14812 W HUSTON ST 91403
Certificate Information: 14812 W HUSTON ST 91403
- Application / Permit
- 23010-20000-00402
- Plan Check / Job No.
- B23VN01225
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW IRR. SHAPED 37' x 64'-6" TWO-STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE AND OPEN TRELLIS; NFPA-13D THRU-OUT
- Permit Issued
- Issued on 5/31/2023
- Issuing Office
- Current Status
- CofO Issued on 2/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2023 | SEAN SHAHMIRI |
| Corrections Issued | 2/21/2023 | SEAN SHAHMIRI |
| Building Plans Picked Up | 2/23/2023 | APPLICANT |
| Quality Review Completed | 5/18/2023 | OMID HEDAYAT |
| Applicant returned to address corrections | 5/18/2023 | SEAN SHAHMIRI |
| Plan Check Approved | 5/30/2023 | SEAN SHAHMIRI |
| Issued | 5/31/2023 | APPLICANT |
| CofO in Progress | 2/2/2024 | RAUL OLAGI |
| Permit Finaled | 2/22/2024 | RUBEN SALAS |
| CofO Issued | 2/22/2024 | RUBEN SALAS |
| Permit Finaled | 2/22/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/7/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 3/7/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/21/2023 | MEGAN GODINEZ |
| Hydrant and Access approval | Cleared | 3/25/2023 | RUEL COLE |
| Stormwater Pollution Mitigatn | Cleared | 4/11/2023 | LUIS LUVANO |
| Trees in Parkway | Cleared | 5/2/2023 | ADALBERTO VERA |
| ZI | Cleared | 5/2/2023 | STEVEN WECHSLER |
| Roof/Waste drainage to street | Cleared | 5/9/2023 | MEGAN GODINEZ |
| Permit | Cleared | 5/17/2023 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/13/2023 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 6/22/2023 | Corrections Issued | THOMAS FINNILA |
| Deputy Reinf. Concrete | 6/23/2023 | Conditional Approval | DAVID MATSON |
| Deputy Reinf. Concrete | 6/23/2023 | Conditional Approval | MICHAEL SMITH |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2023 | Partial Approval | JACK KARGODORIAN |
| Deputy Steel/Welding | 7/17/2023 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2023 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2023 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 7/26/2023 | Conditional Approval | DAVID MATSON |
| PLUMBING-Rough | 8/3/2023 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 8/7/2023 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 8/7/2023 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 8/7/2023 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2023 | Not Ready for Inspection | THOMAS FINNILA |
| MERV13>=Rough | 8/14/2023 | Corrections Issued | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 8/14/2023 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 8/18/2023 | Approved | THOMAS FINNILA |
| HVAC-Rough | 8/18/2023 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 8/18/2023 | Approved | THOMAS FINNILA |
| Shower Pan | 8/18/2023 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 8/25/2023 | Approved | THOMAS FINNILA |
| Green Building Rough | 8/25/2023 | Approved | THOMAS FINNILA |
| MERV13>=Rough | 8/25/2023 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 8/29/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 8/31/2023 | Partial Approval | CHRISTOPHER ROJAS |
| Insulation | 9/5/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 9/5/2023 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 9/13/2023 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 12/1/2023 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Final | 12/1/2023 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Final | 12/1/2023 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Final | 12/19/2023 | Corrections Issued | THOMAS FINNILA |
| HVAC-Final | 12/19/2023 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 12/19/2023 | Corrections Issued | THOMAS FINNILA |
| Final | 12/21/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 12/21/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Final | 12/21/2023 | Not Ready for Inspection | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 12/21/2023 | SGSOV Not Ready | THOMAS FINNILA |
| Final | 1/19/2024 | Corrections Issued | JOHN COLEMAN |
| Footing/Foundation/Slab | 1/19/2024 | Approved | JOHN COLEMAN |
| Green Building Final | 1/19/2024 | Approved | JOHN COLEMAN |
| MERV13>=Final | 1/19/2024 | Approved | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 1/19/2024 | SGSOV Approved | JOHN COLEMAN |
| Service/Power Release | 1/19/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Smoke Detectors | 1/19/2024 | Approved | JOHN COLEMAN |
| Final | 2/1/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Service/Power Release | 2/1/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 2/2/2024 | OK to Issue CofO | CHRISTOPHER ROJAS |