11642 N GERALD AVE 91344
Certificate Information: 11642 N GERALD AVE 91344
- Application / Permit
- 23010-20000-00067
- Plan Check / Job No.
- B23VN00156
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan NEW 1,190 SQ. FT. 1-STORY NEW DETACHED A.D.U. IN THE REAR OF THE LOT PER LAMC
- Permit Issued
- Issued on 7/18/2023
- Issuing Office
- Current Status
- CofO Issued on 8/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2023 | WEIJIAN HUANG |
| Corrections Issued | 2/6/2023 | WEIJIAN HUANG |
| Plan Check Approved | 7/6/2023 | JOSEPH RAFOLS |
| Plan Check Approved | 7/17/2023 | JOSEPH RAFOLS |
| Issued | 7/18/2023 | APPLICANT |
| CofO in Progress | 7/23/2024 | JAVIER RAMOS JR |
| Permit Finaled | 8/7/2024 | RUBEN SALAS |
| CofO Issued | 8/7/2024 | RUBEN SALAS |
| Permit Finaled | 8/7/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/5/2023 | RIDWAN HARDY |
| Stormwater Pollution Mitigatn | Cleared | 6/9/2023 | SARAH YOUSSEF |
| Address approval | Cleared | 6/12/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 6/15/2023 | NIKKI ZULUETA |
| Roof/Waste drainage to street | Cleared | 6/28/2023 | NIKKI ZULUETA |
| GPI Written Notices | Cleared | 7/6/2023 | WEIJIAN HUANG |
| Grading Pre-Inspection | Cleared | 7/6/2023 | WEIJIAN HUANG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baraty,, Patrick; Lic. No.: S5900 | 450 NORTH BRAND BLVD STE 600 GLENDALE, CA 91203 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/24/2023 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 10/27/2023 | Conditional Approval | RAUL OLAGI |
| Special/Order Compliance | 10/27/2023 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 11/27/2023 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 11/27/2023 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 11/27/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 11/27/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 11/27/2023 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 11/27/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 11/29/2023 | Approved | JAVIER RAMOS JR |
| Insulation | 11/29/2023 | Approved | JAVIER RAMOS JR |
| Sewer | 12/19/2023 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 12/19/2023 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Final | 2/15/2024 | Approved | JAVIER RAMOS JR |
| Final | 2/15/2024 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 2/15/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 2/15/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 2/15/2024 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 2/15/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 2/22/2024 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 2/22/2024 | SGSOV Approved | JAVIER RAMOS JR |
| Gas Test | 5/10/2024 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 5/10/2024 | Approved | JAVIER RAMOS JR |
| Final | 7/23/2024 | OK to Issue CofO | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 7/23/2024 | Approved | JAVIER RAMOS JR |