9300 N KESTER AVE 91402

Certificate Information: 9300 N KESTER AVE 91402

Application / Permit
23010-20000-00308
Plan Check / Job No.
B23VN00847
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: (N) SECOND UNIT 2-STORY SINGLE FAMILY DWELLING PER SENATE BILL 9 TWO-UNIT DEVELOPMENT.
Permit Issued
Issued on 6/1/2023
Issuing Office
Current Status
CofO Issued on 1/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/24/2023 APPLICANT
Assigned to Plan Check Engineer 2/16/2023 DANIEL YIP
Corrections Issued 2/18/2023 DANIEL YIP
Quality Review Completed 2/21/2023 GARO TELMI
Applicant returned to address corrections 5/2/2023 DANIEL YIP
Plan Check Approved 5/19/2023 DANIEL YIP
Issued 6/1/2023 APPLICANT
CofO in Progress 6/12/2024 ROBERT GOLD
No Progress 6/12/2024 ROBERT GOLD
CofO in Progress 6/12/2024 ROBERT GOLD
CofO in Progress 6/17/2024 ROBERT GOLD
CofO in Progress 12/19/2024 JENNIFER RABUCHIN
Permit Finaled 1/2/2025 RUBEN SALAS
Permit Finaled 1/2/2025 RUBEN SALAS
CofO Issued 1/2/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/2/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/2/2023 LEE GUILBEAUX
Sewer availability Cleared 3/2/2023 LEE GUILBEAUX
Senate Bill 9 Cleared 3/6/2023 ASHLEY RODARTE
Hydrant and Access approval Cleared 3/13/2023 MATTHEW CRAIG
Stormwater Pollution Mitigatn Cleared 4/4/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 4/10/2023 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Roberts,, Jeffrey Allan; Lic. No.: NA56881       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/23/2023 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 6/23/2023 Partial Approval JENNIFER RABUCHIN
Pre-Inspection 6/23/2023 Corrections Issued JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 6/27/2023 Approved JENNIFER RABUCHIN
Deputy Wood Construction 8/9/2023 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 8/9/2023 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 8/9/2023 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 8/9/2023 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/15/2023 Partial Approval ROBERT GOLD
HVAC-Rough 8/15/2023 Not Ready for Inspection ROBERT GOLD
PLUMBING-Rough 8/15/2023 Not Ready for Inspection ROBERT GOLD
HVAC-Rough 8/28/2023 Not Ready for Inspection JENNIFER RABUCHIN
Interior/Exterior Lathing 8/28/2023 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 8/28/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 9/14/2023 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 9/14/2023 Approved MISAEL ESPARZA
Green Building Rough 9/14/2023 Approved MISAEL ESPARZA
HVAC-Rough 9/14/2023 Approved MISAEL ESPARZA
PLUMBING-Rough 9/14/2023 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 9/14/2023 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 9/28/2023 Approved JENNIFER RABUCHIN
Shower Pan 9/28/2023 Corrections Issued JENNIFER RABUCHIN
Verify Sprinkler Sign Off 9/28/2023 Approved JENNIFER RABUCHIN
Insulation 10/2/2023 Approved MICHEL ABAJAN
Drywall Nailing 10/4/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 10/4/2023 Not Ready for Inspection JENNIFER RABUCHIN
Shower Pan 10/4/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 10/18/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 11/20/2023 Corrections Issued JENNIFER RABUCHIN
Gas Test 11/20/2023 Approved JENNIFER RABUCHIN
HVAC-Final 11/20/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 11/20/2023 Approved JENNIFER RABUCHIN
Service/Power Release 11/20/2023 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Final 12/8/2023 Approved JENNIFER RABUCHIN
Final 12/8/2023 Not Ready for Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 12/8/2023 Approved JENNIFER RABUCHIN
Gas Test 12/8/2023 Approved JENNIFER RABUCHIN
Green Building Final 12/8/2023 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 12/8/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 12/8/2023 Not Ready for Inspection JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 12/8/2023 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 12/8/2023 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 12/8/2023 Approved JENNIFER RABUCHIN
Final 2/15/2024 Corrections Issued MICHEL ABAJAN
Green Building Final 2/15/2024 Not Ready for Inspection MICHEL ABAJAN
Service/Power Release 2/15/2024 Not Ready for Inspection MICHEL ABAJAN
Final 2/22/2024 Corrections Issued THOMAS FINNILA
Green Building Final 2/22/2024 Approved THOMAS FINNILA
Service/Power Release 2/22/2024 Approved THOMAS FINNILA
ELECTRICAL-Final 4/11/2024 Approved JENNIFER RABUCHIN
Final 4/11/2024 Conditional Approval JENNIFER RABUCHIN
HVAC-Final 4/11/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 4/11/2024 Approved JENNIFER RABUCHIN
Final 6/17/2024 Corrections Issued ROBERT GOLD
Final 12/19/2024 OK to Issue CofO JENNIFER RABUCHIN