18946 W INGOMAR ST 91335

Certificate Information: 18946 W INGOMAR ST 91335

Application / Permit
23010-20000-00063
Plan Check / Job No.
B23VN00154
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN (N) 2-STORY DETACHED ADU PER LAMC 12.22 A.33 (c)-(d) WITH NFPA 13D
Permit Issued
Issued on 11/25/2024
Issuing Office
Current Status
CofO Issued on 2/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/9/2023 APPLICANT
Assigned to Plan Check Engineer 1/27/2023 JOHNPAUL ISIP
Corrections Issued 1/30/2023 JOHNPAUL ISIP
Applicant returned to address corrections 10/30/2024 JOHNPAUL ISIP
Plan Check Approved 11/20/2024 JOHNPAUL ISIP
Issued 11/25/2024 APPLICANT
CofO in Progress 11/4/2025 ARUTYUN MADATYAN
Permit Finaled 2/9/2026 JOHN JANSON
CofO Issued 2/9/2026 JOHN JANSON
Permit Finaled 2/9/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/1/2023 COLIN LOREDO
Drainage to Storm Drain Cleared 2/1/2023 COLIN LOREDO
Sewer availability Cleared 2/1/2023 COLIN LOREDO
ZI Cleared 2/6/2023 DANG NGUYEN
Eng Process Fee Ord 176,300 Cleared 4/8/2023 MARKOS PEREZ-BRAN
Low Impact Development Cleared 9/27/2024 ERNEST TSE
Roof/Waste drainage to street Cleared 10/23/2024 MARKOS PEREZ-BRAN
Hydrant and Access approval Cleared 10/25/2024 JOHN CONNEALLY

Contact Information

Contractor Owner-Builder       ,
Engineer Zohrevand,, Pedram; Lic. No.: C82328 19562 VENTURA BLVD UNIT 238      TARZANA, CA 91356

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/6/2024 Partial Approval ARUTYUN MADATYAN
Excavation/Setback/Form/Re-Bar 12/13/2024 Approved ARUTYUN MADATYAN
Footing/Foundation/Slab 12/13/2024 Approved ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 1/3/2025 Corrections Issued ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 1/23/2025 Approved ARUTYUN MADATYAN
Green Building Rough 1/23/2025 Not Ready for Inspection ARUTYUN MADATYAN
Verify Sprinkler Sign Off 1/23/2025 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Rough 2/4/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 2/4/2025 Partial Approval ARUTYUN MADATYAN
PLUMBING-Rough 2/4/2025 Approved ARUTYUN MADATYAN
Verify Sprinkler Sign Off 2/4/2025 Not Ready for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 2/12/2025 Corrections Issued ARUTYUN MADATYAN
HVAC-Rough 2/12/2025 Approved ARUTYUN MADATYAN
Verify Sprinkler Sign Off 2/12/2025 Approved ARUTYUN MADATYAN
Insulation 2/14/2025 Corrections Issued JOHN COLEMAN
Shower Pan 2/27/2025 Approved JOHN KIDWELL
Drywall Nailing 3/3/2025 Approved ARUTYUN MADATYAN
Green Building Rough 3/3/2025 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 9/8/2025 Approved ARUTYUN MADATYAN
Final 9/8/2025 Corrections Issued ARUTYUN MADATYAN
Green Building Final 9/8/2025 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 9/8/2025 SGSOV Not Ready ARUTYUN MADATYAN
Service/Power Release 9/8/2025 Not Ready for Inspection ARUTYUN MADATYAN
Smoke Detectors 9/8/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 10/17/2025 Not Ready for Inspection ARUTYUN MADATYAN
Final 10/17/2025 Not Ready for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 10/17/2025 SGSOV Not Ready ARUTYUN MADATYAN
Service/Power Release 10/17/2025 Not Ready for Inspection ARUTYUN MADATYAN
Final 10/28/2025 Corrections Issued ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 10/28/2025 SGSOV Approved ARUTYUN MADATYAN
Service/Power Release 10/28/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 11/4/2025 Approved ARUTYUN MADATYAN
Final 11/4/2025 OK to Issue CofO ARUTYUN MADATYAN
HVAC-Final 11/4/2025 Approved ARUTYUN MADATYAN
PLUMBING-Final 11/4/2025 Approved ARUTYUN MADATYAN