343-345 W 46TH ST 90037
Certificate Information: 343-345 W 46TH ST 90037
- Application / Permit
- 23010-20000-00074
- Plan Check / Job No.
- B23VN00180
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePlan New (4) Story Duplex with attached 4-Car Garage
- Permit Issued
- Issued on 1/10/2024
- Issuing Office
- Current Status
- CofO Issued on 8/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2023 | ARSALAN SHABESTARI |
| Corrections Issued | 2/23/2023 | ARSALAN SHABESTARI |
| Quality Review Completed | 3/10/2023 | GARO TELMI |
| Plan Check Approved | 10/18/2023 | ARSALAN SHABESTARI |
| Issued | 1/10/2024 | APPLICANT |
| CofO in Progress | 8/23/2025 | ALEJANDRO DE ARTOLA |
| No Progress | 8/24/2025 | DEROLD HAUFF |
| CofO in Progress | 8/24/2025 | DEROLD HAUFF |
| Permit Finaled | 8/28/2025 | DEROLD HAUFF |
| Permit Finaled | 8/28/2025 | DEROLD HAUFF |
| CofO Issued | 8/28/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/26/2023 | ADRIAN SANCHEZ |
| SB8 RUD | Cleared | 6/14/2023 | JULIE LIEU |
| Highway dedication | Cleared | 6/17/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/21/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 6/21/2023 | TREVOR QUAN |
| Hydrant and Access approval | Cleared | 8/21/2023 | LAVEON RIDER |
| Low Impact Development (LID) | Cleared | 8/21/2023 | VICTOR MENDOZA |
| Roof/Waste drainage to street | Cleared | 8/23/2023 | ADRIAN SANCHEZ |
Contact Information
| Contractor | F S Z Bros General Contractors Inc; Lic. No.: 794097-B | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/17/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 5/30/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 6/20/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 6/24/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 7/3/2024 | Approved | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2024 | Corrections Issued | MICHAEL LEWIS |
| Deputy Wood Construction | 7/26/2024 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 7/31/2024 | Conditional Approval | ALEX COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 8/6/2024 | Approved | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 8/9/2024 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2024 | Partial Approval | MICHAEL LEWIS |
| PLUMBING-Rough | 10/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2024 | Partial Approval | MICHAEL LEWIS |
| HVAC-Rough | 10/29/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| ELECTRICAL-Rough | 10/30/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/31/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 11/7/2024 | Corrections Issued | CRAIG DAVIS |
| BUILDING-Rough-Frame | 11/8/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 11/8/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| MERV13>=Rough | 11/8/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 11/12/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2024 | Corrections Issued | CRAIG DAVIS |
| HVAC-Rough | 11/14/2024 | Corrections Issued | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2024 | Approved | SABAS ALONSO |
| HVAC-Rough | 11/21/2024 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 11/25/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Rough | 11/25/2024 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 11/25/2024 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 11/25/2024 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 12/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 12/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Wood Frame | 12/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 12/9/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 12/9/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 12/11/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 12/11/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 12/24/2024 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 1/15/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 4/2/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 4/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 4/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 4/30/2025 | Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 4/30/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 4/30/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 4/30/2025 | Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 5/1/2025 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 5/1/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 5/1/2025 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 6/27/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 8/4/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| MERV13>=Final | 8/4/2025 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 8/4/2025 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 8/4/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 8/11/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 8/11/2025 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/12/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 8/13/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/22/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 8/22/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |