/2024 | Partial Approval | BRENDAN MORELLI |
| Footing/Foundation/Slab | 10/23/2024 | Approved | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2024 | Partial Approval | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2024 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Rough | 1/29/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Rough | 2/4/2025 | Approved | BARRY HACHE |
| PLUMBING-Rough | 2/4/2025 | Not Ready for Inspection | BARRY HACHE |
| PLUMBING-Rough | 2/11/2025 | Corrections Issued | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2025 | No Access for Inspection | BARRY HACHE |
| PLUMBING-Rough | 2/14/2025 | No Access for Inspection | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2025 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Rough | 2/19/2025 | Approved | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2025 | Approved | BARRY HACHE |
| Rough-Elec/Plmb/HVAC | 2/25/2025 | Not Ready for Inspection | BARRY HACHE |
| Green Building Rough | 2/28/2025 | Corrections Issued | BARRY HACHE |
| Interior/Exterior Lathing | 3/10/2025 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 3/18/2025 | Not Ready for Inspection | BARRY HACHE |
| Green Building Rough | 3/18/2025 | Approved | BARRY HACHE |
| HVAC-Rough | 3/18/2025 | Corrections Issued | BARRY HACHE |
| Verify Sprinkler Sign Off | 3/18/2025 | Not Ready for Inspection | BARRY HACHE |
| BUILDING-Rough-Frame | 3/21/2025 | Not Ready for Inspection | BARRY HACHE |
| Verify Sprinkler Sign Off | 3/21/2025 | Not Ready for Inspection | BARRY HACHE |
| BUILDING-Rough-Frame | 3/24/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Rough | 3/24/2025 | Approved | BARRY HACHE |
| Verify Sprinkler Sign Off | 3/24/2025 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 4/3/2025 | Approved | BARRY HACHE |
| Verify Sprinkler Sign Off | 4/3/2025 | Approved | BARRY HACHE |
| Wood Frame | 4/3/2025 | Approved | BARRY HACHE |
| Insulation | 4/11/2025 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 4/11/2025 | Approved | BARRY HACHE |
| Drywall Nailing | 4/28/2025 | Approved | ANTHONY RAMOS |
| Sewer | 7/17/2025 | Approved | BARRY HACHE |
| Service/Power Release | 9/24/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 2/10/2026 | Corrections Issued | BARRY HACHE |
| HVAC-Final | 2/10/2026 | Corrections Issued | BARRY HACHE |
| PLUMBING-Final | 2/10/2026 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Final | 2/12/2026 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Final | 2/12/2026 | Not Ready for Inspection | LUIS CASTRO |
| PLUMBING-Final | 2/12/2026 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Final | 2/13/2026 | Approved | RAUL BARAJAS |
| Final | 2/13/2026 | Not Ready for Inspection | RAUL BARAJAS |
| HVAC-Final | 2/13/2026 | Approved | RAUL BARAJAS |
| PLUMBING-Final | 2/13/2026 | Approved | RAUL BARAJAS |
| Final | 2/25/2026 | OK to Issue CofO | RAUL BARAJAS |
| Green Building Final | 2/25/2026 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 2/25/2026 | SGSOV Approved | RAUL BARAJAS |
| Service/Power Release | 2/25/2026 | Approved | RAUL BARAJAS |
| Smoke Detectors | 2/25/2026 | Approved | RAUL BARAJAS |