10233 N COLLETT AVE 91343
Certificate Information: 10233 N COLLETT AVE 91343
- Application / Permit
- 23010-20000-00200
- Plan Check / Job No.
- B23VN00594
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: (N) 38'-6" X 22'-6" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d). (N) 4' X 11'-6" PORCH ATTACHED TO ADU PER ENGINEERING
- Permit Issued
- Issued on 9/21/2023
- Issuing Office
- Current Status
- CofO Issued on 1/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2023 | ALEC MOUSAKHANIAN |
| Corrections Issued | 1/29/2023 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 4/29/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 8/3/2023 | ALFRED RAMIREZ |
| Issued | 9/21/2023 | APPLICANT |
| CofO in Progress | 1/2/2025 | JAVIER RAMOS JR |
| Permit Finaled | 1/24/2025 | RUBEN SALAS |
| CofO Issued | 1/24/2025 | RUBEN SALAS |
| Permit Finaled | 1/24/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/17/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/21/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/21/2023 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 7/24/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 7/25/2023 | ROMAN GUTIERREZ |
| Grading Pre-Inspection | Cleared | 8/2/2023 | ALEC MOUSAKHANIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/16/2023 | Approved | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 11/22/2023 | Partial Approval | KEVIN BERBERYAN |
| PLUMBING-Rough | 11/30/2023 | Partial Approval | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 12/5/2023 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 12/5/2023 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 12/5/2023 | Partial Approval | JAVIER RAMOS JR |
| Deputy Wood Construction | 1/3/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2024 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 2/23/2024 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 2/23/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 2/23/2024 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 2/23/2024 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 2/23/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 2/26/2024 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 3/29/2024 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 3/29/2024 | Approved | JAVIER RAMOS JR |
| Insulation | 3/29/2024 | Approved | JAVIER RAMOS JR |
| Shower Pan | 3/29/2024 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 4/12/2024 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 4/12/2024 | Approved | JAVIER RAMOS JR |
| Final | 11/8/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Green Building Final | 11/8/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 11/8/2024 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 11/8/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 11/8/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Smoke Detectors | 11/8/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 11/19/2024 | Approved | JAVIER RAMOS JR |
| Final | 11/19/2024 | Partial Inspection | JAVIER RAMOS JR |
| HVAC-Final | 11/19/2024 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 11/19/2024 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 11/19/2024 | Approved | JAVIER RAMOS JR |
| Final | 12/31/2024 | OK to Issue CofO | JAVIER RAMOS JR |