8416 N ENCINO AVE 91325
Certificate Information: 8416 N ENCINO AVE 91325
- Application / Permit
- 23010-20000-00580
- Plan Check / Job No.
- B23VN01658
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 21'-9" x 41'-9" IRR. SHAPED ONE-STORY DET. ACCESSORY DWELLING UNIT [PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)]; NFPA-13D THRU-OUT
- Permit Issued
- Issued on 8/8/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/23/2023 | SEAN SHAHMIRI |
| Corrections Issued | 3/6/2023 | SEAN SHAHMIRI |
| Quality Review Completed | 3/8/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 3/9/2023 | APPLICANT |
| Applicant returned to address corrections | 5/16/2023 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 7/27/2023 | SEAN SHAHMIRI |
| Plan Check Approved | 8/7/2023 | SEAN SHAHMIRI |
| Issued | 8/8/2023 | APPLICANT |
| CofO in Progress | 10/3/2025 | NICHOLAS TROWBRIDGE |
| CofO Issued | 10/23/2025 | RUBEN SALAS |
| Permit Finaled | 10/23/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/6/2023 | MEGAN GODINEZ |
| Hydrant and Access approval | Cleared | 3/20/2023 | MATTHEW CRAIG |
| Low Impact Development (LID) | Cleared | 4/25/2023 | ERNEST TSE |
| Eng Process Fee Ord 176,300 | Cleared | 4/26/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 4/26/2023 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 7/27/2023 | MEGAN GODINEZ |
| SB8 RUD | Cleared | 7/27/2023 | BLAKE BOULIGNY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/13/2023 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 11/6/2023 | Approved | JAVIER RAMOS JR |
| Deputy Reinf. Concrete | 11/7/2023 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2024 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 5/13/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 5/13/2024 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 5/22/2024 | Approved | JAVIER RAMOS JR |
| Sewer | 6/6/2024 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 8/21/2024 | Corrections Issued | JAVIER RAMOS JR |
| Insulation | 8/21/2024 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 8/21/2024 | Partial Approval | JAVIER RAMOS JR |
| Shower Pan | 8/21/2024 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/3/2024 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2024 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 9/3/2024 | Approved | JAVIER RAMOS JR |
| Insulation | 9/3/2024 | Approved | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 9/3/2024 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 10/2/2024 | Approved | MICHAEL CORTEZ |
| Drywall Nailing | 8/28/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 8/28/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 8/28/2025 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 8/28/2025 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Service/Power Release | 8/28/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 8/28/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 9/8/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Service/Power Release | 9/8/2025 | No Access for Inspection | NICHOLAS TROWBRIDGE |
| Final | 10/2/2025 | OK to Issue CofO | NICHOLAS TROWBRIDGE |
| Service/Power Release | 10/2/2025 | Approved | NICHOLAS TROWBRIDGE |