4435 N KATHERINE AVE 91423
Certificate Information: 4435 N KATHERINE AVE 91423
- Application / Permit
- 23010-20000-00262
- Plan Check / Job No.
- B23VN00666
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW IRR. SHAPED 35'-4" x 73'-3" TWO-STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE AND OPEN TRELLIS; NFPA-13D THRU-OUT
- Permit Issued
- Issued on 6/27/2023
- Issuing Office
- Current Status
- CofO Issued on 8/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/9/2023 | SEAN SHAHMIRI |
| Corrections Issued | 2/13/2023 | SEAN SHAHMIRI |
| Quality Review Completed | 2/13/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 2/14/2023 | APPLICANT |
| Applicant returned to address corrections | 6/8/2023 | SEAN SHAHMIRI |
| Plan Check Approved | 6/26/2023 | SEAN SHAHMIRI |
| Issued | 6/27/2023 | APPLICANT |
| CofO in Progress | 8/5/2024 | MISAEL ESPARZA |
| Permit Finaled | 8/16/2024 | DANIEL ORRANTE |
| CofO Issued | 8/16/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/16/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 2/17/2023 | SHAELYN ROWEN |
| Hydrant and Access approval | Cleared | 3/11/2023 | LAVEON RIDER |
| Eng Process Fee Ord 176,300 | Cleared | 4/5/2023 | SHAELYN ROWEN |
| Sewer availability | Cleared | 4/5/2023 | SHAELYN ROWEN |
| Stormwater Pollution Mitigatn | Cleared | 4/26/2023 | ERNEST TSE |
| ZI | Cleared | 6/8/2023 | STEVEN WECHSLER |
| Roof/Waste drainage to street | Cleared | 6/26/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/20/2023 | Partial Approval | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 7/27/2023 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2023 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2023 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2023 | Corrections Issued | MISAEL ESPARZA |
| Deputy Wood Construction | 10/11/2023 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2023 | Partial Approval | MISAEL ESPARZA |
| HVAC-Rough | 10/18/2023 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 10/18/2023 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2024 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 1/19/2024 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 1/25/2024 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 1/25/2024 | Approved | MISAEL ESPARZA |
| Green Building Rough | 1/25/2024 | Approved | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 1/25/2024 | Approved | MISAEL ESPARZA |
| Insulation | 2/16/2024 | Approved | THOMAS FINNILA |
| Drywall Nailing | 2/26/2024 | Approved | SALVADOR MARTINEZ |
| Shower Pan | 3/19/2024 | Approved | MISAEL ESPARZA |
| Underground Mechanical | 3/19/2024 | Partial Approval | MISAEL ESPARZA |
| Interior/Exterior Lathing | 4/1/2024 | Partial Approval | MISAEL ESPARZA |
| Sewer | 4/1/2024 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 4/3/2024 | Approved | MISAEL ESPARZA |
| Final | 7/8/2024 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 7/8/2024 | Approved | DAVID ANDERSON |
| Green Building Final | 7/8/2024 | Not Ready for Inspection | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 7/8/2024 | SGSOV Approved | DAVID ANDERSON |
| Service/Power Release | 7/8/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 7/8/2024 | Approved | DAVID ANDERSON |
| Service/Power Release | 7/9/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 7/25/2024 | Approved | JOSE AVILA |
| PLUMBING-Final | 7/25/2024 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 7/29/2024 | Approved | MISAEL ESPARZA |
| Final | 7/29/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 7/29/2024 | Approved | MISAEL ESPARZA |
| HVAC-Final | 7/29/2024 | Approved | MISAEL ESPARZA |
| Service/Power Release | 7/29/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 7/31/2024 | OK to Issue CofO | MISAEL ESPARZA |
| Service/Power Release | 7/31/2024 | Approved | MISAEL ESPARZA |