11949 W RUNNYMEDE ST 91605
Certificate Information: 11949 W RUNNYMEDE ST 91605
- Application / Permit
- 23010-20000-00077
- Plan Check / Job No.
- B22VN17423
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 1-STORY ADU (403 SQFT) PER CA GOVT. CODE 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d)(g)
- Permit Issued
- Issued on 7/25/2023
- Issuing Office
- Current Status
- CofO Issued on 8/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/5/2023 | PETER MOSESIAN |
| Corrections Issued | 1/7/2023 | PETER MOSESIAN |
| Quality Review Completed | 1/12/2023 | OMID HEDAYAT |
| Plan Check Approved | 4/5/2023 | PETER MOSESIAN |
| Issued | 7/25/2023 | APPLICANT |
| CofO in Progress | 8/12/2024 | JUAN VALENZUELA |
| Permit Finaled | 8/19/2024 | DANIEL ORRANTE |
| CofO Issued | 8/19/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/19/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 2/9/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/9/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/9/2023 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 2/10/2023 | KURT CORRAL |
Contact Information
| Contractor | Sauer Paul Construction; Lic. No.: 1079869-B | , |
| Engineer | Zohrevand,, Pedram; Lic. No.: C82328 | 19562 VENTURA BLVD UNIT 238 TARZANA, CA 91356 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/15/2023 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 8/15/2023 | Not Ready for Inspection | JOHN HAYES |
| METHANE-Barrier | 8/15/2023 | Approved | JOHN HAYES |
| METHANE-Subgrade | 8/15/2023 | Not Ready for Inspection | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 10/25/2023 | Approved | MISAEL ESPARZA |
| Footing/Foundation/Slab | 10/25/2023 | Approved | MISAEL ESPARZA |
| METHANE-Subgrade | 10/25/2023 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 1/5/2024 | Not Ready for Inspection | ROBERT GOLD |
| HVAC-Rough | 1/5/2024 | Not Ready for Inspection | ROBERT GOLD |
| Insulation | 1/5/2024 | Corrections Issued | ROBERT GOLD |
| PLUMBING-Rough | 1/5/2024 | Not Ready for Inspection | ROBERT GOLD |
| Wood Frame | 1/5/2024 | Corrections Issued | ROBERT GOLD |
| Rough-Elec/Plmb/HVAC | 2/15/2024 | Approved | DAVID ANDERSON |
| Insulation | 2/20/2024 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 2/20/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Wood Frame | 2/22/2024 | Approved | JOHN HAYES |
| Drywall Nailing | 2/23/2024 | Approved | JOHN HAYES |
| Green Building Rough | 2/23/2024 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 2/23/2024 | Approved | JOHN HAYES |
| Shower Pan | 2/23/2024 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 5/30/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 5/30/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 5/30/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 5/30/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 5/30/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| METHANE-Final | 5/30/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| METHANE-Rough | 5/30/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 5/30/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 5/30/2024 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 5/30/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 5/30/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 5/30/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 6/12/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 6/12/2024 | Not Ready for Inspection | JOSE AVILA |
| Final | 6/12/2024 | Not Ready for Inspection | JOSE AVILA |
| Green Building Final | 6/12/2024 | Not Ready for Inspection | JOSE AVILA |
| HVAC-Final | 6/12/2024 | Not Ready for Inspection | JOSE AVILA |
| Service/Power Release | 6/12/2024 | Not Ready for Inspection | JOSE AVILA |
| Wood Frame | 6/12/2024 | Not Ready for Inspection | JOSE AVILA |
| Pre-Inspection | 6/20/2024 | Partial Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 8/8/2024 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 8/8/2024 | Approved | JUAN VALENZUELA |
| Final | 8/8/2024 | OK to Issue CofO | JUAN VALENZUELA |
| Green Building Final | 8/8/2024 | Approved | JUAN VALENZUELA |
| HVAC-Final | 8/8/2024 | Approved | JUAN VALENZUELA |
| Service/Power Release | 8/8/2024 | Approved | JUAN VALENZUELA |