7899 N RUDNICK AVE 91304
Certificate Information: 7899 N RUDNICK AVE 91304
- Application / Permit
- 23010-20000-00203
- Plan Check / Job No.
- B23VN00598
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED NEW DETACHED 26'-0" X 44'-0" 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d) WITH PREFAB ROOF TRUSS. ALL WORK PER ENGR DESIGN.
- Permit Issued
- Issued on 6/21/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2023 | HAYATO TSUCHIYA |
| Corrections Issued | 1/25/2023 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 1/31/2023 | APPLICANT |
| Issued | 6/21/2023 | APPLICANT |
| CofO in Progress | 3/28/2024 | JEFFREY HARTLINE |
| CofO Issued | 4/12/2024 | JOHN JANSON |
| Permit Finaled | 4/12/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/2/2023 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/23/2023 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 2/23/2023 | JOSE DUARTE-DIAZ |
| Construction near power lines | Cleared | 5/7/2023 | RIDWAN HARDY |
| Low Impact Development | Cleared | 6/13/2023 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 6/15/2023 | TAL SHEMEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21757 DEVONSHIRE ST. SUITE 3 CANOGA PARK, CA 91311 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/29/2023 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 7/5/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 7/6/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Underground Mechanical | 7/6/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 7/14/2023 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 8/25/2023 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 9/1/2023 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 9/1/2023 | Corrections Issued | JEFFREY HARTLINE |
| Wood Frame | 9/1/2023 | Corrections Issued | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Wood Frame | 9/8/2023 | Partial Approval | CHRIS CHRISTENSEN |
| HVAC-Rough | 9/15/2023 | Approved | DAVID SCANTLIN |
| Underground Mechanical | 9/15/2023 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 9/25/2023 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 9/25/2023 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 9/25/2023 | Approved | JEFFREY HARTLINE |
| Underground Mechanical | 9/25/2023 | Approved | JEFFREY HARTLINE |
| Verify Sprinkler Sign Off | 9/25/2023 | Approved | JEFFREY HARTLINE |
| Pre-Inspection | 9/29/2023 | Off-Hour Fees Due | |
| Insulation | 9/30/2023 | Corrections Issued | DAVID ANDERSON |
| Insulation | 9/30/2023 | Off-Hour Fees Due | |
| Drywall Nailing | 10/11/2023 | Approved | JEFFREY HARTLINE |
| Service/Power Release | 11/8/2023 | Not Ready for Inspection | JEFFREY HARTLINE |
| Shower Pan | 12/6/2023 | Approved | JEFFREY HARTLINE |
| Green Building Final | 2/21/2024 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 2/21/2024 | SGSOV Approved | JEFFREY HARTLINE |
| Service/Power Release | 2/21/2024 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Final | 3/27/2024 | Approved | JEFFREY HARTLINE |
| Final | 3/27/2024 | OK to Issue CofO | JEFFREY HARTLINE |
| HVAC-Final | 3/27/2024 | Approved | JEFFREY HARTLINE |
| PLUMBING-Final | 3/27/2024 | Approved | JEFFREY HARTLINE |
| Smoke Detectors | 3/27/2024 | Approved | JEFFREY HARTLINE |