14812 W HUSTON ST 91403

Certificate Information: 14812 W HUSTON ST 91403

Application / Permit
23010-20000-00402
Plan Check / Job No.
B23VN01225
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW IRR. SHAPED 37' x 64'-6" TWO-STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE AND OPEN TRELLIS; NFPA-13D THRU-OUT
Permit Issued
Issued on 5/31/2023
Issuing Office
Current Status
CofO Issued on 2/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/1/2023 APPLICANT
Assigned to Plan Check Engineer 2/16/2023 SEAN SHAHMIRI
Corrections Issued 2/21/2023 SEAN SHAHMIRI
Building Plans Picked Up 2/23/2023 APPLICANT
Quality Review Completed 5/18/2023 OMID HEDAYAT
Applicant returned to address corrections 5/18/2023 SEAN SHAHMIRI
Plan Check Approved 5/30/2023 SEAN SHAHMIRI
Issued 5/31/2023 APPLICANT
CofO in Progress 2/2/2024 RAUL OLAGI
Permit Finaled 2/22/2024 RUBEN SALAS
CofO Issued 2/22/2024 RUBEN SALAS
Permit Finaled 2/22/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/7/2023 MEGAN GODINEZ
Sewer availability Cleared 3/7/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 3/21/2023 MEGAN GODINEZ
Hydrant and Access approval Cleared 3/25/2023 RUEL COLE
Stormwater Pollution Mitigatn Cleared 4/11/2023 LUIS LUVANO
Trees in Parkway Cleared 5/2/2023 ADALBERTO VERA
ZI Cleared 5/2/2023 STEVEN WECHSLER
Roof/Waste drainage to street Cleared 5/9/2023 MEGAN GODINEZ
Permit Cleared 5/17/2023 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/13/2023 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 6/22/2023 Corrections Issued THOMAS FINNILA
Deputy Reinf. Concrete 6/23/2023 Conditional Approval DAVID MATSON
Deputy Reinf. Concrete 6/23/2023 Conditional Approval MICHAEL SMITH
Floor/Roof Diaphrgm/Shear Wall 7/6/2023 Partial Approval JACK KARGODORIAN
Deputy Steel/Welding 7/17/2023 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/17/2023 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/19/2023 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/24/2023 Not Ready for Inspection THOMAS FINNILA
Deputy Drilled-In Anchors 7/26/2023 Conditional Approval DAVID MATSON
PLUMBING-Rough 8/3/2023 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 8/7/2023 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 8/7/2023 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 8/7/2023 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/9/2023 Not Ready for Inspection THOMAS FINNILA
MERV13>=Rough 8/14/2023 Corrections Issued THOMAS FINNILA
Verify Sprinkler Sign Off 8/14/2023 Approved THOMAS FINNILA
ELECTRICAL-Rough 8/18/2023 Approved THOMAS FINNILA
HVAC-Rough 8/18/2023 Approved THOMAS FINNILA
PLUMBING-Rough 8/18/2023 Approved THOMAS FINNILA
Shower Pan 8/18/2023 Approved THOMAS FINNILA
BUILDING-Rough-Frame 8/25/2023 Approved THOMAS FINNILA
Green Building Rough 8/25/2023 Approved THOMAS FINNILA
MERV13>=Rough 8/25/2023 Approved THOMAS FINNILA
Interior/Exterior Lathing 8/29/2023 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 8/31/2023 Partial Approval CHRISTOPHER ROJAS
Insulation 9/5/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 9/5/2023 Approved MISAEL ESPARZA
Drywall Nailing 9/13/2023 Approved THOMAS FINNILA
ELECTRICAL-Final 12/1/2023 Not Ready for Inspection THOMAS FINNILA
HVAC-Final 12/1/2023 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 12/1/2023 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 12/19/2023 Corrections Issued THOMAS FINNILA
HVAC-Final 12/19/2023 Approved THOMAS FINNILA
PLUMBING-Final 12/19/2023 Corrections Issued THOMAS FINNILA
Final 12/21/2023 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 12/21/2023 Not Ready for Inspection THOMAS FINNILA
Green Building Final 12/21/2023 Not Ready for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 12/21/2023 SGSOV Not Ready THOMAS FINNILA
Final 1/19/2024 Corrections Issued JOHN COLEMAN
Footing/Foundation/Slab 1/19/2024 Approved JOHN COLEMAN
Green Building Final 1/19/2024 Approved JOHN COLEMAN
MERV13>=Final 1/19/2024 Approved JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 1/19/2024 SGSOV Approved JOHN COLEMAN
Service/Power Release 1/19/2024 Not Ready for Inspection JOHN COLEMAN
Smoke Detectors 1/19/2024 Approved JOHN COLEMAN
Final 2/1/2024 Corrections Issued CHRISTOPHER ROJAS
Service/Power Release 2/1/2024 Approved CHRISTOPHER ROJAS
Final 2/2/2024 OK to Issue CofO CHRISTOPHER ROJAS