1159-1159 1/2 E 43RD PL 90011
Certificate Information: 1159-1159 1/2 E 43RD PL 90011
- Application / Permit
- 23010-20000-00546
- Plan Check / Job No.
- B23VN01534
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (eplan) NEW TWO STORY DUPLEX WITH ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (e).
- Permit Issued
- Issued on 10/15/2024
- Issuing Office
- Current Status
- CofO Issued on 6/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/23/2023 | YOUNG KIM |
| Corrections Issued | 2/28/2023 | YOUNG KIM |
| Quality Review Completed | 3/7/2023 | FARUK SEZER |
| Applicant returned to address corrections | 8/16/2023 | YOUNG KIM |
| Applicant returned to address corrections | 8/24/2023 | YOUNG KIM |
| Applicant returned to address corrections | 8/31/2023 | YOUNG KIM |
| Applicant returned to address corrections | 9/20/2023 | YOUNG KIM |
| Plan Check Approved | 9/28/2023 | YOUNG KIM |
| Issued | 10/15/2024 | APPLICANT |
| CofO in Progress | 5/28/2025 | ALEJANDRO DE ARTOLA |
| No Progress | 6/1/2025 | DEROLD HAUFF |
| CofO in Progress | 6/1/2025 | DEROLD HAUFF |
| Permit Finaled | 6/5/2025 | DEROLD HAUFF |
| CofO Issued | 6/5/2025 | DEROLD HAUFF |
| Permit Finaled | 6/5/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/10/2023 | CELINA MORENO |
| Permit | Cleared | 3/10/2023 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2023 | CELINA MORENO |
| Sewer availability | Cleared | 3/15/2023 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 4/14/2023 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 5/9/2023 | CELINA MORENO |
| SB8 RUD | Cleared | 5/11/2023 | KENNETH LE |
| Low Impact Development (LID) | Cleared | 7/5/2023 | TOMMY YIN |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/18/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 12/13/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 1/3/2025 | Approved | ENRIQUE MIRELES |
| Wood Frame | 1/3/2025 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2025 | Not Ready for Inspection | BARRY HACHE |
| Insulation | 1/6/2025 | Not Ready for Inspection | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 3/7/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 3/7/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 3/7/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 3/10/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 3/10/2025 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 3/10/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 3/10/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 3/10/2025 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 3/10/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 3/11/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 3/11/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 3/18/2025 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 3/18/2025 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 3/18/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 3/19/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 5/9/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 5/13/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 5/20/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 5/20/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 5/20/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 5/22/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 5/22/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 5/22/2025 | Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 5/22/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 5/22/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 5/22/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 5/22/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 5/22/2025 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Service/Power Release | 5/22/2025 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 5/22/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 5/27/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Gas Test | 5/27/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 5/27/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 5/27/2025 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 5/27/2025 | SGSOV Approved | ALEJANDRO DE ARTOLA |