12272 W WICKS ST 91352

Certificate Information: 12272 W WICKS ST 91352

Application / Permit
23010-20000-00248
Plan Check / Job No.
B23VN00629
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ONE-STORY 20' X 42' ACCESSORY DWELLING UNIT PER PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g). AUTOMATIC FIRE SPRINKLER REQUIRED. WORK PER WFPP. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 4/14/2023
Issuing Office
Valley
Current Status
CofO Issued on 10/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/19/2023 APPLICANT
Assigned to Plan Check Engineer 1/20/2023 LUIS RINCON
Corrections Issued 1/21/2023 LUIS RINCON
Building Plans Picked Up 1/25/2023 APPLICANT
Plan Check Approved 4/14/2023 ROSENDO MEDINA
Issued 4/14/2023 APPLICANT
CofO in Progress 10/9/2024 MATTHEW NELSON
Permit Finaled 10/21/2024 DANIEL ORRANTE
CofO Issued 10/21/2024 DANIEL ORRANTE
Permit Finaled 10/21/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/26/2023 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 1/30/2023 JOSE DUARTE-DIAZ
Sewer availability Cleared 1/30/2023 JOSE DUARTE-DIAZ
ZA Case Cleared 1/30/2023 NATHAN ROMINE
ZA Case Cleared 1/30/2023 NATHAN ROMINE
ZA Case Cleared 1/30/2023 NATHAN ROMINE
Roof/Waste drainage to street Cleared 4/12/2023 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/8/2023 Corrections Issued MATTHEW NELSON
PLUMBING-Rough 5/8/2023 Not Ready for Inspection MATTHEW NELSON
Footing/Foundation/Slab 5/12/2023 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 10/20/2023 Partial Approval CHRISTOPHER ROJAS
Sewer 10/20/2023 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 3/19/2024 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 3/19/2024 Corrections Issued MATTHEW NELSON
Green Building Rough 3/19/2024 Approved MATTHEW NELSON
HVAC-Rough 3/19/2024 Approved MATTHEW NELSON
MERV13>=Rough 3/19/2024 Approved MATTHEW NELSON
PLUMBING-Rough 3/19/2024 Corrections Issued MATTHEW NELSON
Verify Sprinkler Sign Off 3/19/2024 Approved MATTHEW NELSON
BUILDING-Rough-Frame 4/1/2024 Approved MATTHEW NELSON
ELECTRICAL-Rough 4/1/2024 Approved MATTHEW NELSON
Interior/Exterior Lathing 4/1/2024 Approved MATTHEW NELSON
PLUMBING-Rough 4/1/2024 Approved MATTHEW NELSON
Insulation 4/5/2024 Approved MATTHEW NELSON
Drywall Nailing 4/10/2024 Approved MATTHEW NELSON
Shower Pan 4/10/2024 Approved MATTHEW NELSON
Interior/Exterior Lathing 4/15/2024 Approved MICHEL ABAJAN
Final 10/8/2024 OK to Issue CofO MATTHEW NELSON
Green Building Final 10/8/2024 Approved MATTHEW NELSON
MERV13>=Final 10/8/2024 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 10/8/2024 SGSOV Approved MATTHEW NELSON
Service/Power Release 10/8/2024 Approved MATTHEW NELSON
Smoke Detectors 10/8/2024 Approved MATTHEW NELSON