14448 W SAYRE ST 91342

Certificate Information: 14448 W SAYRE ST 91342

Application / Permit
23010-20000-00358
Plan Check / Job No.
B23VN01055
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 28'-7" x 41'-0" DETACHED ONE-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d) PER ENGINEERING
Permit Issued
Issued on 9/22/2023
Issuing Office
Current Status
CofO Issued on 11/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/29/2023 APPLICANT
Assigned to Plan Check Engineer 2/3/2023 ROSENDO MEDINA
Corrections Issued 2/8/2023 ROSENDO MEDINA
Applicant returned to address corrections 8/2/2023 PINANK PATEL
Plan Check Approved 8/6/2023 ALFRED RAMIREZ
Issued 9/22/2023 APPLICANT
CofO in Progress 4/10/2025 JENNIFER RABUCHIN
CofO in Progress 4/16/2025 RAUL OLAGI
CofO in Progress 11/5/2025 RAUL OLAGI
Permit Finaled 11/18/2025 RUBEN SALAS
CofO Issued 11/18/2025 RUBEN SALAS
Permit Finaled 11/18/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/8/2023 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 2/9/2023 ROMAN GUTIERREZ
Sewer availability Cleared 2/9/2023 ROMAN GUTIERREZ
Construction near power lines Cleared 6/5/2023 RIDWAN HARDY
Stormwater Pollution Mitigatn Cleared 7/28/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 7/31/2023 ANTHONY MAINEZ

Contact Information

Architect Chopra,, Romesh K; Lic. No.: C9900 152 S CALLE DIAZ      ANAHEIM HILLS, CA 92807
Contractor Owner-Builder       ,
Engineer Chen,, Daniel; Lic. No.: C77440 160 E COMMERCIAL STREET      SAN DIMAS, CA 91773

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/24/2024 Corrections Issued JENNIFER RABUCHIN
Underground Mechanical 1/24/2024 Partial Approval JENNIFER RABUCHIN
Sewer 1/30/2024 Approved JENNIFER RABUCHIN
Underground Mechanical 1/30/2024 Corrections Issued JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 3/21/2024 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 3/21/2024 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 5/9/2024 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 5/9/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/17/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 5/17/2024 Approved JENNIFER RABUCHIN
Green Building Rough 5/17/2024 Approved JENNIFER RABUCHIN
HVAC-Rough 5/17/2024 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 5/17/2024 Approved JENNIFER RABUCHIN
Wood Frame 5/17/2024 Approved JENNIFER RABUCHIN
Insulation 5/21/2024 Approved JENNIFER RABUCHIN
Deputy Wood Construction 5/23/2024 Conditional Approval ROBERT GOLD
Drywall Nailing 5/28/2024 Approved JENNIFER RABUCHIN
Shower Pan 5/28/2024 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 6/18/2024 Approved JENNIFER RABUCHIN
Gas Test 7/15/2024 Approved JENNIFER RABUCHIN
Final 8/13/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 8/13/2024 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 8/13/2024 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 8/13/2024 Corrections Issued JENNIFER RABUCHIN
Smoke Detectors 8/13/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 4/9/2025 Approved JENNIFER RABUCHIN
Final 4/9/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Final 4/9/2025 Approved JENNIFER RABUCHIN
HVAC-Final 4/9/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 4/9/2025 Approved JENNIFER RABUCHIN
Service/Power Release 4/9/2025 Approved JENNIFER RABUCHIN
Final 11/5/2025 OK to Issue CofO RAUL OLAGI