5725 N LEMP AVE 91601

Certificate Information: 5725 N LEMP AVE 91601

Application / Permit
23010-20000-00350
Plan Check / Job No.
B23VN01025
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW 18'-11" x 18'-11"DETACHED GARAGE
Permit Issued
Issued on 8/17/2023
Issuing Office
Valley
Current Status
CofO Issued on 7/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/27/2023 APPLICANT
Assigned to Plan Check Engineer 2/16/2023 SELLA BENYAMIN
Corrections Issued 2/21/2023 SELLA BENYAMIN
Quality Review Completed 2/24/2023 STEVEN KIM
Building Plans Picked Up 2/24/2023 APPLICANT
Plan Check Approved 7/7/2023 SELLA BENYAMIN
Issued 8/17/2023 APPLICANT
CofO in Progress 6/26/2024 CHRISTOPHER ROJAS
Permit Finaled 7/10/2024 RUBEN SALAS
CofO Issued 7/10/2024 RUBEN SALAS
Permit Finaled 7/10/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/10/2023 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 6/8/2023 CARLOS AGUILERA
Stormwater Pollution Mitigatn Cleared 6/8/2023 TOMMY YIN

Contact Information

Contractor P M A Renovations; Lic. No.: 1033506-B 17941 VENTURA BLVD #204      ENCINO, CA 91316
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/18/2023 Corrections Issued RYAN SALAZAR
BUILDING-Rough-Frame 10/25/2023 Corrections Issued RYAN SALAZAR
BUILDING-Rough-Frame 10/30/2023 Not Ready for Inspection RUBEN SALAS
ELECTRICAL-Rough 10/30/2023 Not Ready for Inspection RUBEN SALAS
Interior/Exterior Lathing 11/13/2023 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 11/15/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 11/15/2023 Partial Approval MISAEL ESPARZA
Wood Frame 11/15/2023 Not Ready for Inspection MISAEL ESPARZA
Insulation 11/16/2023 No Access for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 11/21/2023 Approved JOHN COLEMAN
Wood Frame 11/21/2023 Approved JOHN COLEMAN
Insulation 11/27/2023 Approved RYAN SALAZAR
Drywall Nailing 12/1/2023 Approved MICHEL ABAJAN
Final 3/13/2024 Corrections Issued THOMAS FINNILA
Smoke Detectors 3/13/2024 Approved THOMAS FINNILA
BUILDING-Rough-Frame 3/26/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Final 3/26/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Footing/Foundation/Slab 3/26/2024 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 3/26/2024 SGSOV Not Ready CHRISTOPHER ROJAS
Service/Power Release 3/26/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Pre-Inspection 3/28/2024 No Access for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 5/28/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Final 5/28/2024 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 5/28/2024 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 5/28/2024 SGSOV Not Ready CHRISTOPHER ROJAS
Service/Power Release 5/28/2024 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 6/3/2024 Approved CHRISTOPHER ROJAS
Final 6/3/2024 OK to Issue CofO CHRISTOPHER ROJAS
Footing/Foundation/Slab 6/3/2024 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 6/3/2024 SGSOV Approved CHRISTOPHER ROJAS
Service/Power Release 6/3/2024 Not Ready for Inspection CHRISTOPHER ROJAS