12269 W MONTAGUE ST 91331
Certificate Information: 12269 W MONTAGUE ST 91331
- Application / Permit
- 23010-20000-00105
- Plan Check / Job No.
- B23VN00259
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (7) Carport
- Work Description
- NEW 26'-3" X 146'-3" SOLAR PANEL ROOFED CARPORT AT (E) OPEN PARKING STALLS
- Permit Issued
- Issued on 9/5/2023
- Issuing Office
- Current Status
- CofO Issued on 6/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/9/2023 | RAPHAEL ROSAS |
| Corrections Issued | 2/17/2023 | RAPHAEL ROSAS |
| Quality Review Completed | 2/24/2023 | STEVEN KIM |
| Disabled Access Plans Picked Up | 3/1/2023 | APPLICANT |
| Building Plans Picked Up | 4/4/2023 | APPLICANT |
| Applicant returned to address corrections | 4/14/2023 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 5/4/2023 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 6/7/2023 | RAPHAEL ROSAS |
| Plan Check Approved | 9/5/2023 | RAPHAEL ROSAS |
| Issued | 9/5/2023 | APPLICANT |
| CofO in Progress | 6/7/2024 | JEFFREY DURAN |
| Permit Finaled | 6/7/2024 | JEFFREY DURAN |
| CofO Issued | 6/7/2024 | JEFFREY DURAN |
| Permit Finaled | 6/7/2024 | JEFFREY DURAN |
Permit Application Clearance Information
| Stormwater Pollution Mitigatn | Cleared | 5/2/2023 | MARTIN FRAGOSO |
| "Q" conditions | Cleared | 5/16/2023 | NELSON RODRIGUEZ |
| Clean Up Green Up | Cleared | 5/16/2023 | NELSON RODRIGUEZ |
| ZA Case | Cleared | 5/16/2023 | NELSON RODRIGUEZ |
| ZI | Cleared | 5/16/2023 | NELSON RODRIGUEZ |
| DAS Clearance | Cleared | 6/6/2023 | RAPHAEL ROSAS |
| Roof/Waste drainage to street | Cleared | 6/14/2023 | FERNANDO GIL |
| Eng Process Fee Ord 176,300 | Cleared | 6/15/2023 | FERNANDO GIL |
| "T" removal | Cleared | 6/29/2023 | NATHAN ROMINE |
| Hydrant and Access approval | Cleared | 8/31/2023 | GILBERT URREA |
Contact Information
| Contractor | La Solar Group Inc; Lic. No.: 974115-C46 | 520 LIBRARY ST SAN FERNANDO, CA 91340 |
| Engineer | Vinci,, James Richard; Lic. No.: S4411 | 175 E WILBUR ROAD STE 103 THOUSAND OAKS, CA 91360 |
Inspector Information
| JOHN KITCKO, (818) 374-1109 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/4/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Pre-Inspection | 10/4/2023 | Partial Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 10/11/2023 | Corrections Issued | DANNY RODRIGUEZ |
| Pre-Inspection | 10/11/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Final | 10/14/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 10/14/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 10/14/2023 | SGSOV Not Ready | DANNY RODRIGUEZ |
| Smoke Detectors | 10/14/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 10/14/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 11/2/2023 | Partial Approval | DANNY RODRIGUEZ |
| Posting Pre-Inspection | 11/22/2023 | Corrections Issued | GREGORY POMISH |
| Pre-Inspection | 11/29/2023 | Corrections Issued | DEANDRE HOFFMAN |
| Final | 12/22/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 12/22/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 12/22/2023 | SGSOV Not Ready | DANNY RODRIGUEZ |
| Smoke Detectors | 12/22/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 12/22/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Light Gage Steel Frame | 3/8/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Final | 3/13/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 3/13/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 3/13/2024 | SGSOV Not Ready | DANNY RODRIGUEZ |
| Smoke Detectors | 3/13/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 3/13/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Final | 3/20/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 3/20/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 3/20/2024 | SGSOV Not Ready | DANNY RODRIGUEZ |
| Smoke Detectors | 3/20/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 3/20/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 3/26/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 3/26/2024 | SGSOV Not Ready | DANNY RODRIGUEZ |
| Smoke Detectors | 3/26/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 3/26/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Special/Order Compliance | 3/27/2024 | Corrections Issued | DANNY RODRIGUEZ |
| Final | 4/3/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 4/3/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 4/3/2024 | SGSOV Not Ready | DANNY RODRIGUEZ |
| Smoke Detectors | 4/3/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 4/3/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Final | 4/22/2024 | Partial Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 4/22/2024 | Approved | DANNY RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 4/22/2024 | SGSOV No Gas | DANNY RODRIGUEZ |
| Smoke Detectors | 4/22/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Wood Frame | 4/22/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Final | 4/26/2024 | Partial Inspection | DANNY RODRIGUEZ |
| Smoke Detectors | 4/26/2024 | Approved | DANNY RODRIGUEZ |
| Wood Frame | 4/26/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Final | 6/7/2024 | OK to Issue CofO | JEFFREY DURAN |
| Wood Frame | 6/7/2024 | Approved | JEFFREY DURAN |