13060 W OTSEGO ST 91423
Certificate Information: 13060 W OTSEGO ST 91423
- Application / Permit
- 23010-20000-00553
- Plan Check / Job No.
- B23VN01545
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 42' X 65'-6" IRREGULAR SHAPED 2-STORY SFD W/ 2-CAR GARAGE. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/26/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/23/2023 | RAPHAEL ROSAS |
| Corrections Issued | 2/27/2023 | RAPHAEL ROSAS |
| Quality Review Completed | 3/2/2023 | STEVEN KIM |
| Building Plans Picked Up | 3/2/2023 | APPLICANT |
| Applicant returned to address corrections | 5/26/2023 | RAPHAEL ROSAS |
| Plan Check Approved | 5/26/2023 | RAPHAEL ROSAS |
| Issued | 5/26/2023 | APPLICANT |
| CofO in Progress | 3/13/2024 | JOSE AVILA |
| Permit Finaled | 4/13/2024 | RUBEN SALAS |
| CofO Issued | 4/13/2024 | RUBEN SALAS |
| Permit Finaled | 4/13/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/29/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 3/30/2023 | DAGOVERTO GUERRERO |
| Low Impact Development (LID) | Cleared | 4/13/2023 | ANTHONY VARGAS |
| Hydrant and Access approval | Cleared | 4/17/2023 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 4/17/2023 | NIKKI ZULUETA |
| Trees in Parkway | Cleared | 5/11/2023 | ADALBERTO VERA |
| Permit | Cleared | 5/16/2023 | NIKKI ZULUETA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/2/2023 | Not Ready for Inspection | KIRK SANDERS |
| Sewer | 6/2/2023 | Approved | KIRK SANDERS |
| Underground Mechanical | 6/2/2023 | Approved | KIRK SANDERS |
| Footing/Foundation/Slab | 6/15/2023 | Approved | KIRK SANDERS |
| Deputy Other (see comments) | 6/16/2023 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2023 | Partial Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2023 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 8/30/2023 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 9/6/2023 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2023 | Partial Approval | KIRK SANDERS |
| HVAC-Rough | 9/6/2023 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 9/6/2023 | Approved | KIRK SANDERS |
| Deputy Wood Construction | 9/7/2023 | Conditional Approval | JUAN VALENZUELA |
| HVAC-Rough | 9/14/2023 | Conditional Approval | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Shower Pan | 9/20/2023 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 9/21/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 9/26/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2023 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 9/26/2023 | Partial Approval | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 10/3/2023 | Corrections Issued | KIRK SANDERS |
| Underground Mechanical | 10/3/2023 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 10/12/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 10/12/2023 | Approved | KIRK SANDERS |
| Underground Mechanical | 10/12/2023 | Approved | KIRK SANDERS |
| Wood Frame | 10/12/2023 | Not Ready for Inspection | KIRK SANDERS |
| BUILDING-Rough-Frame | 10/18/2023 | Corrections Issued | KIRK SANDERS |
| Green Building Rough | 10/18/2023 | Approved | KIRK SANDERS |
| Verify Sprinkler Sign Off | 10/18/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 10/26/2023 | Approved | JUAN VALENZUELA |
| Insulation | 10/26/2023 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 11/3/2023 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 2/1/2024 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 2/1/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 2/7/2024 | Approved | JOSE AVILA |
| HVAC-Final | 2/21/2024 | Approved | JOSE AVILA |
| Final | 2/26/2024 | Not Ready for Inspection | JOSE AVILA |
| Final | 2/27/2024 | Not Ready for Inspection | JOSE AVILA |
| Green Building Final | 2/27/2024 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 2/27/2024 | SGSOV Approved | JOSE AVILA |
| Service/Power Release | 2/27/2024 | Not Ready for Inspection | JOSE AVILA |
| Smoke Detectors | 2/27/2024 | Approved | JOSE AVILA |
| Final | 2/29/2024 | Partial Approval | JOSE AVILA |
| Service/Power Release | 2/29/2024 | Approved | JOSE AVILA |
| Final | 3/13/2024 | OK to Issue CofO | JOSE AVILA |