11100 W PEORIA ST 91352
Certificate Information: 11100 W PEORIA ST 91352
- Application / Permit
- 23010-20000-00191
- Plan Check / Job No.
- B23VN00552
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (13) Parking Guard
- Work Description
- ePLAN- NEW 8X12 Guard Shack
- Permit Issued
- Issued on 3/20/2024
- Issuing Office
- Current Status
- CofO Issued on 2/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/9/2023 | ARSALAN SHABESTARI |
| Corrections Issued | 3/28/2023 | ARSALAN SHABESTARI |
| Quality Review Completed | 4/7/2023 | GARO TELMI |
| Plan Check Approved | 3/12/2024 | ARSALAN SHABESTARI |
| Issued | 3/20/2024 | APPLICANT |
| CofO in Progress | 1/29/2025 | DANNY RODRIGUEZ |
| Permit Finaled | 2/18/2025 | RICKEY JACKSON |
| CofO Issued | 2/18/2025 | RICKEY JACKSON |
| Permit Finaled | 2/18/2025 | RICKEY JACKSON |
Permit Application Clearance Information
| Green Code | Cleared | 6/8/2023 | MICHAEL AYERS |
| Roof/Waste drainage to street | Cleared | 8/26/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/28/2023 | CARLOS AGUILERA |
| ZA Case | Cleared | 8/29/2023 | NATHAN ROMINE |
| ZA Case | Cleared | 8/29/2023 | NATHAN ROMINE |
| CPC | Cleared | 9/1/2023 | NATHAN ROMINE |
| DAS Clearance | Cleared | 1/29/2024 | ARSALAN SHABESTARI |
| Grading Pre-Inspection | Cleared | 3/4/2024 | ARSALAN SHABESTARI |
Contact Information
| Contractor | Snyder Langston Llc; Lic. No.: 1019188-B | , |
| Contractor | Snyder Langston Residential, Llc; Lic. No.: 1019188-B | , |
Inspector Information
| JOHN KITCKO, (818) 374-1109 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 3/27/2024 | Corrections Issued | DANNY RODRIGUEZ |
| Final | 5/10/2024 | OK to Issue CofO | DANNY RODRIGUEZ |
| Green Building Final | 5/10/2024 | Approved | DANNY RODRIGUEZ |
| Green Building Rough | 5/10/2024 | Approved | DANNY RODRIGUEZ |
| METHANE-Final | 5/10/2024 | Approved | DANNY RODRIGUEZ |
| METHANE-Rough | 5/10/2024 | Approved | DANNY RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 5/10/2024 | SGSOV Not Ready | DANNY RODRIGUEZ |
| Smoke Detectors | 5/10/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 5/10/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 5/10/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 5/13/2024 | Approved | DANNY RODRIGUEZ |
| METHANE-Barrier | 5/13/2024 | Approved | DANNY RODRIGUEZ |
| METHANE-Subgrade | 5/13/2024 | Approved | DANNY RODRIGUEZ |