17198 W VANOWEN ST 91406
Certificate Information: 17198 W VANOWEN ST 91406
- Application / Permit
- 23010-20000-00303
- Plan Check / Job No.
- B23VN00818
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- KEEP 3'-6" WALL AND CONVERT (E) UTILITY ROOM WITH ADDITION INTO A NEW DETACHED TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 10/16/2023
- Issuing Office
- Current Status
- CofO Issued on 8/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/3/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 2/4/2023 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 9/12/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 9/18/2023 | ALFRED RAMIREZ |
| Issued | 10/16/2023 | APPLICANT |
| CofO in Progress | 4/21/2025 | JON MCHUGH |
| CofO in Progress | 5/9/2025 | JON MCHUGH |
| CofO in Progress | 8/7/2025 | JON MCHUGH |
| Permit Finaled | 8/28/2025 | JOHN JANSON |
| CofO Issued | 8/28/2025 | JOHN JANSON |
| Permit Finaled | 8/28/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/15/2023 | FERNANDO GIL |
| Eng Process Fee Ord 176,300 | Cleared | 2/15/2023 | FERNANDO GIL |
| Sewer availability | Cleared | 2/15/2023 | FERNANDO GIL |
| Hydrant and Access approval | Cleared | 3/7/2023 | KURT CORRAL |
| Construction near power lines | Cleared | 7/22/2023 | TINA MIRANDA |
| ZI | Cleared | 7/24/2023 | ASHLEY RODARTE |
| Stormwater Pollution Mitigatn | Cleared | 8/11/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 8/14/2023 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Koma,, Shahram Javadi; Lic. No.: C69497 | 23241 VENTURA BLVD 300 WOODLAND HILLS, CA 91364 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/2/2024 | Corrections Issued | JON MCHUGH |
| Underground Mechanical | 5/2/2024 | Not Ready for Inspection | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 7/8/2024 | Not Ready for Inspection | JON MCHUGH |
| Underground Mechanical | 7/8/2024 | Partial Approval | JON MCHUGH |
| Footing/Foundation/Slab | 7/10/2024 | Corrections Issued | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2024 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Rough | 7/23/2024 | Not Ready for Inspection | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2024 | Corrections Issued | JON MCHUGH |
| HVAC-Rough | 7/23/2024 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 7/23/2024 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 7/25/2024 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Rough | 7/25/2024 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 7/25/2024 | Corrections Issued | JON MCHUGH |
| Wood Frame | 7/25/2024 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 8/1/2024 | Corrections Issued | JON MCHUGH |
| HVAC-Rough | 8/1/2024 | Partial Approval | JON MCHUGH |
| PLUMBING-Rough | 8/1/2024 | Not Ready for Inspection | JON MCHUGH |
| Shower Pan | 8/1/2024 | Approved | JON MCHUGH |
| Wood Frame | 8/1/2024 | Corrections Issued | JON MCHUGH |
| Deputy Wood Construction | 8/2/2024 | Conditional Approval | JON MCHUGH |
| Interior/Exterior Lathing | 8/6/2024 | Not Ready for Inspection | MORRIS JACKSON |
| Rough-Elec/Plmb/HVAC | 8/6/2024 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 8/15/2024 | Corrections Issued | MORRIS JACKSON |
| Interior/Exterior Lathing | 8/15/2024 | Partial Approval | MORRIS JACKSON |
| Wood Frame | 8/15/2024 | Not Ready for Inspection | MORRIS JACKSON |
| BUILDING-Rough-Frame | 8/20/2024 | Partial Approval | MORRIS JACKSON |
| Green Building Rough | 8/20/2024 | Approved | MORRIS JACKSON |
| Insulation | 8/20/2024 | Approved | MORRIS JACKSON |
| Drywall Nailing | 8/26/2024 | Partial Approval | SCOTT SOBEL |
| BUILDING-Rough-Frame | 10/11/2024 | Approved | JON MCHUGH |
| Drywall Nailing | 10/11/2024 | Approved | JON MCHUGH |
| Final | 10/11/2024 | Corrections Issued | JON MCHUGH |
| Green Building Final | 10/11/2024 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 10/11/2024 | SGSOV Not Ready | JON MCHUGH |
| Smoke Detectors | 10/11/2024 | Not Ready for Inspection | JON MCHUGH |
| Final | 12/10/2024 | Corrections Issued | JON MCHUGH |
| Green Building Final | 12/10/2024 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 12/10/2024 | SGSOV Approved | JON MCHUGH |
| Service/Power Release | 12/10/2024 | Approved | JON MCHUGH |
| Smoke Detectors | 12/10/2024 | Not Ready for Inspection | JON MCHUGH |
| Final | 1/15/2025 | Corrections Issued | JON MCHUGH |
| Smoke Detectors | 1/15/2025 | Approved | JON MCHUGH |
| Final | 4/21/2025 | Not Ready for Inspection | JON MCHUGH |
| Final | 5/9/2025 | Corrections Issued | JON MCHUGH |
| Final | 8/7/2025 | OK to Issue CofO | JON MCHUGH |