6902 N WILBUR AVE 91335
Certificate Information: 6902 N WILBUR AVE 91335
- Application / Permit
- 23010-20000-00127
- Plan Check / Job No.
- B23VN00321
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 20' X 29'-6" TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 5/2/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2023 | SELLA BENYAMIN |
| Corrections Issued | 2/23/2023 | SELLA BENYAMIN |
| Quality Review Completed | 2/24/2023 | STEVEN KIM |
| Building Plans Picked Up | 2/28/2023 | APPLICANT |
| Applicant returned to address corrections | 3/7/2024 | SELLA BENYAMIN |
| Plan Check Approved | 5/2/2024 | SELLA BENYAMIN |
| Issued | 5/2/2024 | APPLICANT |
| CofO in Progress | 4/14/2026 | ARUTYUN MADATYAN |
| Permit Finaled | 4/30/2026 | JOHN JANSON |
| CofO Issued | 4/30/2026 | JOHN JANSON |
| Permit Finaled | 4/30/2026 | JOHN JANSON |
Permit Application Clearance Information
| ZI | Cleared | 3/23/2023 | STEVEN WECHSLER |
| Address approval | Cleared | 3/30/2023 | FERNANDO GIL |
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2023 | FERNANDO GIL |
| Sewer availability | Cleared | 3/30/2023 | FERNANDO GIL |
| Stormwater Pollution Mitigatn | Cleared | 1/22/2024 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 2/20/2024 | BRYAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lee,, Richard C C; Lic. No.: S1371 | 19321 VANOWEN ST RESEDA, CA 91335 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/3/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 7/3/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Grading Pre-Inspection | 7/3/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 7/3/2024 | Partial Approval | ARUTYUN MADATYAN |
| Excavation/Setback/Form/Re-Bar | 7/8/2024 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2024 | Partial Approval | JEFFREY BULL |
| Green Building Rough | 7/16/2024 | Not Ready for Inspection | JEFFREY BULL |
| Verify Sprinkler Sign Off | 7/16/2024 | Approved | JEFFREY BULL |
| Deputy Wood Construction | 7/31/2024 | Approved | JEFFREY BULL |
| Rough-Elec/Plmb/HVAC | 8/28/2024 | Approved | JEFFREY BULL |
| Insulation | 9/9/2024 | Not Ready for Inspection | JEFFREY BULL |
| Interior/Exterior Lathing | 9/9/2024 | Partial Approval | JEFFREY BULL |
| Insulation | 9/25/2024 | Approved | JEFFREY BULL |
| Drywall Nailing | 10/3/2024 | Approved | JEFFREY BULL |
| ELECTRICAL-Final | 8/12/2025 | Corrections Issued | JUAN ALVARADO |
| ELECTRICAL-Final | 8/19/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Service/Power Release | 8/19/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 10/16/2025 | Approved | ARUTYUN MADATYAN |
| Final | 10/16/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 10/16/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Final | 10/16/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Green Building Rough | 10/16/2025 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 10/16/2025 | SGSOV Approved | ARUTYUN MADATYAN |
| Service/Power Release | 10/16/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Smoke Detectors | 10/16/2025 | Approved | ARUTYUN MADATYAN |
| Service/Power Release | 12/5/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 2/27/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Green Building Final | 2/27/2026 | Approved | ARUTYUN MADATYAN |
| Service/Power Release | 2/27/2026 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 4/13/2026 | Approved | ARUTYUN MADATYAN |
| Final | 4/13/2026 | OK to Issue CofO | ARUTYUN MADATYAN |
| HVAC-Final | 4/13/2026 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 4/13/2026 | Approved | ARUTYUN MADATYAN |
| Service/Power Release | 4/13/2026 | Approved | ARUTYUN MADATYAN |