17198 W VANOWEN ST 91406

Certificate Information: 17198 W VANOWEN ST 91406

Application / Permit
23010-20000-00303
Plan Check / Job No.
B23VN00818
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
KEEP 3'-6" WALL AND CONVERT (E) UTILITY ROOM WITH ADDITION INTO A NEW DETACHED TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 10/16/2023
Issuing Office
Current Status
CofO Issued on 8/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/27/2023 APPLICANT
Assigned to Plan Check Engineer 2/3/2023 JEROME MAGAT PALMA
Corrections Issued 2/4/2023 JEROME MAGAT PALMA
Applicant returned to address corrections 9/12/2023 ALFRED RAMIREZ
Plan Check Approved 9/18/2023 ALFRED RAMIREZ
Issued 10/16/2023 APPLICANT
CofO in Progress 4/21/2025 JON MCHUGH
CofO in Progress 5/9/2025 JON MCHUGH
CofO in Progress 8/7/2025 JON MCHUGH
Permit Finaled 8/28/2025 JOHN JANSON
CofO Issued 8/28/2025 JOHN JANSON
Permit Finaled 8/28/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/15/2023 FERNANDO GIL
Eng Process Fee Ord 176,300 Cleared 2/15/2023 FERNANDO GIL
Sewer availability Cleared 2/15/2023 FERNANDO GIL
Hydrant and Access approval Cleared 3/7/2023 KURT CORRAL
Construction near power lines Cleared 7/22/2023 TINA MIRANDA
ZI Cleared 7/24/2023 ASHLEY RODARTE
Stormwater Pollution Mitigatn Cleared 8/11/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 8/14/2023 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Koma,, Shahram Javadi; Lic. No.: C69497 23241 VENTURA BLVD 300      WOODLAND HILLS, CA 91364

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/2/2024 Corrections Issued JON MCHUGH
Underground Mechanical 5/2/2024 Not Ready for Inspection JON MCHUGH
Excavation/Setback/Form/Re-Bar 7/8/2024 Not Ready for Inspection JON MCHUGH
Underground Mechanical 7/8/2024 Partial Approval JON MCHUGH
Footing/Foundation/Slab 7/10/2024 Corrections Issued MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 7/15/2024 Corrections Issued JON MCHUGH
ELECTRICAL-Rough 7/23/2024 Not Ready for Inspection JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 7/23/2024 Corrections Issued JON MCHUGH
HVAC-Rough 7/23/2024 Not Ready for Inspection JON MCHUGH
PLUMBING-Rough 7/23/2024 Not Ready for Inspection JON MCHUGH
ELECTRICAL-Rough 7/25/2024 Not Ready for Inspection JON MCHUGH
HVAC-Rough 7/25/2024 Not Ready for Inspection JON MCHUGH
PLUMBING-Rough 7/25/2024 Corrections Issued JON MCHUGH
Wood Frame 7/25/2024 Not Ready for Inspection JON MCHUGH
ELECTRICAL-Rough 8/1/2024 Corrections Issued JON MCHUGH
HVAC-Rough 8/1/2024 Partial Approval JON MCHUGH
PLUMBING-Rough 8/1/2024 Not Ready for Inspection JON MCHUGH
Shower Pan 8/1/2024 Approved JON MCHUGH
Wood Frame 8/1/2024 Corrections Issued JON MCHUGH
Deputy Wood Construction 8/2/2024 Conditional Approval JON MCHUGH
Interior/Exterior Lathing 8/6/2024 Not Ready for Inspection MORRIS JACKSON
Rough-Elec/Plmb/HVAC 8/6/2024 Approved MORRIS JACKSON
BUILDING-Rough-Frame 8/15/2024 Corrections Issued MORRIS JACKSON
Interior/Exterior Lathing 8/15/2024 Partial Approval MORRIS JACKSON
Wood Frame 8/15/2024 Not Ready for Inspection MORRIS JACKSON
BUILDING-Rough-Frame 8/20/2024 Partial Approval MORRIS JACKSON
Green Building Rough 8/20/2024 Approved MORRIS JACKSON
Insulation 8/20/2024 Approved MORRIS JACKSON
Drywall Nailing 8/26/2024 Partial Approval SCOTT SOBEL
BUILDING-Rough-Frame 10/11/2024 Approved JON MCHUGH
Drywall Nailing 10/11/2024 Approved JON MCHUGH
Final 10/11/2024 Corrections Issued JON MCHUGH
Green Building Final 10/11/2024 Not Ready for Inspection JON MCHUGH
SGSOV-Seismic Gas S/O Valve 10/11/2024 SGSOV Not Ready JON MCHUGH
Smoke Detectors 10/11/2024 Not Ready for Inspection JON MCHUGH
Final 12/10/2024 Corrections Issued JON MCHUGH
Green Building Final 12/10/2024 Approved JON MCHUGH
SGSOV-Seismic Gas S/O Valve 12/10/2024 SGSOV Approved JON MCHUGH
Service/Power Release 12/10/2024 Approved JON MCHUGH
Smoke Detectors 12/10/2024 Not Ready for Inspection JON MCHUGH
Final 1/15/2025 Corrections Issued JON MCHUGH
Smoke Detectors 1/15/2025 Approved JON MCHUGH
Final 4/21/2025 Not Ready for Inspection JON MCHUGH
Final 5/9/2025 Corrections Issued JON MCHUGH
Final 8/7/2025 OK to Issue CofO JON MCHUGH