11031 N MONOGRAM AVE 91344

Certificate Information: 11031 N MONOGRAM AVE 91344

Application / Permit
23010-20000-00040
Plan Check / Job No.
B23VN00073
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: (N) 1-STORY SINGLE FAMILY DWELLING PER SB9 TWO UNIT DEVELOPMENT
Permit Issued
Issued on 7/13/2023
Issuing Office
Current Status
CofO Issued on 3/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/7/2023 APPLICANT
Assigned to Plan Check Engineer 2/13/2023 DANIEL YIP
Corrections Issued 2/13/2023 DANIEL YIP
Quality Review Completed 2/14/2023 GARO TELMI
Plan Check Approved 7/13/2023 DANIEL YIP
Issued 7/13/2023 APPLICANT
CofO in Progress 12/18/2023 JAVIER RAMOS JR
No Progress 2/14/2024 ROBERT GOLD
CofO in Progress 2/14/2024 ROBERT GOLD
CofO in Progress 3/4/2024 ROBERT GOLD
No Progress 3/4/2024 ROBERT GOLD
CofO in Progress 3/4/2024 ROBERT GOLD
Permit Finaled 3/4/2024 RUBEN SALAS
CofO Issued 3/4/2024 RUBEN SALAS
Permit Finaled 3/4/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/1/2023 ROMAN GUTIERREZ
Hydrant and Access approval Cleared 4/7/2023 RUEL COLE
Sewer availability Cleared 4/25/2023 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 6/29/2023 NIKKI ZULUETA
Roof/Waste drainage to street Cleared 6/29/2023 NIKKI ZULUETA
Stormwater Pollution Mitigatn Cleared 6/29/2023 LUIS LUVANO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/1/2023 Partial Approval JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 8/7/2023 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 9/7/2023 Approved JAVIER RAMOS JR
HVAC-Rough 9/7/2023 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 9/7/2023 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 9/18/2023 Approved JAVIER RAMOS JR
HVAC-Rough 9/18/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 9/18/2023 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 9/18/2023 Partial Inspection JAVIER RAMOS JR
Insulation 9/25/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 9/25/2023 Approved JAVIER RAMOS JR
PLUMBING-Rough 9/25/2023 Approved JAVIER RAMOS JR
Shower Pan 9/25/2023 Approved JAVIER RAMOS JR
Wood Frame 9/25/2023 Approved JAVIER RAMOS JR
Drywall Nailing 9/28/2023 Approved JAVIER RAMOS JR
Green Building Rough 9/28/2023 Approved JAVIER RAMOS JR
Sewer 11/6/2023 Approved JAVIER RAMOS JR
Underground Mechanical 11/6/2023 Partial Approval JAVIER RAMOS JR
Underground Mechanical 11/9/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 12/7/2023 Approved JAVIER RAMOS JR
ELECTRICAL-Final 12/7/2023 Approved JAVIER RAMOS JR
Final 12/7/2023 OK to Issue CofO JAVIER RAMOS JR
Footing/Foundation/Slab 12/7/2023 Approved JAVIER RAMOS JR
Green Building Final 12/7/2023 Approved JAVIER RAMOS JR
MERV13>=Final 12/7/2023 Approved JAVIER RAMOS JR
MERV13>=Rough 12/7/2023 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 12/7/2023 SGSOV Not Required JAVIER RAMOS JR
Service/Power Release 12/7/2023 Approved JAVIER RAMOS JR
Smoke Detectors 12/7/2023 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 12/7/2023 Approved JAVIER RAMOS JR
Final 2/14/2024 Corrections Issued ROBERT GOLD
Pre-Inspection 2/15/2024 Approved JAVIER RAMOS JR
Special/Order Compliance 2/15/2024 Approved JAVIER RAMOS JR
Pre-Inspection 2/27/2024 Approved JOHN COLEMAN