343-345 W 46TH ST 90037

Certificate Information: 343-345 W 46TH ST 90037

Application / Permit
23010-20000-00074
Plan Check / Job No.
B23VN00180
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ePlan New (4) Story Duplex with attached 4-Car Garage
Permit Issued
Issued on 1/10/2024
Issuing Office
Current Status
CofO Issued on 8/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/12/2023 APPLICANT
Assigned to Plan Check Engineer 2/16/2023 ARSALAN SHABESTARI
Corrections Issued 2/23/2023 ARSALAN SHABESTARI
Quality Review Completed 3/10/2023 GARO TELMI
Plan Check Approved 10/18/2023 ARSALAN SHABESTARI
Issued 1/10/2024 APPLICANT
CofO in Progress 8/23/2025 ALEJANDRO DE ARTOLA
No Progress 8/24/2025 DEROLD HAUFF
CofO in Progress 8/24/2025 DEROLD HAUFF
Permit Finaled 8/28/2025 DEROLD HAUFF
Permit Finaled 8/28/2025 DEROLD HAUFF
CofO Issued 8/28/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/26/2023 ADRIAN SANCHEZ
SB8 RUD Cleared 6/14/2023 JULIE LIEU
Highway dedication Cleared 6/17/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 6/21/2023 TREVOR QUAN
Sewer availability Cleared 6/21/2023 TREVOR QUAN
Hydrant and Access approval Cleared 8/21/2023 LAVEON RIDER
Low Impact Development (LID) Cleared 8/21/2023 VICTOR MENDOZA
Roof/Waste drainage to street Cleared 8/23/2023 ADRIAN SANCHEZ

Contact Information

Contractor F S Z Bros General Contractors Inc; Lic. No.: 794097-B       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/17/2024 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 5/30/2024 Partial Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 6/20/2024 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 6/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 7/3/2024 Approved CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 7/24/2024 Corrections Issued MICHAEL LEWIS
Deputy Wood Construction 7/26/2024 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/30/2024 Partial Approval ALEJANDRO DE ARTOLA
Deputy Wood Construction 7/31/2024 Conditional Approval ALEX COLIN
Floor/Roof Diaphrgm/Shear Wall 8/5/2024 Partial Approval ALEJANDRO DE ARTOLA
Pre-Inspection 8/6/2024 Approved ALEJANDRO DE ARTOLA
Deputy Wood Construction 8/9/2024 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 8/9/2024 Partial Approval MICHAEL LEWIS
PLUMBING-Rough 10/4/2024 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/29/2024 Partial Approval MICHAEL LEWIS
HVAC-Rough 10/29/2024 Not Ready for Inspection MICHAEL LEWIS
ELECTRICAL-Rough 10/30/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 10/31/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 11/7/2024 Corrections Issued CRAIG DAVIS
BUILDING-Rough-Frame 11/8/2024 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/8/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 11/8/2024 Corrections Issued ALEJANDRO DE ARTOLA
MERV13>=Rough 11/8/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 11/12/2024 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/14/2024 Corrections Issued CRAIG DAVIS
HVAC-Rough 11/14/2024 Corrections Issued CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 11/21/2024 Approved SABAS ALONSO
HVAC-Rough 11/21/2024 Approved SABAS ALONSO
BUILDING-Rough-Frame 11/25/2024 Corrections Issued SABAS ALONSO
Green Building Rough 11/25/2024 Approved SABAS ALONSO
PLUMBING-Rough 11/25/2024 Approved SABAS ALONSO
Verify Sprinkler Sign Off 11/25/2024 Approved SABAS ALONSO
BUILDING-Rough-Frame 12/4/2024 Approved ALEJANDRO DE ARTOLA
Insulation 12/4/2024 Corrections Issued ALEJANDRO DE ARTOLA
Wood Frame 12/4/2024 Approved ALEJANDRO DE ARTOLA
Insulation 12/9/2024 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 12/9/2024 Partial Approval ALEJANDRO DE ARTOLA
Insulation 12/11/2024 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 12/11/2024 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 12/24/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 1/15/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 4/2/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 4/24/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 4/24/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 4/30/2025 Approved ALEJANDRO DE ARTOLA
Gas Test 4/30/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 4/30/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 4/30/2025 Approved ALEJANDRO DE ARTOLA
Gas Test 5/1/2025 Approved ALEJANDRO DE ARTOLA
Green Building Final 5/1/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Final 5/1/2025 Approved ALEJANDRO DE ARTOLA
Service/Power Release 6/27/2025 Approved ALEJANDRO DE ARTOLA
Final 8/4/2025 Corrections Issued ALEJANDRO DE ARTOLA
MERV13>=Final 8/4/2025 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 8/4/2025 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 8/4/2025 Approved ALEJANDRO DE ARTOLA
Final 8/11/2025 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 8/11/2025 SGSOV Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 8/12/2025 Approved ALEJANDRO DE ARTOLA
Final 8/13/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 8/22/2025 Approved ALEJANDRO DE ARTOLA
Final 8/22/2025 OK to Issue CofO ALEJANDRO DE ARTOLA