9539 N LANGDON AVE 91343

Certificate Information: 9539 N LANGDON AVE 91343

Application / Permit
23010-20000-00257
Plan Check / Job No.
B23VN00649
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
(N) DETACHED 25' X 26' 2-CAR GARAGE 1/2 BATHROOM. ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 4/7/2023
Issuing Office
Valley
Current Status
CofO Issued on 6/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/20/2023 APPLICANT
Assigned to Plan Check Engineer 1/23/2023 JESSE ARELLANO
Corrections Issued 1/24/2023 JESSE ARELLANO
Building Plans Picked Up 1/27/2023 APPLICANT
Issued 4/7/2023 APPLICANT
CofO in Progress 5/27/2025 VINCENT HANLEY
CofO in Progress 5/27/2025 VINCENT HANLEY
CofO Issued 6/9/2025 RUBEN SALAS
Permit Finaled 6/9/2025 RUBEN SALAS

Permit Application Clearance Information

Stormwater Pollution Mitigatn Cleared 3/31/2023 ROGELIO CORTES
Eng Process Fee Ord 176,300 Cleared 4/3/2023 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 4/4/2023 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Medina,, Ferdinand Casaclang; Lic. No.: C88007 1051 S HOLT AVE APT F      LOS ANGELES, CA 90035

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 6/2/2023 Partial Approval CHRISTOPHER DELLEFIELD
Underground Mechanical 6/2/2023 Partial Approval CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 6/6/2023 Approved CHRISTOPHER DELLEFIELD
Sewer 6/6/2023 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 6/30/2023 Not Ready for Inspection RAUL OLAGI
Rough-Elec/Plmb/HVAC 6/30/2023 Not Ready for Inspection RAUL OLAGI
Underground Mechanical 6/30/2023 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 7/10/2023 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 7/10/2023 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 7/10/2023 Corrections Issued GREGG CUMMINGS
Special/Order Compliance 7/10/2023 Corrections Issued GREGG CUMMINGS
Underground Mechanical 7/10/2023 Partial Approval GREGG CUMMINGS
ELECTRICAL-Rough 7/19/2023 Approved DAVID MATSON
PLUMBING-Rough 7/19/2023 Approved DAVID MATSON
Wood Frame 7/19/2023 Approved DAVID MATSON
Drywall Nailing 8/11/2023 Approved GREGG CUMMINGS
Interior/Exterior Lathing 8/11/2023 Partial Approval GREGG CUMMINGS
Underground Mechanical 8/11/2023 Partial Approval GREGG CUMMINGS
BUILDING-Rough-Frame 5/22/2025 Approved VINCENT HANLEY
Final 5/22/2025 Partial Approval VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/22/2025 SGSOV Approved VINCENT HANLEY
Service/Power Release 5/22/2025 Approved VINCENT HANLEY
Smoke Detectors 5/22/2025 Approved VINCENT HANLEY
Final 5/27/2025 OK to Issue CofO VINCENT HANLEY