11483 W DELANO ST 91606

Certificate Information: 11483 W DELANO ST 91606

Application / Permit
23010-20000-00162
Plan Check / Job No.
B23VN00464
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 1-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) **ePlan**
Permit Issued
Issued on 1/14/2025
Issuing Office
Current Status
CofO Issued on 1/20/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/10/2023 APPLICANT
Assigned to Plan Check Engineer 5/25/2023 NILOOFAR MEHRAIN
Corrections Issued 5/27/2023 NILOOFAR MEHRAIN
Quality Review Completed 5/30/2023 STEVEN KIM
Applicant returned to address corrections 12/15/2023 NILOOFAR MEHRAIN
Plan Check Approved 1/3/2024 NILOOFAR MEHRAIN
Issued 1/14/2025 APPLICANT
CofO in Progress 1/6/2026 ROBERTO PALACIOS-LOPEZ
Permit Finaled 1/20/2026 RUBEN SALAS
CofO Issued 1/20/2026 RUBEN SALAS
Permit Finaled 1/20/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/14/2023 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 8/16/2023 ROMAN GUTIERREZ
Sewer availability Cleared 8/16/2023 ROMAN GUTIERREZ
Hydrant and Access approval Cleared 9/8/2023 LAVEON RIDER
Low Impact Development (LID) Cleared 11/30/2023 TRISH PARAS
Roof/Waste drainage to street Cleared 12/7/2023 BRYAN GODINEZ

Contact Information

Architect Defraites,, Sydney G; Lic. No.: C33440 P.O. BOX 6784      BURBANK, CA 91510
Contractor Owner-Builder       ,
Engineer Clayton,, Andrew; Lic. No.: C85452 10211 LEMONA AVE      MISSION HILLS, CA 91345

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/15/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 1/17/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 1/17/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 1/30/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 1/30/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Sewer 1/30/2025 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 1/30/2025 Approved ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 2/10/2025 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 4/17/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 4/17/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 4/17/2025 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 4/29/2025 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 5/30/2025 Conditional Approval ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 5/30/2025 Conditional Approval ROBERTO PALACIOS-LOPEZ
Green Building Rough 5/30/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 5/30/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 5/30/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 6/3/2025 Not Ready for Inspection MISAEL ESPARZA
Drywall Nailing 6/10/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 6/10/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Insulation 6/10/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 6/10/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 9/9/2025 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 9/9/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 9/9/2025 Approved ROBERTO PALACIOS-LOPEZ
Rough-Elec/Plmb/HVAC 9/9/2025 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 9/9/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 9/26/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 10/15/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 10/15/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 10/15/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Final 10/15/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 10/15/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 10/15/2025 SGSOV Not Required ROBERTO PALACIOS-LOPEZ
Service/Power Release 10/15/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 10/15/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 10/22/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 10/22/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 10/22/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 10/22/2025 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 10/22/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 12/31/2025 Corrections Issued JOSE AVILA
Final 1/5/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Service/Power Release 1/5/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 1/6/2026 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Service/Power Release 1/6/2026 Approved ROBERTO PALACIOS-LOPEZ