17150 W FLANDERS ST 91344

Certificate Information: 17150 W FLANDERS ST 91344

Application / Permit
23010-20000-00135
Plan Check / Job No.
B23VN00376
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: NEW 2-STORY 1,188 SQ FT ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 7/19/2023
Issuing Office
Current Status
CofO Issued on 6/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/13/2023 APPLICANT
Assigned to Plan Check Engineer 1/27/2023 MOHAMMAD ESMAILI
Corrections Issued 1/31/2023 MOHAMMAD ESMAILI
Applicant returned to address corrections 7/11/2023 HANS SANTIAGO
Plan Check Approved 7/18/2023 ANDREW SANTIAGO
Issued 7/19/2023 APPLICANT
CofO in Progress 5/24/2024 STEVEN BACK
Permit Finaled 6/14/2024 JOHN JANSON
CofO Issued 6/14/2024 JOHN JANSON
Permit Finaled 6/14/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/9/2023 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 3/13/2023 JOSE DUARTE-DIAZ
Sewer availability Cleared 3/13/2023 JOSE DUARTE-DIAZ
Stormwater Pollution Mitigatn Cleared 6/23/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 6/30/2023 TAL SHEMEN
Grading Pre-Inspection Cleared 7/3/2023 ROBERT HUGHES
GPI Written Notices Cleared 7/18/2023 MOHAMMAD ESMAILI

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/4/2023 Approved SEAN WIRCH
PLUMBING-Rough 8/15/2023 Partial Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 8/18/2023 Partial Approval JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 8/28/2023 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 10/18/2023 Corrections Issued JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 10/24/2023 Corrections Issued STEVEN BACK
Deputy Wood Construction 10/25/2023 Approved STEVEN BACK
Deputy Drilled-In Anchors 10/26/2023 Approved JEFFREY PARD
ELECTRICAL-Rough 10/30/2023 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 10/30/2023 Not Ready for Inspection STEVEN BACK
HVAC-Rough 10/30/2023 Approved STEVEN BACK
PLUMBING-Rough 10/30/2023 Approved STEVEN BACK
BUILDING-Rough-Frame 11/2/2023 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 11/2/2023 Approved STEVEN BACK
Green Building Rough 11/2/2023 Approved STEVEN BACK
Insulation 11/2/2023 Corrections Issued STEVEN BACK
MERV13>=Rough 11/2/2023 Approved STEVEN BACK
Drywall Nailing 11/14/2023 Approved STEVEN BACK
Insulation 11/14/2023 Approved STEVEN BACK
Interior/Exterior Lathing 11/14/2023 Approved STEVEN BACK
ELECTRICAL-Final 4/1/2024 Not Ready for Inspection STEVEN BACK
Final 4/1/2024 Corrections Issued STEVEN BACK
Green Building Final 4/1/2024 Not Ready for Inspection STEVEN BACK
HVAC-Final 4/1/2024 Not Ready for Inspection STEVEN BACK
MERV13>=Final 4/1/2024 Approved STEVEN BACK
PLUMBING-Final 4/1/2024 Not Ready for Inspection STEVEN BACK
SGSOV-Seismic Gas S/O Valve 4/1/2024 SGSOV Not Ready STEVEN BACK
Smoke Detectors 4/1/2024 Approved STEVEN BACK
Final 5/20/2024 Not Ready for Inspection STEVEN BACK
Green Building Final 5/20/2024 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 5/20/2024 SGSOV Not Required STEVEN BACK
Final 5/24/2024 OK to Issue CofO STEVEN BACK